Settlement of defective storm damage repairs for 2019 and 2020 claims, foundation damage, accommodation and non-financial loss
Text of the determination
Determination
|
Case number
|
12-00-1085873
|
Financial firm
|
Allianz Australia Insurance Limited
Case number: 12-00-1085873 22 August 2025
1 Determination overview
1.1 Complaint
The complainant holds a home building and contents insurance policy with the financial firm (the insurer). He lodged claims for storm damage in 2019 and 2020. The insurer accepted the claims and appointed builders to repair the damage. Both sets of repairs were defective.
On 31 May 2023, AFCA issued determinations setting out how the claims should be settled. The complainant accepted the determinations, making them binding on the insurer.
Determination 890960 required the insurer to appoint a builder to rectify the 2020 repairs. The insurer says it has tried to do this, but the complainant has not allowed it to.
Determination 937642 required the insurer to cash settle the 2019 claim based on a quote from the complainant’s builder. The complainant’s builder refused to provide a quote.
The complainant says the 2020 repairs included the installation of a defective strip drain. The insurer says the complainant was responsible for this installation.
The complainant says the 2020 repairs created drainage issues which directed water under the house, damaging the foundations. He says the insurer must repair the foundations before any repairs can be rectified. The insurer admits the 2020 repairs created drainage issues, and has agreed to rectify them. However, it says the foundation issues are pre-existing.
The complainant wants the insurer to pay for:
· repairs to the home (including the foundations)
· mould remediation
· asbestos removal
· accommodation from 26 June 2024 (when the insurer stopped paying for accommodation) until the home is repaired
· non-financial loss (stress, inconvenience, and delay).
1.2 Issues and key findings
Is the strip drain part of the insured work?
Yes. The insurer must rectify the strip drain as part of the rectification of the 2020 repairs.
Did the 2020 repairs damage the foundations?
No. The 2020 repairs directed water under the house. However, the house has a history of movement and cracking which is normal for a building of its age and type. There is no persuasive evidence that the pattern of movement has changed, or that the cracking has worsened, since the 2020 repairs. Rectification of the 2020 repairs does not include foundation repair or crack repair.
How should the 2020 claim be settled?
The insurer must rectify the 2020 repairs. If the complainant does not allow this, the insurer must pay the complainant the reasonable cost of rectifying the 2020 repairs.
How should the 2019 claim be settled?
The insurer cannot obtain a quote from the complainant. Therefore, it should obtain its own quote for rectification of the 2019 repairs. It should pay the quoted amount, plus 20% for contingencies. It should pay for mould remediation and (if required) asbestos removal.
Is the insurer required to pay more for accommodation?
No. The complainant has not repaired the home and has not allowed the insurer to repair the home. It would not be fair to require the insurer to pay for further accommodation.
Is the complainant entitled to other compensation?
No. The previous determinations awarded $4,000 compensation for non-financial loss. Since the determinations were issued, the insurer’s handling of the claims has been reasonable. The insurer is not required to pay further compensation for non-financial loss.
Why is the outcome fair?
This determination requires the claims to be settled in accordance with previous determinations, to the extent this is possible. Where the claims cannot be settled in accordance with previous determinations, this determination provides alternative methods of settlement to finalise the disputes.
1.3 Determination
This determination is substantially in favour of the insurer.
The 2020 claim must be settled as follows:
· the insurer must appoint a builder to rectify the 2020 repairs. The builder must not be the builder that performed the 2020 repairs
· within 28 days of being advised of the complainant’s acceptance of this determination, the insurer must arrange for the builder to attend the insured property. The insurer must give the complainant at least three days’ notice of the builder’s attendance
· the complainant must allow the builder to access the property and rectify the 2020 repairs. If the complainant does not do so, the insurer must settle the claim by paying the complainant the amount quoted by the insurer’s builder for any outstanding work.
