Home / Suncorp Group / Determination 12-00-1093453
Determination 12-00-1093453
Defective repairs and rectification process, delay in repairs
Summary
Insurer's repairs after a house fire were defective; the insurer agreed to rectify but complainants refused until more detailed drawings were provided. AFCA found the insurer could proceed, allowed complainants to appoint a certifier at insurer's cost, and awarded engineer's fees up to $5,000 and $4,000 for non-financial loss.
The insurer is responsible for its contractors' defective repairs and resulting delay to 30 May 2024, but the drawings were sufficient and later delay was caused by the complainants' refusal to allow rectification.
Issues
- Repairs or contractors primary · upheld
“The insurer agreed that the repairs were defective and required rectification; insurer responsible for its contractors' actions.”
- Poor claim handling secondary · not upheld
“Insurer not required to provide more detailed engineering drawings before beginning rectification process.”
- Delay secondary · upheld
“The insurer is responsible for the complainants being unable to live in their home from 3 November 2023 to 30 May 2024.”
- Unfounded fraud allegation secondary · not upheld
“Complainants say the defective repairs were fraudulently certified; insurer had not said it intended to rely on previous certifications.”
Subjects and remedies
home or building damagepay compensationpay non financial lossrefund fees or chargesrepair or rectify
Text of the determination
Determination
|
Case number
|
12-00-1093453
|
Financial firm
|
AAI Limited
Case number: 12-00-1093453 2 June 2025
Determination overview
Complaint
The complainants hold a home insurance policy with the financial firm (the insurer). They lodged a claim after their home was damaged by fire. The insurer accepted the claim and repaired the home. The repairs were defective. The insurer has agreed to rectify the repairs.
The insurer says it is ready to begin rectification work. The complainants say they will not allow the insurer to begin the rectification work until it provides more detailed engineering drawings. The insurer says the details the complainants are requesting cannot be provided until a later stage in the repair process.
The complainants say the insurer’s defective repairs were fraudulently certified. They say they want the insurer’s builders to carry out the rectification work, but they want to appoint a building certifier to certify the work. The insurer says it is willing to consider this.
Issues and key findings
Is the insurer ready to begin rectification work?
Yes. The insurer is not required to provide more detailed engineering drawings, or any other information, before beginning the process (starting with an on-site visit to prepare a scope of works for rectification).
Can the complainants appoint a building certifier?
Yes. The complainants may appoint a building certifier. The insurer must reimburse the complainants for the reasonable cost of appointing the certifier.
Are the complainants entitled to other compensation?
Yes. The complainants are entitled to:
up to $5,000 (the most AFCA can award) for their engineer’s fees
$4,000 compensation for non-financial loss (stress and inconvenience) caused by the insurer delaying repairs.
Why is the outcome fair?
This determination entitles the complainants to appoint a building certifier while the insurer appoints builders. This means the complainants will not have the burden of managing repairs, but will be able to obtain independent confirmation that the repairs are done correctly.
Determination
This determination is mostly in favour of the insurer.
The complainants must allow the insurer to rectify the defective repairs. If the complainants do not allow the insurer to rectify the defective repairs, the insurer must settle the claim by paying the complainants the reasonable cost of rectifying the defective repairs.
The complainants may appoint a building certifier on the following conditions:
the complainants must appoint a certifier within a reasonable time. If the complainants do not appoint a certifier within a reasonable time (and if the insurer is to proceed with repairs), the insurer may appoint and rely on its own certifier
the complainants must inform the insurer of the identity of the certifier and their role in the repair process. The insurer must take all reasonable steps to cooperate with the certifier. The insurer must not refuse to cooperate with the certifier without reasonable excuse. If the insurer refuses to cooperate with the certifier, it must explain why to the complainants
the certifier may impose requirements on the builder in accordance with the Building Act 1975 (Qld) and other relevant laws and regulations. However, the certifier must not unreasonably interfere with the building works. If the certifier unreasonably interferes with the building works, the insurer may stop the building works and pay the complainants the reasonable cost of any outstanding building works
the insurer must reimburse the complainants for the reasonable cost of appointing the certifier.
Upon receipt of proof of payment, the insurer must reimburse the complainants for the cost of appointing their engineer, up to a maximum of $5,000.
The insurer must pay the complainants $4,000 compensation for non-financial loss.
Reasons for determination
Is the insurer ready to begin rectification work?
Yes. The insurer is not required to provide more detailed engineering drawings, or any other information, before beginning the process (starting with an on-site visit to prepare a scope of works for rectification).
Insurer agreed to rectify defective repairs
On 8 October 2022, the complainants lodged a claim for fire damage to their home. The insurer accepted the claim and appointed a builder to repair the damage. The complainants said all repairs were defective.
The complainants appointed an engineer (SC), who inspected the property on 12 October 2023 and 11 January 2024. After each inspection, SC reported defects in the repairs.
The insurer agreed that the repairs were defective and required rectification. The insurer appointed a different builder to carry out the rectification work.
Complainants demand more detailed engineering drawings
The insurer says it is ready to begin the rectification work.
