Home / Chubb / Determination 12-00-986055
Determination 12-00-986055
Cash settlement offer for water leak repairs and temporary accommodation
Summary
The lot owner disputed the insurer's cash settlement for water leak repairs and temporary accommodation, and sought far more. The panel increased the building repair allowance to $186,009.84, confirmed $77,838.71 for temporary accommodation and awarded $2,000 non-financial loss, plus interest.
The panel preferred the insurer's quantity surveyor scope and updated rates over the complainant's unreasonable quotes, with a 20% contingency.
Issues
- Claim amount dispute primary · upheld“The insurer should increase its allowance based on its quantity surveyor's estimate and in the manner set out in section 2.1.”
- Poor claim handling secondary · upheld“The panel accepts there were aspects of the insurer's claims handling that were unreasonable.”
Subjects and remedies
home or building damagepay claimpay interestpay non financial loss
Related
Text of the determination
Determination
|
Case number
|
12-00-986055
|
Financial firm
|
Chubb Insurance Australia Limited
Case number: 12-00-986055 30 October 2024
Determination overview
Complaint
The complainant is a beneficiary under a strata policy underwritten by the financial firm (insurer). The complainant lodged a claim with the insurer for damage to the insured unit caused by a water leak.
The insurer accepted the claim and is seeking to cash settle the repairs. This is because the complainant is seeking to complete private repairs. The insurer has made an offer of settlement.
The complainant disputes the insurer’s offer saying it is inadequate. She is seeking a greater amount towards the repair costs as well as a range of other remedies.
Issues and key findings
Is the insurer’s offer fair?
Mostly. The insurer should increase its allowance based on its quantity surveyor’s (HR) estimate and in the manner set out in section 2.1.
Should the insurer pay more temporary accommodation?
No. The insurer’s offer is fair.
Should the insurer pay the complainant’s other costs?
No. The exchanged information does not show the complainant is entitled to the other costs claimed.
Is the complainant entitled to non-financial loss?
The insurer’s offer of $2,000 is a fair offer for the delays and inconveniences its claims handling has caused the complainant.
Determination
This determination is substantially in favour of the insurer.
Within 21 days of the insurer receiving notice the complainant accepts this determination, the insurer is to pay the following (minus any policy deductions and amounts it has already contributed towards these matters):
the amounts set out in section 2.1 for the building repairs
$77,838.71 for temporary accommodation
$2,000 compensation for non-financial loss.
Reasons for determination
Is the insurer’s offer fair?
Parties dispute the allowance for building repairs
This complaint involves three claim numbers. In its email dated 18 July 2024, the insurer has offered $257,467.14 to resolve the claims and the complaint, comprised of the following:
$207,328.57 inclusive of building repairs ($174,328.57) and temporary accommodation ($33,000) offered on 7 May 2024 – these all have a 20% contingency included
$2,000 for non-financial loss
$44,838.57 additional temporary accommodation offered on 4 June 2024
$3,300 for building permit and engineering costs
The complainant disputes this. She notes her quantity surveyor (R) estimated her cost to be between $280,000 to $330,000 for the building repairs and says it is reasonable for this to be met. She is seeking a greater amount for temporary accommodation and a range of other remedies.
Insurer’s quantity surveyor (HM) reviewed several quotes and scopes
The complainant provided quotes from 3D and S, along with R’s estimate. The quotes and ranges were as follows:
$296,573.42 from 3D
$331,056 from SL
$280,000 to $330,000 from R.
The insurer is relying on a quote from A ($113,346.20) and three quotes from S (totalling $39,231.01 less $7,303.40 for works completed) to underpin its offer.
The insurer engaged a quantity surveyor, HM, to review the quotes provided by both the complainant and itself. HM provided a detailed report dated 6 March 2024. HM noted the scope of works for 3D and SL were similar to that relied upon by the insurer. However, HM considered the prices from 3D and SL fell significantly outside the expected range (+/- 10%) for works of this scope, size and complexity.