The 2019 claim must be settled as follows:
· the insurer must appoint a builder to inspect the property and provide a quote to rectify the 2019 repairs. The insurer must pay the quoted amount, plus 20% for contingencies. If the complainant does not allow an inspection, the insurer must pay $10,310.26 for the rectification of the 2019 repairs
· the insurer must arrange an inspection to determine the extent of mould contamination and obtain a quote for mould remediation. The insurer must pay the quoted amount, plus 20% for contingencies. If the complainant does not allow an inspection, the insurer must pay $9,379.34 for mould remediation
· the insurer must arrange a further inspection to determine whether asbestos removal is required for the rectification of the 2019 repairs. If required, the insurer must obtain a quote for asbestos removal. The insurer must pay the quoted amount, plus 20% for contingencies. If the complainant does not allow an inspection, the insurer is not required to pay for asbestos removal.
2 Reasons for determination
2.1 Is the strip drain part of the insured work?
Yes. The insurer must rectify the strip drain as part of the rectification of the 2020 repairs.
Insurer arranged repairs in 2020
On 14 February 2020, the complainant’s home was damaged by a storm. The damage was to the patio paving and patio roof on the east side of the house.
The insurer appointed a builder to repair the damage. On 2 March 2020, the builder inspected the property and said the following repairs were required:
· replace damaged patio roof sheeting
· remove, re-level, and re-fit pavers.
The builder issued an invoice for repairs (which did not list the work completed) on 28 August 2020.
Parties disagree on who was responsible for strip drain
In 2020, a strip drain was installed at the south end of the patio, near the south-east corner of the house. In 2023, an engineer appointed by the insurer said the strip drain was undersized and improperly installed. The parties agree the strip drain is defective.
The complainant says the strip drain was installed by the insurer’s builder.
The insurer says the installation of the strip drain was private work arranged by the complainant, and the complainant is responsible for rectifying it.
The insurer has offered to pay the costs of rectifying the drainage issues around the patio. However, it says it is not required to do so.
Strip drain installation was part of insured work
The insurer provided a copy of a letter from its builder to the complainant. The letter said the complainant wanted to appoint the builder’s sub-contractor to connect a strip drain to a storm water inlet. The letter said this would be separate to the insured work, and the complainant would pay for it. There are several problems with this document:
· it was supposedly written in 2020 (when the builder was working at the complainant’s home), but is dated 2 July 2025 (the day before the insurer provided the document to AFCA)
· it has a space for the complainant to acknowledge the work was ‘private works’ and the insurer would not be responsible for the quality of the work. However, it is not signed. The builder says it does not have a signed copy
· the builder says it sent the document to the complainant for him to sign and return. However, there is no record of it being sent to the complainant.
The complainant says he never appointed anyone to perform private work, nor did he ever discuss the possibility of private work with the insurer’s builders.
Having considered the information provided by both parties, I am satisfied the insurer’s builder (or its sub-contractor) installed the strip drain. I am satisfied this was part of the insured work and not private work. The insurer must rectify this as part of the rectification of the 2020 repairs.
2.2 Did the 2020 repairs damage the foundations?
No. The 2020 repairs directed water under the house. However, the house has a history of movement and cracking which is normal for a building of its age and type. There is no persuasive evidence that the pattern of movement has changed, or that the cracking has worsened, since the 2020 repairs. Rectification of the 2020 repairs does not include foundation repair or crack repair.
Complainant says insured work caused foundation movement
The insurer’s builder removed and re-laid the patio paving in 2020. The patio paving slopes towards the house. This causes rainwater to flow towards the house and enter the subfloor. This is a defect the insurer is responsible for rectifying.
The complainant says water entering the subfloor has caused foundation movement. If this is correct, it means rectification of the 2020 repairs will include repairing the foundations and repairing cracks caused by movement.
Insurer’s engineers say movement caused by multiple factors
The complainant said the storm in February 2020, combined with the defective repairs in 2019, caused cracking in the external brickwork. However, some of this cracking was visible in photographs taken from the street in 2014. Determination 890960 concluded neither the storm in February 2020 nor the defective repairs in 2019 contributed to the cracking.
The insurer appointed an engineer (CD), who inspected the home on 15 April 2020 and prepared a report dated 30 April 2020. This was before the completion of the 2020 repairs, which occurred between March 2020 and August 2020. CD’s report said:
· the house had minor cracking consistent with ‘normal and expected thermal expansion’
· there were no signs of building movement caused by the storm in February 2020.
