Home / Suncorp Group / Determination 12-24-102268
Determination 12-24-102268
Dispute over the cash settlement amount for additional hail damage repairs after a quote variation
Summary
The insurer cash settled a hail claim for $45,464.80, then rejected a $38,641.75 variation, offering $1,106.61 or repairs instead. AFCA found the offer reasonable, with $1,000 compensation for delay and no professional costs.
The policy allows the insurer to settle by its own assessed actionable quote, which was reasonable, and the complaint was not complex enough to warrant professional costs.
Issues
- Claim amount dispute primary · not upheld“Insurer has offered to pay an additional $1,106.61 or repair the property itself; complainant did not justify the higher quote costs.”
- Delay secondary · upheld“Considering the delays in response to the variation request, I consider [$1,000] appropriate.”
Subjects and remedies
home or building damagenatural disasterpay claimpay non financial loss
Related
All Suncorp Group determinations · Find similar determinations
Text of the determination
Determination
|
Case number
|
12-24-102268
|
Financial firm
|
AAI Limited
Case number: 12-24-102268 29 April 2025
Determination overview
Complaint
This complaint relates to a claim for hail damage under a home and contents policy with the financial form (insurer). The insurer accepted the claim and issued a cash settlement based on a quote provided by the complainant for $45,464.80. Later, the complainant provided the insurer with a scope of works for additional repairs for $38,641.75. The insurer engaged its own repairer, who said the works would cost a further $1,106.61. The insurer has offered to undertake the repairs or pay the complainant a further $1,106.61 for the additional repairs.
The complainant, who is represented, is seeking a further $38,641.75 to cover further repairs, together with $2,500 for non-financial loss compensation and $2,500 for professional fees.
Issues and key findings
Is the insurer’s offer reasonable?
Yes. The insurer has offered to pay an additional $1,106.61 or repair the property itself (providing the complainant repays the initial cash settlement sum).
Is the insurer required to pay other compensation?
Yes. The insurer has offered $1,000 in compensation in acknowledgement of the claims handling experience. Considering the delays in response to the variation request, I consider this appropriate.
Is the insurer required to pay the complainant’s professional service fees?
No. The complaint was not unusually complex, and the complainant could have pursued without professional assistance. The insurer is not required to pay professional costs.
Why is the outcome fair?
The outcome is fair because the insurer has offered to repair the property in accordance with its obligations under the policy or pay the complainant a cash settlement based on an actionable quote. It would not be fair to require the insurer to pay additional repair costs in the circumstances.
It is fair for the insurer to pay compensation for the delays following the variation request.
Determination
This determination is substantially in favour of the insurer. The complainant may choose to allow the insurer to undertake the repairs or accept the additional cash settlement offered by the insurer.
Within 10 business days of being notified of the complainant’s acceptance of this determination and their choice, to the insurer is to:
pay the complainant $2,106.61; or
commence repairs (the complainant must first repay the initial cash settlement of $45,464.80 to the insurer) and pay the complainant $1,000.
The insurer is not required to take any further action until the complainant makes any such election.
Reasons for determination
Is the insurer’s offer reasonable?
Yes. The insurer has offered to pay an additional $1,106.61 or repair the property itself (providing the complainant repays the initial cash settlement sum).
Insurer has now offered to undertake repairs
In March 2023, the complainant lodged a claim for hail damage that occurred on 8 December 2022. In July 2023, the insurer issued a cash settlement of $45,464.80 based on the complainant’s first quote by their builder AC. The insurer says that the complainant chose a cash settlement and that it told the complainant that they had other options available. It does not appear that the insurer specifically offered to undertake the repairs at this point.
In December 2023, the complainant’s representative provided a building quote variation from AC for additional repairs amounting to $38,641.75. The insurer engaged its own repairer, who said the works would cost a further $1,106.61. The insurer has offered to undertake the repairs or pay the complainant a further $1,106.61 for the additional repairs, based on its own repairer’s actionable quote.
