Summary

Complainant claimed rectification of water ingress in his garage ceiling said to stem from earlier storm repairs. AFCA found for the insurer, finding the cracked ridge pointing was not caused by the storm or repairs, and that its offer to repair the ceiling with excess waived was fair.

The complainant bore the onus of showing a claimable loss caused by an insured event or the insurer's repairs and provided no expert evidence, while the insurer's builder reports showed the damaged pointing was original.

Issues

Subjects and remedies

home or building damagenatural disasterno remedy

Related

All Youi determinations · Find similar determinations

Text of the determination

Determination | Case number | 12-24-114140 | Financial firm | Youi Pty Ltd Case number: 12-24-114140 22 August 2025 1 Determination overview 1.1 Complaint The complainant holds a home and contents policy with the financial firm (the insurer). On 2 November 2020, he lodged a claim with the insurer for damage to his property following a storm on 31 October 2020. The insurer accepted the claim and repaired the property. In April 2024, the complainant says that further water ingress was observed in the garage, and he says that it relates to the previous repairs or from the insured event. The insurer has denied the claim and says that the damage is not caused by the original event or subsequent repairs. The insurer has offered to repair the damage under a previously withdrawn claim and offered to waive the $950 excess to undertake the ceiling repairs. The complainant disputes this and wants the insurer to undertake rectification repairs. He also seeks compensation for the undue stress and inconvenience caused by the insurer’s claims handling. 1.2 Issues and key findings Is the insurer required to undertake rectification repairs? No. The complainant has not shown that the damage to the ridge cap pointing is from the previous insured event or the insurer’s repairs. The insurer is therefore not required to undertake rectification repairs. However, the insurer’s offer to repair the damage to the garage ceiling under its previously closed claim with a waiver of the excess is fair and reasonable. Is the complainant entitled to non-financial loss compensation? No. I am satisfied that the insurer has appropriately managed the claim and no compensation is warranted. Why is the outcome fair? The outcome is fair as it reflects the insurer’s liability which does not extend to repairs as rectification but rather under a new claim for damage to the garage ceiling only. 1.3 Determination This determination is in favour of the insurer. Should the complainant accept the determination, the insurer is to: · reopen the previously closed claim and within 21 days of being advised that the complainant has completed repairs to the ridge cap pointing, appoint a builder to conduct repairs to the garage ceiling and to include the removal of debris within the ceiling cavity as part of the previous claim · should the complainant elect, the insurer can cash settle the complainant in the sum of $4,584.46 based on the quote from OS and includes a 20% uplift for contingencies and loss of lifetime guarantee. 2 Reasons for determination 2.1 Is the insurer required to undertake rectification repairs? No. The complainant has not shown that the damage to the ridge cap pointing is from the previous insured event or the insurer’s repairs. The insurer is therefore not required to undertake rectification repairs. However, the insurer’s offer to repair the damage to the garage ceiling under its previously closed claim with a waiver of the excess is fair and reasonable. Complainant bears the onus of establishing a claimable loss The complainant is required to show, on the balance of probabilities (that is more likely than not), that he suffered a claimable loss under the policy. This means that he must show the loss was caused by a risk for which he is insured. Once the complainant, on balance, establishes a claimable loss, the insurer is liable for the loss unless it shows an exclusion or limiting condition applies. The insurer has the onus of proving, on balance, the application of the exclusion or condition. There is no dispute that the complainant received a copy of the insurer’s policy documents. The insurer is therefore entitled to rely on the policy terms and conditions in assessing the claim. The policy covers several insured events subject to limits, conditions and exclusions as set out in the policy, including the listed event of ‘Storm’. There is no dispute that a storm occurred on 31 October 2020, and the property sustained hail damage, with water entering the property. The insurer accepted the claim for damage and repaired the property. The repairs were completed in November 2021. The repairs included repairs to damaged roof tiles and internal repairs because of water ingress into several rooms, including the garage. The complainant contacted the insurer after noticing water damage to the garage ceiling in March 2024. He says that this damage relates to the previous insured event and/or the repairs undertaken by the insurer. He says that the damage is in the vicinity of the previous damage that he had reported in October 2021. The complainant also claimed that there was additional damage to the study. However, he is no longer pursuing this aspect of the claim. The policy provides a lifetime guarantee on the quality of workmanship and materials authorised and paid directly by the insurer, including rectification of inadequate repairs. Insurer obtained expert reports The insurer engaged the original builder, OS to inspect the property and assess the damage and confirm whether there were any works requiring rectification. OS inspected the property on 11 April 2024. OS observed new water damage to the plasterboard ceilings of the garage. OS says that following an inspection of the roof, it identified cracked pointing to the ridge capping tiles located directed above the water damaged area. OS found that the water ingress has occurred during the recent rain event causing damage to the insulation and plasterboard ceiling. OS says: As this area of ridge capping was re pointed during roof repairs from hail damage in 2020, we believe that the pointing is defective and should be the responsibility of the roofing trade who completed these repairs. OS has provided a quote for the repairs to the garage ceiling dated 22 April 2024 in the amount of $3,820.38. The insurer then engaged the builder (AA) who undertook the roof repairs to inspect. AA observed the cracked roof pointing which was believed to be the point of ingress. AA confirmed that this section of roof pointing was not replaced during the original repairs but is original to the building. The previous repairs show a distinct colour change. AA’s report includes several colour photographs taken at the time of