CD inspected the home again on 17 February 2022 and prepared a supplementary report dated 7 March 2022. The report said:
· the cracking and movement had not noticeably worsened since its previous inspection on 15 April 2020
· the cracking was consistent with ‘normal and expected thermal expansion’ and differential footing movement. Differential footing movement was caused by seasonal moisture variation, a nearby tree, and inadequate surface drainage (the report said there was poor drainage at the north-east corner of the property but did not explain why).
The insurer appointed another engineer (EE), who inspected the home on 9 January 2023 and prepared a report dated 23 January 2023. The report said:
· there had been no significant change in floor levels, foundation movement, or cracking since CD’s inspection on 17 February 2022
· the signs of movement and cracking in the property were ‘typical for the age and construction type of the dwelling’.
The insurer appointed another engineer (VV), who inspected the home on 19 October 2023. VV’s inspection focused on the patio area. VV produced a report dated 3 November 2023 which said:
· the patio paving bricks were uneven and sloped towards the building. The strip drain was undersized and improperly installed
· the property had other structural issues which were outside the scope of its investigation, including:
> timber rot concentrated in the area under the bathroom/laundry, suggesting a leak (an inspection by the insurer’s builder on 4 December 2023 found no leaks in the bathroom, but an inspection by the complainant’s building inspector on 19 November 2024 found a visible leak in the shower and water damage in the subfloor)
> a hole excavated in the south-west corner of the subfloor, potentially compromising the foundations. The footings in this area seemed to have been partially demolished
> numerous cracks throughout the interior and exterior (some of which had been patched), suggesting ongoing foundation movement
> poor drainage generally (the back yard sloped towards the house), allowing water to flow into the subfloor
· floor levels were ‘well within expected tolerances’. VV did not believe the foundations had been impacted by runoff from the patio (or the suspected leak under the bathroom).
VV provided a second report dated 10 February 2024. The complainant says VV did not inspect the property a second time. VV’s second report said:
· the damage to the home could be attributed to long-term changes in soil moisture
· changes in soil moisture were caused by multiple factors, including:
> poor site drainage from the back yard
> permeable (i.e. unpaved) surfaces next to the house
> a large tree next to the north-east corner of the house
> plumbing issues in the bathroom/laundry area
> poorly maintained roof drainage and downpipes, which directed water to the founding soils
> the patio strip drain being poorly maintained and regularly overflowing
· the patio paving was sloped towards the house. This would encourage moisture to accumulate under the house but was not the dominant cause of the damage.
Complainant’s experts say movement caused by poor drainage
The complainant appointed a building inspector, who inspected the home on 19 November 2024 and said:
· site drainage was ‘inadequate… due to poor pavement works that directed water into the subfloor area’
· the poor drainage was the likely cause of external and internal cracking.
The complainant appointed an engineer, who inspected the home on 3 August 2023 and said:
· the stormwater system in the south-west corner was improperly installed (the patio paving and strip drain are in the south-east corner)
· this led to water saturation in the soil, causing heave (upward movement) of the footings.
The complainant’s engineer inspected the property again on 11 January 2024 and said:
· incorrect installation of the patio paving directed water under the house via the subfloor access door
· this water ‘would be affecting the foundations’. It may have softened the soil, leading to settlement (downward movement) of the footings.
Floor level surveys showed little movement
CD conducted a floor level survey on 15 April 2020. The survey showed floor levels varied by up to 15mm. CD said this was ‘relatively level’. CD said the survey showed ‘no concerning trends, or signs of significant building movement’.
CD conducted another floor level survey on 17 February 2022. The survey showed floor levels varied by up to 11mm. CD said the movement had not noticeably worsened since its previous inspection.
EE conducted a floor level survey on 9 January 2023. The survey showed floor levels varied by up to 13mm. EE said no significant movement had occurred since CD’s inspection.
The complainant’s engineer conducted a floor level survey on 3 August 2023. The survey showed floor levels varied by up to 23mm. The complainant’s engineer did not say how significant this was, or how it compared to previous surveys.
VV conducted a floor level survey on 19 October 2023. The survey showed floor levels varied by up to 18mm. VV’s report said floor levels varied by up to 16mm (apparently overlooking one of the measurements), which it described as ‘moderate’, ‘relatively level’, and ‘well within expected tolerances’. VV said there was a widespread pattern of fall towards the north, with no ‘pattern of localised movement’.