The insurer says that it may rely on the policy wording to provide a cash settlement for less than what it might cost an insured and that the quote by its own repairer is actionable. The policy sets out the process the insurer is required to take to settle a claim. The relevant policy provision is set out below at section 3.2. The steps are as follows:
When damage is covered, insurer engages a builder from its supplier network to prepare a scope of works and provide a quote
Insurer arranges for it to be assessed
Where amount is less than sum insured, the insurer will offer the insured to have their home repaired/rebuilt
Where an insured rejects this offer, the insurer pays the assessed quote (on new for old basis), noting specifically that it might be less than it would cost the insured because of trade discounts.
The insurer did not initially offer to undertake the repairs, presumably because the complainant provided a quote from her preferred repairer.
However, the insurer has followed this process in relation to the variation request. That is, it engaged its own builder to prepare a scope of works and quote and then assessed it. It has offered to undertake the repairs. It may rely on the policy provisions in respect of the cash settlement figure. It must do so fairly. It is accordingly necessary to consider the insurer’s assessment.
Insurer’s quote appears reasonable
AC’s variation quote dated 16 November 2023 includes the following additional works, he says are necessary in addition to the original:
|
Main roof – Colorbond corrugated curved roof sheeting .66 curving soft sheets instead of 0.42BMT instead of Colorbond corrugated curved roof sheeting
|
$26,214
(less 14,135.00 in original quote)
|
Dry Pan flashing required (not in original quote) required to cover over roof sheet to prevent roof leakages
|
$210
|
PVC pipe - due to curved roof required as edge roll
|
$688.80
|
Foam cladding – no allowance for foam cladding in original scope of work. Required to remove apron flashing once cladding removed and cannot be reinstated
|
$1,856.25
|
Plastering external wall will need to be rendered to bring back to pre-loss condition
|
$9,937.50
|
Supply and paint to all affected work areas
Paint PVC pipe
|
$2,252.50
$450
|
Drop sheets
|
$450
Following receipt of AC’s variation, the insurer consulted its repairer (HR). The insurer’s assessor’s notes include the following:
The roof sheets do not need to be thicker except for the front awning
The dry pan flashing only needs to be 250mm wide and 2.5m long
Render repairs estimate – only 20m² required
No additional costs required for drop sheets.
HR completed a further quote. The main differences in the quote figure overall are the roof sheets and the rendering. The complainant has not provided evidence to support the necessity of the inclusions in their quote over and above what the insurer has identified.
It is perplexing that the complainant’s repairer decided that it needed to increase their quote by 85% after the cash settlement. There are no doubt circumstances where significant factors are not considered in the original quote, usually due to unforeseen circumstances, or perhaps due to human error. I am not convinced that this is the case in these circumstances. The complainant has not provided convincing justification of the otherwise higher costs in their quote.
I am satisfied that the insurer has engaged with this process in good faith and is entitled to rely on the policy provision to justify its quote in these circumstances. It is fair for the complainant to choose whether to accept the insurer’s cash settlement or to allow the insurer to complete the repairs
Is the insurer required to pay compensation for non-financial loss?
Yes. The insurer is to pay the complainant $1,000, as previously offered.
AFCA can award compensation for poor claim handling
Under paragraph D.3 of the AFCA Rules, AFCA may award compensation for non-financial loss (capped at $5,400) where the insurer’s actions have caused an unusual amount of:
physical inconvenience
time taken to resolve the situation
interference with the complainant’s expectation of enjoyment or peace of mind.
However, AFCA adopts a conservative approach to the award of compensation for non-financial loss. AFCA expects complainants to be moderately robust and bear the usual stress and inconvenience associated with an insurance claim.
The onus is on the complainant to establish he has suffered a loss because the insurer mishandled the claim.
Insurer’s offer is fair
The complainant experienced some delays after submitting the variation request. The insurer has acknowledged this and offered $1,000 in compensation. I consider this appropriate in the circumstances because the insurer has not otherwise mishandled the claim.
Is the insurer required to pay for the complainant’s professional costs?
No. The complaint was not unusually complex, and the complainant could have pursued without professional assistance. The insurer is not required to pay professional costs.