As part of the preparation for the rectification work, the insurer appointed an engineer (ECE) who prepared a set of engineering drawings dated 28 March 2024. The complainants say these drawings are not detailed enough.
The complainants have not appointed their own builders. They say they want the rectification work done by the insurer’s builders. However, they say they will not allow the insurer to begin the rectification work until it provides more detailed engineering drawings.
Insurer addressed concerns about engineering drawings
On 28 March 2024, ECE prepared a set of engineering drawings.
On 30 April 2024, SC reviewed ECE’s drawings and said further details were required.
On 30 May 2024, ECE responded to SC’s concerns as follows:
|
SC concern
|
ECE response
|
The drawings do not show all bracing end connections and offset dimensions. They do not show all truss elevation details.
|
These details are to be developed by the roof truss supplier when replacement roof trusses are ordered.
|
The drawings do not include certified drawings from the patio roof manufacturer.
|
These drawings are to be supplied by the patio roof manufacturer.
|
The drawings do not detail the connections required at the base of the new wall framing.
|
This is subject to the discretion of the building certifier.
On 3 June 2024, the insurer’s builder said ECE’s drawings were ‘standard’, and they did not need any further engineering drawings to prepare a scope of works.
The complainants have not provided any further information from SC or any other experts.
SC said ECE’s drawings were lacking some details. ECE said those details would be provided later by other experts. The complainants say they do not accept this explanation. However, they have not provided any information to refute it. They have not provided information showing it is necessary for the insurer to provide the requested details at this stage.
The panel is satisfied that the engineering drawings provided by ECE are sufficiently detailed to allow the next stage of repairs to proceed.
Reasonable for insurer to arrange on-site visit
The insurer says it wants to arrange an on-site meeting with its contractors, the complainants, and SC to ‘gain an agreement on the scope of work’. The insurer has offered to reimburse the complainants for any fee charged by SC to attend the meeting.
The insurer has prepared several scopes of work for repairs. The complainants used the insurer’s scopes of work to prepare a combined scope of works. The complainants say their combined scope of works can be used as ‘starting point’ for rectification, and there is ‘no point in seeking a further external scope of works’.
The complainants say the insurer’s scopes of work (the basis for their combined scope of work) are ‘grossly incorrect’. The combined scope of works explicitly states it does not include all work required to rectify the defective repairs. The complainants say the building is deteriorating over time because the insurer has left it exposed to the elements, which means the building may have incurred more damage since the complainants submitted the combined scope of works on 8 October 2024.
For the above reasons, the panel is not satisfied that any existing scope of works can be used as the basis for rectification work. It is reasonable for the insurer to inspect the building and prepare a fresh scope of works for rectification.
Insurer must pay cash settlement if complainants do not allow repairs
The insurer is ready and willing to begin the process of rectifying the defective repairs (starting with an on-site visit to prepare a scope of works for rectification). The insurer is not required to provide any further information before beginning the process.
The complainants have prevented the insurer from rectifying the repairs. If the complainants continue to prevent the insurer from rectifying the repairs, the insurer must settle the claim by paying the complainants the reasonable cost of rectifying the repairs.
AFCA does not have enough information to determine the reasonable cost of rectifying the defective repairs. If the insurer cash-settles the claim, it must assess the reasonable cost of any outstanding claim-related repairs. If the parties cannot agree on the reasonable cost of outstanding claim-related repairs, the complainants may lodge another AFCA complaint.
Can the complainants appoint a building certifier?
Yes. The complainants may appoint a building certifier. The insurer must reimburse the complainants for the reasonable cost of appointing the certifier.
Complainants may appoint certifier
The complainants say they want the insurer’s contractors to repair the home, but they want to appoint a building certifier to certify the insurer’s repairs.
The insurer said it was willing to consider the complainants’ request to appoint a certifier, but asked ‘what the scope of their role would be in the repair process’. The insurer expressed concern that the certifier would ‘substantially impede the progression of the claim’.
The insurer has not provided information showing it would be unfairly disadvantaged by the complainants appointing a certifier. Noting the problems arising from the previous repairs, the panel considers it reasonable for the complainants to appoint a certifier.
The complainants may appoint a building certifier on the following conditions:
the complainants must appoint a certifier within a reasonable time. If the complainants do not appoint a certifier within a reasonable time (and if the insurer is to proceed with repairs), the insurer may appoint and rely on its own certifier
the complainants must inform the insurer of the identity of the certifier and their role in the repair process. The insurer must take all reasonable steps to cooperate with the certifier. The insurer must not refuse to cooperate with the certifier without reasonable excuse. If the insurer refuses to cooperate with the certifier, it must explain why to the complainants
the certifier may impose requirements on the builder in accordance with the Building Act 1975 (Qld) and other relevant laws and regulations. However, the certifier must not unreasonably interfere with the building works. If the certifier unreasonably interferes with the building works, the insurer may stop the building works and pay the complainants the reasonable cost of any outstanding building works
the insurer must reimburse the complainants for the reasonable cost of appointing the certifier.
