Determination 12-00-981048

Flood claim cash settlement amount and claim handling delay

FirmSuncorp Group
Decided2024-06-27
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$228,349
Non-financial loss$1,000
Amount claimed$242,527
SourceAFCA PDF

Summary

After a flood damaged his property, the complainant disputed the insurer's cash settlement of about $214,770 and sought more, including disputed lower-level fixtures. AFCA required a settlement of $228,348.67 including a 10% contingency, interest from 27 August 2022, and $1,000 non-financial loss.

A cash settlement based on the insurer's quotes is fair with a contingency for unforeseen works, and the claimant must prove the disputed items were flood damaged.

Issues

Subjects and remedies

home or building damagenatural disasterpay claimpay interestpay non financial loss

Related

All Suncorp Group determinations · Find similar determinations

Text of the determination

Determination | Case number | 981048 | Financial firm | AAI Limited Case number: 981048 6 June 2024 Determination overview Complaint The complainant holds a home insurance policy with the financial firm (insurer). He lodged a claim with the insurer after his property was damaged by flood on 27 February 2022. The insurer accepted the claim. However, a dispute has arisen over the cash settlement amount for repairs to the property. In particular, the parties dispute whether various lower level fixtures, such as the kitchenette, laundry and bathroom (disputed items), were damaged by the flood event. The complainant is represented by a consumer advocate for this complaint. For brevity, any reference to the complainant will include both. Issues and key findings Is the complainant entitled to an increase in the cash settlement? Yes. The insurer should have included a 10% contingency in its cash settlement for potential unforeseen variations. This should now be added. However, the complainant is not entitled to a higher sum. This is because the complainant has not shown the disputed items were damaged by the flood. Further, the information shows the insurer’s settlement, with a 10% contingency, is fair. Should the insurer pay non-financial loss? Yes. There were aspects of the claim the insurer handled unreasonably. The insurer should pay $1,000 in non-financial loss. Determination This determination is mostly in favour of the insurer. Within 21 days of the insurer receiving notice the complainant accepts this determination, the insurer is required to: settle the claim as set out in section 2.1, and pay $1,000 in non-financial loss. Reasons for determination Is the complainant entitled to an increase in the cash settlement? Circumstances of the claim The complainant purchased the property in late 2021. He says he intended to renovate the upper level of the property and appointed a builder to commence the renovations in January 2022. At the time of the flood, he says only the upper level of the property was completely stripped out. The complainant lodged a claim after the property sustained damage from the flood on 27 February 2022. The damage included the lower level of the property being substantively submerged. He also advised the pontoon had been washed away and was not recovered. The insurer assessed the damage and investigated the claim. It requested information from the complainant to show the lower level had retained the disputed items before the flood event. The insurer later formed the view the complainant’s evidence was insufficient to show the disputed items were in place at the time of the flood event. However, it accepted some of the damage from the flood event and made an offer to cash settle $212,096.70 to the complainant for repairs. This included: ARC’s quote of $153,446.60 for internal repairs which did not include the disputed items electrical repairs $34,970.10 air conditioner $16,500 contents $7,180 Following submissions at AFCA, the insurer later agreed to add $2,673 based on a further quote from ARC for missing items. The insurer denied cover for the pontoon as there was no cover under the policy and the complainant does not dispute this. The complainant claims the cash settlement offered does not repair all of the claim related damage to the property. He is claiming: full cover for all the damage sustained in the flood including the disputed items an increase in the cash settlement including contingency and interest non-financial loss compensation interest Complainant claims lower level was not under renovation It is a general principle of insurance law that it is up to the policyholder to prove, on the balance of probabilities, that they have suffered a claimable loss. Once proven, the onus then shifts to the insurer to prove that the loss or damage falls outside the scope of cover provided by the policy or is otherwise excluded. The insurer disputes whether the lower level had retained the disputed items. The insurer notes the property was under renovation at the time of the flood. The insurer says the complainant has not produced any contemporaneous information to show these were in situ at the time of the flood. Photos which were provided after the flood do not show this. There is no information provided to confirm the extent of the renovations was solely limited to the upper level. Where the complainant did provide photos to show some of the disputed items were in place, they were taken months before the claimed event and before renovations commenced. The insurer also notes that in an earlier conversation on 2 March 