Insurer not required to pay professional costs
The complainant was represented by a paid consumer advocate. The complainant’s representative says the insurer should pay $2,500 for its professional service fees.
The policy excludes cover for professional services.
Under the AFCA Rules, we can require an insurer to contribute to professional costs a complainant incurred in making a complaint.
We aim to provide a dispute resolution process that is accessible to complainants without any need for professional assistance. Therefore, a party that appoints a paid representative will generally have to pay for this themselves. We may still require an insurer to contribute to a complainant’s professional costs if the complaint was unusually complex and the complainant could not reasonably have been expected to handle it without professional assistance.
The issues involved in this complaint were not unusually complex. In my view, the circumstances of this complaint do not warrant an award of professional costs.
The insurer is not required to contribute to professional costs the complainant incurred in making this complaint.
Why is the outcome fair?
The outcome is fair because the insurer has offered to repair the property in accordance with its obligations under the policy or pay the complainant a cash settlement based on an actionable quote. It would not be fair to require the insurer to pay additional repair costs in the circumstances.
It is fair for the insurer to pay compensation for the delays following the variation request.
Supporting information
The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided.
While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.
Relevant provisions of the policy
|
Product Disclosure Statement
|
How we settle home claims
We will aim to use a member of our builder supplier network to repair or rebuild the damage to the home. Sometimes this is not always possible e.g. if there is pre-existing damage. This will determine how the home claim will be settled.
When a member from our supplier network can complete the repair or rebuild
When your claim for loss or damage to the home is covered, we will engage a builder from our supplier network to prepare a scope of works and provide a quote on the cost to repair or rebuild the home on a ‘new for old’ basis.
Once the scope of works and quote is provided to us, we will arrange for it to be assessed. This will involve reviewing the quote to make sure that the quote is appropriate and reasonable for the scope of works. This includes a consideration of the appropriateness of materials, repair method, labour and material costs and overall cost.
When a member of our supplier network is unable to complete the repair or rebuild
When your claim for loss or damage to the home is covered and a member of our supplier network is unable to complete the repair or rebuild, we will ask you to engage a builder to provide a scope of works and provide a quote on the cost to repair or rebuild your home on a ‘new for old’ basis.
Once the scope of works and quote is provided to us, we will arrange for it to be assessed. This will involve reviewing the quote to determine it is appropriate and reasonable for the scope of works. This includes a consideration of the appropriateness of materials, repair method, labour and material costs and overall cost effectiveness.
If the quote is appropriate and reasonable for the scope of works, we will then pay you the assessed amount. If it is not, the quote may be adjusted. This may include adjusting the scope of works or the quote. We will then pay you the adjusted amount of the quote.
If we pay you for the repair or rebuild, the Lifetime guarantee for home repairs does not apply, see page 96.
When we settle the home claim we will not:
— pay more than the relevant sum insured or policy limit;
— pay extra because you paid more for an item when it was originally purchased;
— pay extra to repair or rebuild the home to a better standard, specification or quality than it was before the loss or damage occurred, except as stated in the meaning of ‘new for old’ (see page 92) or unless stated otherwise in your policy;
— fix inherent defects, structural defects, structural faults and/or faulty/poor workmanship that are not covered by your policy (see section 3 ‘Things we don’t cover’ on page 33), other than a defect or fault that we guarantee under this policy;
— pay extra to repair or rebuild undamaged parts (some limited cover is available in ‘Matching undamaged parts’ see page 74);
— fix or pay to fix pre-existing damage (unless your policy provides otherwise)
|
We do not cover
Extra costs or other losses following an incident covered by your policy extra costs or other losses (financial and non-financial loss) following an incident covered by your policy, including but not limited to:
— loss of income or wages;
— medical expenses;
— costs, including the cost of your time, to prove your loss or to help us with your claim (e.g. telephone calls, postage) unless stated otherwise in your policy;
— cost of hiring appliances after yours suffer loss or damage;
— professional, expert, legal, consulting or valuation costs, unless you obtained our prior authority to incur these costs
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.