The complainant’s engineer inspected the home again on 11 January 2024. The complainant’s engineer did not do another floor level survey, but measured the exterior brickwork. This showed a level variation of up to 20mm, with a downward slope to the north. This was consistent with the floor level surveys, which generally showed lower floor levels in the north.
The floor level surveys indicate parts of the floor may have moved, relative to other parts of the floor, by up to 12mm between February 2022 and August 2023. According to the engineers’ reports, this degree of movement is not significant.
No pattern of movement around patio or strip drain
The patio paving is along the east side of the house. The strip drain is at the south-east corner. There is no clear pattern of movement along the east side of the house, or around the south-east corner.
The complainant’s engineer said the patio paving directed water under the house via the subfloor access door (near the middle of the east side of the house). However, there is no clear pattern of movement around this location.
The north-west corner of the house was one of the highest points in the 2020 floor level survey, but one of the lowest points in the 2023 floor level survey. The complainant says this shows the north-west corner of the house has dropped significantly. The defective strip drain is at the opposite corner of the house. It is possible that water could have entered the subfloor from the east, flowed over the soil, and pooled in the north-west corner, causing localised foundation movement. However, there is no persuasive evidence that this occurred. As stated above, the degree of movement shown in the floor level surveys was not significant.
EE’s report of 23 January 2023 includes a photograph taken from the street in 2014. The photograph shows cracking to the brickwork in the north-west corner. This indicates the foundations in the north-west corner had a history of movement before 2020. The information provided by the parties does not show the pattern of movement in the north-west corner changed after the insurer’s repairs in 2020.
No sign movement or cracking has worsened since 2020
The complainant says the house has major structural damage. However, the engineers said the degree of movement and cracking evident in the house was normal for a building of its type and age.
The complainant’s building inspector said the external and internal cracking was likely caused by poor drainage. However, the building inspector did not distinguish between cracks that were present before the 2020 repairs and cracks that appeared afterwards. The home has had visible external cracks since at least 2014.
The expert reports show there is internal and external cracking throughout the house. However, none of the expert reports show the cracking has become worse since 2020.
Insured work did not contribute to building movement or cracking
The 2020 repairs directed water under the house. However, the information provided by the parties does not show this water caused any damage to the house.
The house has a history of movement and cracking that is normal for a building of its age and type. The information provided by the parties does not show the pattern of movement changed, or the cracking became worse, after the 2020 repairs.
2.3 How should the 2020 claim be settled?
The insurer must rectify the 2020 repairs. If the complainant does not allow this, the insurer must pay the complainant the reasonable cost of rectifying the 2020 repairs.
Determination 890960 requires insurer to rectify 2020 repairs
Determination 890960 said the complainant could choose whether to accept a cash settlement for the cost of rectifying the 2020 repairs or have the insurer rectify the 2020 repairs. The complainant chose to have the insurer rectify the 2020 repairs.
The insurer must rectify the 2020 repairs. This includes:
· demolishing and rebuilding the patio
· re-laying or replacing the pavers, ensuring they do not direct water under the house
· rectifying the strip drain.
Rectification of the 2020 repairs does not include foundation repair, underpinning, restumping, or relevelling, and it does not include repairs to internal or external cracks.
Complainant has not allowed insurer to rectify 2020 repairs
The insurer says it attempted to rectify the 2020 repairs in accordance with Determination 890960, but the complainant refused to allow its builders onto the property.
The complainant says he never refused the insurer’s builders access to the property. He says he is willing to allow the insurer’s builders to access the property, except the builder who performed the 2020 repairs.
On 24 April 2024, the insurer offered to appoint a new builder (AB) ‘to conduct/explore restoration works/make safe works that would lead to your property being rendered liveable and you able to move back into the property’. The insurer did not say what work this would include. It said AB may need to inspect the home to determine what work was required to make it liveable.
On 24 April 2024, the complainant replied to the insurer’s email. He rejected the insurer’s offer, citing ‘the unsatisfactory quality of work performed by your previous contractors’. He said he would wait for AFCA’s determination.
On 24 June 2024, the complainant said no work could be done on the property until the insurer agreed to repair the foundations. For the reasons stated above, the insurer is not required to repair the foundations.