2022, the complainant said the builder was working on the downstairs section at the time. He was also directed to take photos when doing a make safe and strip out. However, despite this, limited photos were provided and none show the disputed items were in situ at the time of the flood event. By the time the insurer’s expert attended the property, the lower level was substantively stripped out and no evidence remained of the disputed items. The complainant maintains the renovations was solely limited to the upstairs area. In an interview conducted with him and his wife on 27 September 2022, they both maintain the renovations were limited to the upstairs area. The complainant’s representative also provided a file note of a conversation with the builder on 5 February 2024 who confirmed this. The complainant was asked to provide information of any quotes or plans with the builder prior to the flood. None were available. Neither has any contemporaneous information been provided between him and the builder to confirm the extent of works agreed to. Information does not show disputed items were damaged in the flood event Having carefully considered the exchanged information, I note the following. There is no contemporaneous documentation to confirm the complainant’s position the renovations were solely limited to the upper level. No quotes, invoices, photos or correspondence between him and the builder confirm this. This is despite the fact a quote was provided by the builder for works to be done after the floods. It is not clear why no documentation can be produced confirming the extent of works done prior to the flood. The complainant’s discussion with the insurer on 3 March 2023, which is contemporaneous to the event, did say ‘Now, I have a builder currently working on site who was doing the downstairs section for me’. This indicates the downstairs section was included in the renovations. It is consistent with the fact that none of the contemporaneous information show the items were in situ at the time. Further, in that same discussion, the complainant was clearly instructed to take photos of the areas before they were cleaned up and stripped. The complainant said ‘Yeah. I’ve got 1,000’, meaning photos. However, much fewer photos were provided. None of these show the disputed items were in situ at the time of the flooded event. Limited information has been provided by the builder beyond the file note. According to the parties, the builder did not want to co-operate. Further, a file note of a conversation with the builder much later after the fact is not, of itself, compelling in the absence of any contemporaneous documents. I acknowledge the complainant and his wife remain steadfast in their submissions the renovations were limited to the upstairs area. Given AFCA’s process does not allow witnesses to be cross examined, then the ability to test such evidence is limited. As a result, contemporaneous information is significant in such a process to be able to substantiate information that is disputed. In this regard, the contemporaneous information is lacking. No documentation can be produced to show the disputed areas were in situ. That is unusual, particularly given the clear instructions to take photos of the strip, the acknowledgement that many photos were available and yet no photo being available to show these items were in situ. Further, the lack of any contemporaneous information confirming the extent of the renovations is unusual. Given all this I am not persuaded, on the balance of probabilities, the complainant has shown the disputed items were damaged by the flood. It follows the complainant has not established a claimable loss for these aspects of the claim. Settlement should be based on insurer’s quotes The complainant’s submission dated 27 March 2024 noted that even if the kitchenette, bathroom and laundry are excluded, the costs he will incur is $242,526.76. He says this is $85,690.88 in addition to the amount allowed in the insurer’s figures. The complainant provided a breakdown of the amount sought. This is attached in section 3.2. I have carefully reviewed them and note the following. The first group of items do not appear related to repairing the claim related damage. Much of it relates to contents. For instance, it includes a lawn mower, whipper snipper, barbeque, ladder and TV. It is not clear how they are related to repairing the claim related damage. I also note the insurer had cash settled the contents. Therefore, I do not accept the items under this area should be included for the building repairs. The second group appears to relate to the claim related repairs. This totals $279,291.61. However, included in that is accommodation. It is unclear what this amount is based on and, to what extent, it is outstanding with respect to that already agreed to by the insurer. I also note that the complainant’s submission dated 27 March 2024 said he would be concede seeking any further allowance for alternate accommodation. Therefore, this should be excluded. Further, the quote for the kitchenette, laundry and bathroom should be excluded as I do not accept the information shows they were flood damaged. This leaves $216,540.80. The complainant, in accounting for the insurer’s settlement, has only allowed $156,835.88. This is based on two quotes provided by the insurer’s contractor ARC. However, the complainant has excluded the insurer’s cash settlement of an electrical quote for $34,970.10 and a replacement air-conditioner of $16,500 from the calculations. I