inspection. The photographs clearly show the area that was previously repaired and the darker coloured pointing. The damaged pointing is adjacent to this area, separated by one ridge cap and along the same ridge line. The insurer says that based on the report from AA, the damage was not from the original insured event or the repairs. The insurer says that the damage to the ridge cap pointing is excluded from cover under its general exclusions for wear, tear and gradual deterioration. Insurer conducted repairs in October 2021 The insurer has also provided reports from OS following its attendance at the property on 6 October 2021. OS attended after the complainant had reported water stains to the garage ceiling following AA’s repairs. OS inspected the roof at this time and found that two roof tiles above the two areas of water stains to the garage. OS observed that one tile had a broken water course and says it would have been missed during the roof inspection. The second tile had a fracture mark which OS says indicated that the tile was likely broken from the original storm. OS says that it replaced both tiles with spares. OS did not observe any maintenance issues or defects at this time. The insurer has provided a copy of the variation submitted by OS dated 7 October 2021 for the painting of the ceiling and cornice in the garage following the inspection. Complainant’s arguments do not advance his position The complainant says: · the damage should be considered rectification works as the damage could have been missed from the previous claim · the roof was not repaired by AA but by AL · the damage to the garage ceiling was not repaired in October 2021 · OS’s comments support that the damage was related to the previous roof repairs · he engaged a building consultant who does storm damage work. The consultant advised that the issue with the stains in his garage ceiling are related to the storm in 2020 and not a new weather event · the building consultant made these comments following an inspection of the damage. The complainant has not provided any expert evidence. The cracked ridge pointing is along the same ridge line to the previously repaired ridge cap. However, I place little weight on OS’s comments that the roof pointing was defective because it was the area that had been previously repaired by AA. The colour difference between the original area and the repaired area is distinctive. I am not persuaded that there is any evidence to dispute the findings from AA that this area had not been previously repaired. Further, I am satisfied that subsequent inspections by OS in October 2021 would have likely identified a crack in the ridge pointing if it was present at this time. That is, I am satisfied that it was not caused by the previous insured event. I am satisfied based on the reports provided, that AA undertook the repairs to the roof on behalf of the insurer. I am unable to comment whether AA engaged AL to undertake the repairs as a sub-contractor. The complainant refers to an email dated 30 September 2021 where he refers to the mould on the garage ceiling. However, the invoice from OS supports that the painting was not undertaken until sometime after the variation was provided to the insurer dated 7 October 2021. The complainant’s submission to AFCA note that he observed mould ‘reappearing’ on the ceilings. This is consistent with the information provided by the insurer that OS repainted the garage ceiling after undertaken minor repairs to two roof tiles in October 2021. I do not accept the complainant’s position that repairs were not undertaken. I place little weight on comments made by a building consultant to the complainant in the absence of any formal reports. The complainant has raised concerns about the legitimacy of the invoicing submitted by AA as part of the previous claim process. This is not a matter that AFCA is able to determine and is a matter between the insurer and the builder. Damage to ridge cap pointing is not related to previous claim or repairs In the circumstances, the complainant has not established that the damage to the ridge cap pointing is a claimable loss, and the insurer is not required to pay the cost of repairing the ridge cap pointing. Given the complainant has not shown the damage to the roof is a claimable loss under the policy, there is no requirement to consider/discuss the policy exclusions and conditions. The insurer says that it has offered for the complainant to claim the damages to the garage ceiling under the previously closed claim with no excess applying. However, would not cover the costs of repair for the ridge cap pointing itself. The insurer says that this was offered to the complainant on 26 July 2024. I am satisfied that the insurer’s offer is fair and reasonable and consistent with its policy terms. I note the insurer has offered to have the debris of the broken tiles in the ceiling cavity removed under its lifetime guarantee. 2.2 Is the complainant entitled to non-financial loss compensation? No. I am satisfied that the insurer has appropriately managed the claim and no compensation is warranted. AFCA can award compensation for non-financial loss Under our Rules, AFCA can award up to $6,300 compensation for non-financial loss. This must relate to poor claims handling or other actions of the insurer which cause an unusual degree of stress, delay, or inconvenience. We expect complainants to be moderately robust, and we will not award compensation for the ordinary degree of inconvenience involved in making a claim. Insurer has managed the claim reasonably The complainant says that the insurer’s denial of the claim has placed undue stress and inconvenience on him and his family and has adversely affected the health of his wife. However, I am satisfied that the insurer has managed the claim reasonably well. It appointed its experts to attend and re-assess the damage in a timely manner. It provided a timely claim decision to the complainant and offered to waive the excess in relation to re-opening a claim for the internal damage to the ceiling. While I understand that the claims process has had an impact on the complainant and his family, I am not satisfied that it from the action of the insurer in handling the claim. 2.3 Why is the outcome fair? The outcome is fair as it reflects the insurer’s liability which does not extend to repairs as rectification but rather under a new claim for damage to the garage ceiling only. 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to: · the legal principles · applicable industry codes or guidance · good industry practice · previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. I have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, I have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider: · available documents · the recollections of the parties · all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.