Having considered the information provided by both parties, I am satisfied the complainant has not allowed the insurer to repair his property.
Insurer must cash settle claim if complainant will not allow repairs
The complainant has not allowed the insurer to rectify the 2020 repairs. However, if the complainant allows it, the insurer could still rectify the 2020 repairs.
The insurer has not said it is no longer willing to rectify the 2020 repairs. It has not provided information showing the delay has made it impossible to rectify the 2020 repairs or increased the cost of doing so.
If the complainant accepts this determination, the insurer must appoint a builder to rectify the 2020 repairs. If the complainant does not allow the insurer’s builder to complete the work, the insurer must settle the 2020 claim by paying the complainant the amount quoted by the insurer’s builder for any outstanding work.
2.4 How should the 2019 claim be settled?
The insurer cannot obtain a quote from the complainant. Therefore, it should obtain its own quote for rectification of the 2019 repairs. It should pay the quoted amount, plus 20% for contingencies. It should pay for mould remediation and (if required) asbestos removal.
Determination 937642 requires cash settlement based on complainant’s quote
On 11 August 2019, the complainant’s home was damaged by rain entering through roof tiles. The damage was to the bathroom and open plan area (kitchen, lounge and dining room).
The complainant said other areas (including the roof) were also damaged by the storm. However, Determination 937642 concluded there was ‘no satisfactory evidence’ of this.
The insurer appointed a builder to repair the damage. The repairs were defective.
Determination 937642 said the 2019 claim should be settled as follows:
· the complainant must nominate two building companies
· the insurer must select one of these builders to prepare a quote to rectify the 2019 repairs
· the insurer must pay the complainant the quoted amount, plus 20% for contingencies.
Complainant’s builder refuses to provide quote
The complainant nominated two builders. The insurer chose one of them.
On 10 August 2023, the complainant’s builder inspected the property. Between August 2023 and January 2024, the insurer repeatedly asked the builder to provide its quote.
On 18 September 2023, the builder told the insurer its quote was ‘95% complete’ and it would submit it the next day.
On 15 January 2024, the builder told the insurer:
This particular property whilst I have been to site has a problematic foundation and water laying underneath the house.
Until such time as these matters are resolved I will not be forwarding any quote…
On 16 January 2024, the builder told the insurer:
The facts are I can not and will not provide a quote until such time as the building is stabilised…
No justification for refusal to provide quote
The complainant’s builder said it cannot provide a quote because of the property’s foundation and drainage issues.
The insurer is not responsible for repairing the building’s foundations.
The insurer is responsible for rectifying the drainage issues around the patio (and has agreed to do so). However, the information provided by the parties does not show the drainage issues are damaging the areas affected by the 2019 repairs. Even if they were, this would not prevent a builder from providing a quote to rectify the 2019 repairs. There is nothing to stop the complainant’s builder from providing a quote while noting:
· it is not willing to perform the quoted work unless the property’s foundations and drainage are improved
· if the property’s foundations and drainage are improved, its quote may be outdated by the time the improvements are complete
· if the property sustains further damage (because of foundation and drainage issues, or for any other reason), this could increase the cost of repairing it.
The complainant refuses to appoint another builder, or allow the insurer to appoint another builder, to provide a quote to rectify the 2019 repairs. He says the insurer obtaining a quote from another builder would breach Determination 937642.
Quote from complainant’s builder not reliable
The complainant’s builder refused to provide a quote to rectify the 2019 repairs. However, the complainant’s builder provided a quote for repairs to the complainant’s home. The quote was dated 7 February 2025 and totalled $197,970.30.
The quote did not claim to be limited to the cost of rectifying the 2019 repairs. The 2019 repairs were to the bathroom and the open plan area (kitchen, lounge and dining room). Most of the quote was for unrelated work, including:
· demolition of the bathroom, kitchen, and laundry
· new flooring in three bedrooms
· repairs to the roof and eaves
· foundation repair and relevelling
· replacement of the patio and paving (to be arranged by the insurer in settlement of the 2020 claim).
The complainant’s builder’s quote cannot be used to determine the cost of rectifying the 2019 repairs.
Insurer should obtain quote to rectify 2019 repairs
Determination 937642 requires the insurer to settle the 2019 claim based on a quote by the complainant’s builder.