do not accept these should be excluded. For instance, the complainant’s spreadsheet for claim related damage includes a quote from his builder (AM) totalling $164,883.20. Included in that quote was ‘All required electrical work’ and ‘Replace damage outdoor-ducted air unit’. There is nothing to suggest those works were in addition to the amounts settled by the insurer. Given the amount settled for electrical work was fairly substantive, and there is no indication another air unit was damaged, it is likely these amounts were included in AM’s quote. Therefore, if I include the amounts allowed by the insurer for electrical works and the unit, it has agreed to pay $207,589.70. This means the difference between what the insurer has paid, and what the complainant is seeking for the repairs, is only $8,951.06. Given this, I accept it is fair to base a cash settlement on the insurer’s quote. However, I consider it fair that a contingency be allowed. Whilst the insurer says it provided a 20% contingency, this was based on a ‘20% CAT Event Loading’. The complainant says this loading does not cover the risks of unforeseen works. Instead, it is to enable the contractor to carry out the works at the fixed rate agreed with. The insurer has not specifically refuted this. Accordingly, I consider it fair to allow for a contingency for the risks of unforeseen works and the loss of lifetime guarantee. The complainant has advocated for 30%. I disagree. Even on the complainant’s own quotes, the insurer’s settlement excluding a contingency is fairly close. Instead, I consider it fair to allow for 10%. This brings a total of $228,348.67 for the building repairs minus any outstanding policy deductibles (e.g. excess). I consider this fair to resolve all outstanding issues in the complainant’s table in section 3.2. This is because if I exclude the accommodation and the quote for the kitchenette, laundry and bathroom, the proposed figure exceeds the other amounts sought by the complainant for all other items by $3,292.91. It is also not clear if the complainant has substantiated his entitlement to all the other items, such as the contents in the first group. Insurer to pay interest on any outstanding sum from 27 August 2022 The complainant has also sought interest on any outstanding sum from mid-June. The complainant says the insurer has unduly delayed the claim and provided various submissions in support. The insurer made an offer to settle the claim on 6 February 2023. This was almost a year after the claim lodged. This is too long to assess such a claim. I do accept the insurer was entitled to investigate the claim. There were legitimate concerns about the disputed items which remain unsubstantiated. There were also some delays due to the complainant’s unavailability. I also note the claim was lodged when resources were limited and the complainant’s builder was not co-operating. In my view, a reasonable period to investigate, assess and consider the claim in such circumstances should have taken six months. This accounts for the complainant’s unavailability, the limited resources, the complex nature of the claim and the unusual background. Therefore, the insurer should pay interest on any outstanding sum payable pursuant to section 57 of the Insurance Contracts Act 1984 from 27 August 2022 until payment is made. Should the insurer pay non-financial loss? Compensation is awarded conservatively Under the AFCA Rules, we may award compensation (capped at $5,400) for non-financial loss. This is where a complainant has suffered an unusual degree or extent of physical inconvenience, time taken to resolve the situation or interference with their expectation of enjoyment or peace of mind due to the insurer’s conduct. We take a conservative approach to compensation for non-financial loss. It is not awarded when a person suffers the normal degree of inconvenience when a problem occurs. Insurer should pay $1,000 in non-financial loss I accept there were some unreasonable delays. In particular, it appears a proper assessment of the internal damage was not done until months later. This delayed the claim. I do not accept all aspects of the insurer’s claims handling was unreasonable. As stated before, I accept the insurer’s decision to investigate the claim was reasonable. I also note much of the delays following the insurer’s claim decision was due to the complainant’s pursuing a financial remedy for the disputed items which was not substantiated. Further, the complainant has not shown the insurer’s cash settlement offer was substantively unfair. Given all this, and considering our conservative approach, it is fair the insurer pays $1,000 in non-financial loss to the complainant. Why is the outcome fair? The insurer should include a 10% contingency to cover the risk of unforeseen works and the loss of lifetime guarantee. The insurer is not required to pay anything further for the claim. This is because the complainant has not shown his loss exceeds this amount. The insurer should pay $1,000 in non-financial loss given there were unreasonable aspects of its claims handling. Supporting information The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to: the legal principles applicable industry codes or guidance good industry practice previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider: available documents the recollections of the parties all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established. Complainant’s breakdown

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.