Dispute over extent of hail damage and whether the roof needs full replacement rather than cash settlement for damaged sheets

FirmSuncorp Group
Decided2025-07-28
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$693
Non-financial loss$1,000
Amount claimed$65,749
SourceAFCA PDF

Summary

The complainant sought $65,748.62 for full roof replacement after hail damage; the insurer cash settled repairs of damaged sheets. AFCA found the settlement correct but ordered a 15% contingency uplift of $693.23 and $1,000 compensation for delays.

The policy limits liability to damaged parts and expert evidence showed limited hail damage below the 20% threshold, but the cash settlement omitted a contingency for transfer of risk and handling was delayed.

Issues

Subjects and remedies

home or building damagenatural disasterpay claimpay non financial loss

Related

All Suncorp Group determinations · Find similar determinations

Text of the determination

Determination | Case number | 12-24-115462 | Financial firm | AAI Limited Case number: 12-24-115462 18 June 2025 Determination overview Complaint The complainant lodged a claim with the financial firm (insurer) under her home insurance policy. This is for the damage sustained to the roof as a result of a storm event. The complainant is represented by (CO). For simplicity, I will refer to the complainant and CO as the ‘complainant’. The insurer accepted the internal water damage and partially accepted hail damage to the roof. The insurer says the hail indentation is minimal and could be rectified. The insurer cash settled the complainant $18,615.84 less the applicable policy excess. The complainant is dissatisfied with the settlement and says the extent of the hail damage exceeds 20% of the roof and therefore, according to the relevant building guidelines, the roof requires full replacement. The complainant is seeking $65,748.62 for the full replacement of the roof. Issues and key findings Is the insurer’s roof settlement fair in all the circumstances? The insurer has correctly settled the complainant for the roof repairs in line with the policy’s terms and conditions. However, the insurer is required to add a 15% contingency for the transfer of risk. Is the insurer liable for compensation? The insurer is required to pay the complainant $1,000 compensation. Why is the outcome fair? The parties are bound by the terms and conditions of the policy. The complainant did not establish a loss beyond the insurer’s settlement. The insurer has correctly settled the complainant for the damage sustained to the roof as a result of the hail event. Determination This determination is substantially in favour of the insurer. Within 14 days of receiving notification, the complainant accepts this determination; the insurer is required to pay the complainant: an uplift of 15% of the settlement as a contingency payment totalling $693.23 $1,000 non-financial loss compensation. Once the insurer issues the payment, it is not required to take any further action regarding the claim. Reasons for determination Is the insurer’s roof settlement fair in the circumstances? The insurer has correctly settled the complainant for the roof repairs in line with the policy’s terms and conditions. However, the insurer is required to add a 15% contingency for the transfer of risk. The parties dispute the extent of the roof damage There is no dispute: there was a storm event the insurer accepted internal water damage the insurer accepted there is hail damage to the roof. In saying that, the parties disagree on the extent of the insurer’s liability for the roof damage. The complainant is not disputing the scope of work for the internal damage. The complainant seeks a full roof replacement whereas the insurer seeks to limit its liability to only the affected roof sheets as a result of hail. The complainant is seeking $65,748.62 for the full roof replacement. The insurer says it is only liable for the damaged parts of the property, and its liability does not extend to the undamaged parts of the property, including the undamaged roof sheeting. The insurer estimated the repairs to the roof as $4,621.54 and accordingly issued a cash settlement to the complainant. The policy outlines how a claim should be settled The full details of the policy coverage, conditions, limitations, and exclusions are contained within the Product Disclosure Statement (PDS) and Certificate of Insurance (COI). It is not disputed that the PDS and COI have been provided to the complainant. Therefore, the insurer is entitled to rely upon the terms of the policy, including its conditions, limitations, and exclusions, to determine its obligations to the complainant. The complainant’s policy states the insurer will only repair or rebuild the parts that are damaged in the incident covered by the policy. Further, the policy states the insurer does not cover the replacement of the undamaged parts of the property. The policy then elaborates on different circumstances where the insurer will only limit its liability to the damaged parts. Amongst the circumstances the policy