The complainant’s builder refuses to provide a quote. Therefore, the 2019 claim cannot be settled in accordance with Determination 937642.
As the insurer cannot obtain a quote from the complainant, it should obtain its own quote for the rectification of the 2019 repairs.
Insurer must arrange inspection to obtain new quote
In February 2023, the insurer obtained estimates of $15,876 and $17,812 to rectify the 2019 repairs. Determination 937642 said these estimates could not be relied upon because they were prepared by interstate builders who did not inspect the property and were not going to do the repairs.
AB provided a quote dated 17 January 2025 totalling $8,591.88. The insurer has offered to appoint AB to do the repairs. However, the complainant says the quote was prepared by an interstate office of AB without inspecting the property. The insurer has not refuted this. I am not satisfied AB’s quote is reliable.
The insurer must arrange an inspection of the property by a builder who can provide a quote to rectify the 2019 repairs. The insurer must act fairly in obtaining the quote, taking all reasonable steps to ensure the quote accurately assesses what the complainant would have to pay to have the work done. The insurer must pay the quoted amount, plus 20% for contingencies. If the complainant does not allow an inspection, the insurer must settle the 2019 claim (excluding mould remediation and asbestos removal) by paying $10,310.26 (AB’s quote of $8,591.88, plus 20% for contingencies).
Insurer must pay for mould remediation
Determination 937642 says the rectification of the 2019 repairs should include mould remediation.
The complainant’s builder provided a mould remediation quote dated 3 July 2024 totalling $25,703.70. The quote included the removal of all flooring and ceiling insulation in the home. The information provided by the parties does not show this work is necessary for mould remediation.
AB provided a mould remediation quote dated 8 January 2025 totalling $7,816.12. The quote only included mould removal in the bathroom, patio, and crawlspace. It did not include the cost of removing any concealed mould.
The insurer’s restorer inspected the property on 9 December 2024, and said:
· there was mould in the bathroom ceiling lining
· the restorer ‘reasonably suspected’ there was concealed mould under the carpet outside the bathroom, in the bedroom next to the bathroom, in the eaves outside the toilet, and in wall cavities in the bathroom and dining room
· the home was suspected to have ‘abnormal settled mould ecology’ because drying fans had been directed into the ceiling cavity, blowing dust and debris throughout the home.
The extent of mould contamination in the property is unknown. Therefore, it is not possible to determine the cost of mould remediation.
The insurer must arrange a further inspection to determine the extent of mould contamination in the property. This will include invasive tests (such as removing skirting boards and wall lining). After determining the extent of mould contamination, the insurer must obtain a quote for mould remediation. The insurer must pay the quoted amount, plus 20% for contingencies.
If the complainant does not allow a further inspection (including the invasive tests required to search for concealed mould), the insurer may settle the mould remediation aspect of the claim by paying $9,379.34 (AB’s quote of $7,816.12, plus 20% for contingencies).
Insurer must determine whether property requires asbestos removal
The complainant says drying fans directed into the ceiling blew asbestos dust throughout the home.
The restorer’s report said a sample taken from the kitchen tile underlay contained asbestos. It did not say what the source of the asbestos was, or whether it was dangerous. It did not say why the kitchen floor was the only place tested for asbestos.
The restorer’s report said ‘appropriate measures should be implemented’ if the kitchen tiles are stripped out. This suggests the asbestos will not pose a threat if the kitchen tiles are left in place.
The restorer’s report said:
· the kitchen kickboards should be removed to inspect the cabinets for water damage
· if the cabinets have water damage, they should be disposed of
· no excess moisture was detected in the kitchen tiles.
This indicates it is unlikely that the kitchen tiles will need to be stripped out, which may mean the asbestos does not pose a threat. However, the report does not conclusively state that asbestos removal is not required. None of the other expert reports say whether asbestos removal is required. The insurer has not commented on the discovery of asbestos at the property.
The insurer must arrange a further inspection to determine whether any asbestos removal is required for the rectification of the 2019 repairs. If required, the insurer must obtain a quote for asbestos removal. The insurer must pay the quoted amount, plus 20% for contingencies.
2.5 Is the insurer required to pay more for accommodation?
No. The complainant has not repaired the home and has not allowed the insurer to repair the home. It would not be fair to require the insurer to pay for further accommodation.