For SL’s quote, HM said the following:
it included replacement of all kitchen joinery and benchtop which exceeds the accepted scope of works
identified a range of examples where the amount exceeded the reasonable cost, including the following:
> $12,000 (exclusive of GST) for repairs to a storage cupboard where the cost is likely to be around $2,700 (exclusive of GST)
> $15,000 (exclusive of GST) for first floor bedroom which is likely to be around $6,687 (exclusive of GST)
> $30,000 (exclusive of GST) for repairs works to ground floor bathroom which is likely to be around $17,743 (exclusive of GST)
For 3D, HM said it has included the supply and installation of a new kitchen and stone which exceeds the insurer’s scope of works and is not substantiated. It also considers the timeframe allowed, being 24 weeks, to be excessive.
In contrast, HM considered AB’s quote to be reasonable.
Insurer should pay $186,009.84 plus interest
Having carefully considered all the exchanged information, the panel notes the following.
It is persuaded by HM’s evidence. HM has provided a careful and detailed report reviewing a range of quotes. It has highlighted plausible and logical reasons as to why it considered the complainant’s two quotes as being unreasonable.
In contrast, R’s report is brief. It has not reviewed the quotes and scopes in any detail. It has provided a general cost estimate with no breakdown. It also appeared to include a complete replacement of all cabinetry, benchtop and splashbacks in the kitchen. The exchanged information does not clearly show this is required.
The panel notes the complainant maintains the benchtop was damaged by the insurer’s contractors. However, little objective information is provided in support. This claim has been ongoing for a long time. In such circumstances, the panel does not accept there is sufficient basis to include this.
Therefore, on balance, the panel accepts it is reasonable to rely on the insurer’s quotes as a basis to calculate a fair settlement given HM’s evidence.
The panel notes the insurer’s settlement is based on prices current to November 2022. The panel does not consider this is fair given the following:
it is not clear if any payments were made to the complainant back then based on those amounts
the insurer has substantively increased the offer from then to include AB’s quote and a contingency.
Instead, given these specific circumstances, the panel considers it fair for more updated rates to be allowed. On that point, the panel prefers HM’s estimate. It is generally consistent with the reasonable rates and allowances provided by the insurer. There is nothing to indicate its overall allowances and rates are unfair. It is based on a fair scope of works
On that point, the panel considers it is fair to allow $154,985.60. This adds back the depreciation ($9,729 exclusive of GST). The panel also notes the following additions and deductions to the above amount:
an allowance of $4,026 for furniture removal
a deduction of $7,303.40 for works done already
an addition of $3,300 for the building permit and engineering costs
an additional 20% contingency for the amounts allowed.
This brings the total to $186,009.84 for all the building repairs. Interest should also be included in this amount given it has not been paid. Interest is payable from 6 April 2024, being one month after HR issued its costings, until payment is made. The rate is to be calculated pursuant to section 57 of the Insurance Contracts Act 1984.
Complainant is seeking a range of other costs
In an email sent around 7 March 2024, the complainant included a range of costs she is seeking reimbursement for, including:
curtains and blinds
cleaning costs
controller reinstatement
repairs to front door
four missing doors
installation of doors and handles
damaged ovens
damaged modem
mould report and PVR sign off costs
storage boxes and packing materials
moving costs
It is not clear to what extent some of these items are covered by the policy. For instance, the policy does not cover the lot owner contents. This likely includes the controller, curtains, blinds and modem. If the complainant is seeking reimbursement of this due to the insurer’s claims handling, there is no objective information in support to show the insurer should be responsible for these costs.
For other items claimed (cleaning, doors, ovens, mould, storage and moving), it is not clear to what extent this is claim related and, if it is, why it is not covered by the scope of works or the 20% contingency. Given this, the panel considers the 20% contingency is sufficient allowance for any claim related repairs not covered by the insurer’s quote.
Should the insurer pay more temporary accommodation?
Insurer’s offer is fair
The insurer had offered to pay 11 weeks for temporary accommodation. This was to account for the estimated repair timeframe. The insurer later provided a further allowance for 139 days. This was to account for its delay in assessing additional information and provide a correct cash settlement figure.
The breakdown is as follows:
$33,000 for the 11 week period – this was based on a weekly rate of $2,500 per week with a 20% contingency added to the total
$44,838 for a 138-day period – based on a daily rate of $322.58 per day ($10,000 per month divided by 31 days).
The complainant queried the amount noting she says the delays have all been caused by the insurer. She also questioned the daily allowance provided by the insurer as it initially allowed $2,500 per week. This translates to a daily rate of $357.14.
The complainant is seeking $2,500 per month from 19 December 2022 to current.