Complainants’ certifier can provide advice on certification
The complainants say the defective repairs were fraudulently certified.
The insurer appointed the same certifier to certify the rectification work.
The complainants say the insurer gave ‘written advice that they intend to rely on the false certification for the future building’. However, the insurer has not said it intends to rely on previous certifications. When asked by AFCA, the complainants were not able to provide an example of the insurer saying it intended to rely on previous certifications.
The complainants say all certifications obtained by the insurer must be withdrawn. It is not clear whether it is possible to withdraw certifications. The insurer asked its building coordinator whether it is possible to withdraw certifications. The building coordinator said the new builder would need to get their own certifications, but did not say whether it is possible to withdraw previous certifications. The complainants have not provided information showing it is possible to withdraw certifications.
This determination allows the complainants to appoint a building certifier to certify the rectification work. The complainants’ certifier can provide advice on what is required to certify the rectification work, whether any previous certifications must be (or can be) withdrawn, and whether any previous certifications can be relied upon.
Are the complainants entitled to other compensation?
Yes. The complainants are entitled to:
up to $5,000 (the most AFCA can award) for their engineer’s fees
$4,000 compensation for non-financial loss (stress and inconvenience) caused by the insurer delaying repairs.
Insurer must contribute to cost of complainants’ engineer
Under the AFCA Rules, we can require an insurer to contribute to professional costs a complainant incurred in making a complaint. We cannot award more than $5,000 for professional costs unless there are special circumstances. The panel does not consider there are special circumstances in this case warranting an award of more than $5,000 for professional costs.
In considering whether an insurer should contribute to a complainant’s costs, we consider whether they were reasonably incurred, and whether they helped resolve the complaint.
The complainants appointed an engineer who identified defects in the insurer’s repairs. The insurer accepts the repairs were defective. In the circumstances, it was reasonable for the complainants to appoint an engineer. The complainants’ engineer provided information that was relevant to the complaint and helped the panel prepare this determination.
Upon receipt of proof of payment, the insurer must reimburse the complainants for the cost of appointing their engineer (SC), up to a maximum of $5,000.
Insurer must pay $4,000 compensation for non-financial loss
Under the AFCA Rules, we can award up to $6,300 compensation for non-financial loss if a complainant suffered an unusual degree of stress, inconvenience, or delay because an insurer mishandled a claim.
The defective repairs have delayed the complainants being able to move back into their home.
The insurer’s notes say the repairs were due for completion on 3 November 2023. However, the repairs were defective. The repairs were carried out by the insurer’s contractors acting on the insurer’s behalf. The insurer is responsible for its contractor’s actions. The insurer is responsible for delaying repairs from 3 November 2023.
On 30 April 2024, the complainant’s engineer (SC) raised concerns with the engineering drawings provided by ECE. On 30 May 2024, ECE addressed those concerns. Since then, repairs have been delayed because the complainants have not allowed the insurer to proceed with rectification work. The insurer is not responsible for delays from 30 May 2024.
The insurer is responsible for the complainants being unable to live in their home from 3 November 2023 to 30 May 2024.
The insurer has provided temporary accommodation for the complainants. This has mitigated the effect of the delay on the complainants. However, while the complainants have not been deprived of accommodation, they have still suffered the stress and inconvenience of not being able to live in their own home.
The panel considers it fair in all the circumstances for the insurer to pay the complainants $4,000 compensation for non-financial loss.
Decision on temporary accommodation not finalised
The complainants are living in temporary accommodation provided by the insurer. The insurer has offered to continue to pay for the complainants’ accommodation until 27 June 2025. The insurer says it will consider paying for further accommodation if necessary.
The complainants say this determination must require the insurer to continue to pay for their accommodation until they return home.
Under the policy, the insurer is required to pay up to $67,310 (10% of the home sum insured) for temporary accommodation. The insurer should also pay for any further accommodation expenses incurred because of delays caused by the insurer. However, it would not be fair to require the insurer to pay for accommodation expenses incurred because of delays caused by the complainants.
It would not be fair for this determination to require the insurer to continue to pay for the complainants’ accommodation until they return home. This is because the complainants’ return home may be delayed for reasons outside the insurer’s control (such as the complainants refusing to allow repairs to their home).
At this stage, it is not clear how much longer the complainants will need temporary accommodation, or how much more temporary accommodation the insurer is willing to pay for. It would not be appropriate for the panel to make a final decision about whether the insurer is required to pay for further temporary accommodation.
If the insurer decides to stop paying for the complainants’ accommodation, and the complainants dispute this decision, the complainants may lodge another AFCA complaint.
Why is the outcome fair?
This determination entitles the complainants to appoint a building certifier while the insurer appoints builders. This means the complainants will not have the burden of managing repairs, but will be able to obtain independent confirmation that the repairs are done correctly.
Supporting information
The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided.
While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome.
A panel determined this matter
Due to the nature of this complaint, we referred it to a panel for determination. The panel includes:
an ombudsman
a member with extensive experience in consumer and small business advocacy
a member with extensive experience in insurance.