Complainant has not allowed insurer to repair home
In November 2023, the complainant said there was mould in his home. The insurer arranged temporary accommodation for the complainant because of the alleged mould issues. The insurer paid for the complainant’s accommodation from 4 December 2023 to 26 June 2024.
On 23 April 2024, the complainant proposed that the insurer buy a caravan for him to live in.
On 24 April 2024, the insurer offered to appoint a builder (AB) to make the home liveable. The insurer offered to pay for temporary accommodation for the duration of AB’s work. The complainant rejected this offer.
On 7 June 2024, the insurer said it would not pay for accommodation after 26 June 2024 because the complainant had not allowed mould remediation work.
Insurer not required to pay more for accommodation
The complainant has not arranged any repairs to his home and, since 24 April 2024, has not allowed the insurer to repair his home.
The complainant’s email of 24 April 2024 said he was rejecting the insurer’s offer to appoint a builder because of ‘the unsatisfactory quality of work performed by your previous contractors’. The insurer arranged repairs (by different builders) in 2019 and 2020, and both sets of repairs were defective. In the circumstances, it is understandable that the complainant would be reluctant to allow the insurer to arrange further repairs. However, if the complainant was not willing to allow the insurer to arrange repairs, it was incumbent on him to arrange repairs himself.
On 24 April 2024, the insurer offered to appoint its builder to make the home liveable. If the complainant accepted this offer (or appointed his own builder to make the home liveable), it is likely the home would have been liveable by 26 June 2024. In the circumstances, it would not be fair to require the insurer to pay for further accommodation.
2.6 Is the complainant entitled to other compensation?
No. The previous determinations awarded $4,000 compensation for non-financial loss. Since the determinations were issued, the insurer’s handling of the claims has been reasonable. The insurer is not required to pay further compensation for non-financial loss.
AFCA can award compensation for non-financial loss
Under the AFCA Rules, we can award up to $6,300 compensation for non-financial loss if a complainant suffered an unusual degree of stress, inconvenience, or delay because an insurer mishandled a claim.
We do not award compensation for the usual amount of inconvenience involved in making a claim. We do not award compensation for delays caused by the complainant, or other factors outside the insurer’s control.
Determinations 890960 and 937642 each awarded the complainant $2,000 compensation for non-financial loss. This settles the complainant’s entitlement to compensation for non-financial loss to the date of the determinations, 31 May 2023. I have considered whether the insurer has mishandled the claims since 31 May 2023.
Insurer not required to pay further compensation for non-financial loss
The insurer has done everything it reasonably could have to comply with the determinations.
Determination 937642 required the insurer to settle the 2019 claim based on a quote from the complainant’s builder. The insurer could not do this because the complainant’s builder refused to provide a quote. The insurer offered to obtain a quote from another builder nominated by the complainant, obtain a quote from its own builder, or appoint its builder to repair the home. The complainant rejected these options.
Determination 890960 required the insurer to appoint a builder to rectify the 2020 repairs. The insurer could not do this because the complainant has not allowed the insurer’s builders to repair his home.
The insurer said the installation of the strip drain was not part of the insured repairs. I have concluded the insurer was wrong to take this position. However, from 21 February 2024, the insurer agreed to cover the costs of rectifying the drainage issues around the patio. The insurer’s denial of responsibility for the strip drain did not ultimately delay the resolution of the claims.
The complainant made submissions to AFCA in February 2025, and the insurer did not respond to those submissions until July 2025. However, this did not delay the resolution of this complaint.
Since 31 May 2023, the insurer has not made any errors that caused the complainant to suffer an unusual degree of stress, inconvenience, or delay. Therefore, the insurer is not required to pay further compensation for non-financial loss.
2.7 Why is the outcome fair?
This determination requires the claims to be settled in accordance with previous determinations, to the extent this is possible. Where the claims cannot be settled in accordance with previous determinations, this determination provides alternative methods of settlement to finalise the disputes.
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:
· the legal principles
· applicable industry codes or guidance
· good industry practice
· previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. I have reviewed and considered all of the information the parties have provided.
While the parties have raised a number of issues in their submissions, I have restricted this determination to the issues that are relevant to the outcome.