It is not necessarily clear to what extent, if any, the complainant has incurred temporary accommodation costs once the insurer ceased paying for this. She has provided no receipts or evidence that she has incurred any costs in this regard, let alone the weekly amount sought.
The panel is also not persuaded the complainant’s experts have provided a reasonable repair estimate. On this point, the panel accepts HR’s evidence that the likely timeframe is 10 weeks. It is consistent with the insurer’s estimates. HR also provided compelling factors as to why there were issues with the complainant’s quotes.
The panel also does not accept all the delays were caused by the insurer. The complainant has pursued the complaint seeking a much more substantial amount towards the repairs. Her position has not been supported. There were also delays in the claim itself due to the complainant seeking private repairs. These have substantively contributed to the delay in her claim being resolved.
Given all this, the panel does not consider there is any basis to conclude the insurer’s allowance for temporary accommodation is unfair.
Should the insurer pay the complainant’s other costs?
Complainant not entitled to other costs
The complainant has also sought these remedies:
Medical costs
Legal costs
Water costs
Body corporate
Electricity
Financial costs - credit card interest for accommodation
Quantity surveyor supervision
The panel does not accept any of these are substantiated.
There is no medical evidence to show the costs she is claiming are solely, or dominantly, caused by the insurer’s poor claims handling. They are also not covered by the policy.
The complainant has not substantiated the amounts sought for water, body corporate or electricity or set out the basis for such claims.
The complainant has not provided statements, or other evidence, of the credit card interest incurred for alleged late payments.
Professional costs not payable
Under Rule D.5, AFCA may decide an insurer is to contribute to the professional costs incurred by a complainant during a complaint. These costs can be awarded if the complainant needed an expert to understand or establish their claim. These costs are capped at $5,400 unless exceptional circumstances apply.
The panel does not accept the complainant’s experts assisted her. For instance, there is no information of the particular advice the lawyers provided that she needed to agitate her claim. Her quantity surveyor’s evidence was not persuasive in establishing her claim. Given this, the insurer is not required to contribute to these costs.
Is the complainant entitled to non-financial loss?
Compensation is awarded conservatively
Under the AFCA Rules, we may award compensation (capped at $5,400) for non-financial loss. This is where a complainant has suffered an unusual degree or extent of physical inconvenience, time taken to resolve the situation or interference with their expectation of enjoyment or peace of mind due to the insurer’s conduct.
We take a conservative approach to compensation for non-financial loss. It is not awarded when a person suffers the normal degree of inconvenience when a problem occurs.
Insurer’s offer is fair
The panel accepts there were aspects of the insurer’s claims handling that were unreasonable. Its initial offer did not account for all the claim related repairs or provide a sufficient contingency. The allowance of temporary accommodation did appear short at the time.
However, the panel accepts the complainant contributed to the delay in seeking a significantly higher amount that was not substantiated. It is also not clear if the complainant is being over-compensated for the temporary accommodation given:
there is no information to show she incurred temporary accommodation costs after the insurer ceased paying for this, and
the insurer’s allowance covers much more than the required timeframe for the repairs.
Given all this, the panel considers the insurer’s offer of $2,000 for non-financial loss is fair in all the circumstances.
Supporting information
The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided.
While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome.
A panel determined this matter
Due to the nature of this complaint, we referred it to a panel for determination. The panel includes:
an ombudsman
a member with significant experience in consumer and small business advocacy
a member with extensive experience in general insurance
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.
Policy wording
|
Page Number
|
Policy Wording
|
20-21
|
5. Additional Benefits B
....
b) Loss of Rent, and Temporary Accommodation
...
i) Temporary Accommodation
Where the Lot Owner occupies the Lot, the reasonable
cost of:
a) immediate emergency accommodation and meals
up to $2,500; and
b) Temporary Accommodation,
necessarily incurred by the Lot Owner if the Lot is made
unfit to be occupied for its intended purpose.
We will pay an amount of money for temporary
accommodation calculated on the basis of similar
accommodation located in the vicinity of the Location.
We will pay from the time of the physical loss,
destruction or damage until the time the Lot Owner reoccupies the Lot following completion of reinstatement
or replacement of Your Insured Property.
However, Our maximum liability for Loss of Rent and
Temporary Accommodation is limited to the amount
or percentage of the Limit of Liability shown in Your
Policy Schedule.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.