provides is when roof sheeting is damaged. The policy clearly states that the insurer will only replace the damaged roof sheeting and not the undamaged roof sheeting. Parties dispute the extent of the hail damage and the required rectification The complainant’s main argument is that the hail damage is affecting 33% of the roof. The complainant says the Queensland Building and Construction Commission (QBCC) guidelines state that if the damage to the roof exceeds 20% of the roof, a full replacement is required for compliance. The complainant’s builder (AC) says the main roof sustained significant hail damage. AC says approximately 33% of the roof was damaged as a result of the golf ball sized hail. AC says there are significant indentations that have the potential to accumulate dust, dirt and water which will result in rust. AC says this will affect the structural integrity of the roof and a full roof replacement is required. The insurer’s builder (AB) observed internal water damage. AB recommended a roof report. The insurer’s roofer (LV) noted hail damage on the rear left side of the lower roof. LV noted that two sheets showed signs of damage. In addition to the two sheets, LV noted three indentations to the ridge cap to the front lower roof and minor damage to the whirly bird. LV also noted impact damage to the second storey’s roof caused by tools when removing nail fixing and replacing them with screws. In his report, the insurer’s engineer (KM) says: the roof sheeting on the front single story is deteriorated with surface corrosion evidence throughout the roof sheeting to the lower roof is reaching the end of its serviceable life there is a section of the roof where the sheet has holes from corrosion there are a total of two dents to the roof sheeting and two dents to the ridge capping which are related to hail. KM also noted hail damage to the skylight and multiple whirly birds located on different roofs on the property. KM confirmed that the roof sheets can be replaced in separate sections, and the roof does not need to be lifted and/or replaced to repair the hail damage. This is given the battens are in good condition. There is no persuasive evidence the battens are not in good condition. The complainant disagrees with KM’s assessment and says that the engineer did not utilise the chalking method when carrying out its inspection. Importantly, the complainant does not dispute that the roof is corroded and is over 70 years old, where corrosion is expected to occur. No persuasive evidence that roof replacement is warranted I have carefully considered the exchanged evidence and the parties’ arguments. I am not satisfied that the complainant has established that the hail damaged roof sheets cannot be replaced successfully or that the roof requires full replacement. Firstly, I do not find AC’s assessment to be conclusive. In his report, AC does not explain the basis of his conclusion that 33% of the roof was hail damaged. I note LV’s, AB’s and KM’s findings are consistent. While KM has noted additional indentations, he remains consistent with the other experts regarding the limited hail damage. In his report, AC noted the damaged roof sheets as ‘20/84’. I am not satisfied that this figure equates to 33% of the roof being damaged. I note AC did not provide any plausible explanation, substantiating this figure. The photographs included in AC’s report do not conclusively establish the extent of the damage. This includes the mud map which does not clearly show the extent of the hail indentation as AC describes. There is no persuasive evidence that the hail damage is sporadic in nature as the complainant asserts. Further, AC did not provide any persuasive evidence to refute KM’s and AB’s findings, including KM’s reference to the extent of the pre-existing damage and that the roof is past its serviceable lifetime. I am not satisfied that AC’s findings are consistent with the rest of the available evidence. I find KM conclusive, persuasive and logical in his assessment and findings. Secondly, the policy restricts the insurer’s liability to damaged parts and not undamaged parts. In this instance, the insurer is only liable for the damaged sections of the roof. This is the extent of the insurer’s liability under its contractual agreement with the complainant. KM says the roof material is available, and the damaged sheets can be replaced successfully. Thirdly, I acknowledge the QBCC guidelines. While the exchanged evidence does not assist the complainant in establishing that 20% of the roof is hail damaged, I will provide the following comments for completion. KM estimated the hail damage to the roof as 3%, being 2 roof sheets out of 70 sheets. I note AB’s quote factors in the replacement of 10 roof sheets. Even if the insurer is required to replace 10 sheets, I accept the number of sheets to be replaced is still below the 20% threshold. Further, the complainant did not provide persuasive evidence to show the non-compliance of the proposed repairs in light of KM’s findings. In other words, there is no persuasive evidence: the replacement of the roof sheets compromises the structural integrity of the roof the property would be an unacceptable insurable risk there is screw hole misalignment. Lastly, I acknowledge the complainants’ arguments. Amongst other things, the complainant says: the insurer approved roof replacements for other claims the insurer’s assessment failed to use the chalking method. I do not accept the insurers’ decisions to replace roofs under other claims is binding. In other words, an insurer is entitled to assess each claim based on its own merits. Further, the findings of the insurer’s experts are consistent despite different assessment methods. Considering the evidence as a whole, I am not satisfied that the complainant has established that the extent of the hail damage to the roof, deems it irreparable. The insurer is required to factor contingency in its cash settlement The exchanged evidence shows the insurer cash settled the complainant for the roof repairs based on AB’s quote and KM’s assessment totalling $4,621.54. There is no dispute the complainant opted for a cash settlement for her repairer to undertake the repairs. When an insurer undertakes the repairs to the insured property, it warrants the workmanship of its repairs. Further, by cash settling the claim, the insurer transfers the risk of any additional works. I note the cash settlement has failed to factor in a contingency uplift for the transfer of risk. Within 14 days of receiving notification the complainant accepts this determination, the insurer is required to pay the complainant an uplift of 15% of the settlement as a contingency payment totalling $693.23. Once the insurer issues the payment, it is not required to take any further action regarding the storm damage. Is the insurer liable for compensation? The insurer is required to pay the complainant $1,000 compensation. AFCA may award compensation for non-financial loss AFCA may award compensation for non-financial loss if there has been an unusual degree or extent of physical inconvenience, time taken to resolve a complaint or interference with the complainant’s expectation of enjoyment or peace of mind. AFCA takes a conservative approach to awarding compensation. We do not award compensation because the complainant has suffered some inconvenience and delays. AFCA expects complainants to be moderately robust and to bear the normal degree of inconvenience experienced when a problem occurs and to take reasonable steps to manage the situation. The complainant is dissatisfied with the insurer’s handling of the claim and that the insurer has breached the General Insurance Code of Practice (GICOP). Amongst other things, the complainant says the insurer failed to: address the complainant’s concerns in a timely manner respond to the complainant’s queries regarding the progress of the claim explain the cash settlement basis issue a claim decision in a timely manner assess the claim proactively. The insurer is required to pay the complainant $1,000 compensation I have carefully considered the exchanged evidence, including the complainant’s chronology of events. I accept the insurer handled the claim reasonably overall. The insurer organised several assessments throughout the life of the claim to establish the extent of its liability. Further, I accept the insurer continued to accommodate the complainant’s concerns, resulting in these numerous assessments. Further, having reviewed the insurer’s claim notes, I note that the insurer’s asbestos assessor attended the insured property unannounced to the complainant and the assessment was rescheduled. Further, the claim notes show that the insurer did not provide timely updates to the complainant and that most of the contact was initiated by the complainant. Further, I accept the insurer unreasonably delayed the settlement of the internal damage despite this damage not being in dispute. The insurer acknowledged some delays following the internal assessment reports. I also accept there were delays in appointing KM. I acknowledge the complainant’s reference to different sections of the GICOP. The GICOP can only be considered to the extent compensation would be warranted. I accept the insurer could have handled the claim better. Accordingly, I accept the insurer is required to pay the complainant $1,000 compensation for the delays and inconvenience. Why is the outcome fair? The parties are bound by the terms and conditions of the policy. The complainant did not establish a loss beyond the insurer’s settlement. The insurer has correctly settled the complainant for the damage sustained to the roof as a result of the hail event Supporting information The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to: the legal principles applicable industry codes or guidance good industry practice previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all the information the parties have provided. While the parties have raised several issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider: available documents the recollections of the parties all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.