Determination 12-00-1083698

Declined stormwater ingress damage claim due to non-compliant v-gutter

FirmAllianz Australia
Decided2025-01-13
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The insurer declined an internal water damage claim because a v-gutter was non-compliant. AFCA required the insurer to cover the internal damage repair, but not the cost of bringing the gutter up to standard.

The insurer and its consultants failed to identify and disclose the non-compliant gutter during an earlier claim, so it is fair to cover this one-time damage, though rectification remains the complainant's responsibility.

Issues

Subjects and remedies

home or building damagepay claim

Related

All Allianz Australia determinations · Find similar determinations

Text of the determination

Determination | Case number | 12-00-1083698 | Financial firm | Allianz Australia Insurance Limited Case number: 12-00-1083698 29 November 2024 Determination overview Complaint The complainant holds a home building and contents policy (policy) with the financial firm (insurer). On 22 February 2024, a claim was lodged for stormwater ingress damage to the insured building. The insurer has declined the claim. It says the stormwater ingress and associated building damage is due to a non-compliant v-gutter on the roof, which due to poor drainage is unable to remove rainwater adequately. This caused overflow into the ceiling below. The policy does not cover loss or damage due to inherent defects, faulty design, structural defects or poor workmanship. The complainant disputes the insurer’s position and says he had arranged maintenance works to the gutter in question on the insurer’s instructions under a previous claim in 2021. Further, that these works were arranged via a consultant ‘C’ introduced to him through the insurer’s agent’s ‘P’. Issues and key findings Is the insurer entitled to decline the claim? No. It is fair in all the circumstances that the insurer be required to cover the complainant for the claimed internal stormwater ingress damage under the claim. However, the insurer is not obliged to cover the costs associated with ensuring the v-gutter is compliant with the relevant Australian Building Standards (Standards) moving forward. Why is the outcome fair? The outcome is fair because the insurer, despite having arranged assessments of the roof (including the v-gutter) by multiple consultants under the 2021 claim (Claim 1), failed to identify and inform the complainant that the v-gutter was non-compliant. The complainant arranged all the maintenance works recommended by the insurer through its consultants’ ‘T’ and P. It is fair in all the circumstances to accept that had the insurer made the complainant aware of the non-compliant gutter, he would have had it rectified in 2021-2022 (and the present damage would not have occurred). However, it would be unfair to require the insurer to cover the costs associated with ensuring the v-gutter is rectified to meet the relevant standards. This responsibility rests with the complainant. Determination This determination is in favour of the complainant. The insurer is to accept the claim and cover the complainant for the cost to repair the internal stormwater ingress damage. However, the insurer is not required to extend cover for the cost to rectify the non-compliant v-gutter and any associated maintenance works. Reasons for determination Is the insurer entitled to decline the claim? No. It is fair in all the circumstances that the insurer be required to cover the complainant for the claimed internal stormwater ingress damage under the claim. However, the insurer is not obliged to cover the costs associated with ensuring the v-gutter is compliant with the relevant Australian Building Standards (Standards) moving forward. Circumstances relevant to the consideration of this complaint I have considered all the exchanged information and am satisfied it establishes the following: on 15 November 2021, the complainant lodged Claim 1 for hail damage to the insured building. The insurer arranged for P to assess the damage who in turn appointed roof specialists T to complete a roof inspection based on the reports from P and T the insurer partially accepted the claim and informed the complainant of maintenance works he would need to arrange based on the recommendations put forward by T and P the complainant arranged for the recommended works (including to the roof gutters) to be completed by C through a private arrangement. However, C’s works were based entirely on the recommendations provided by T and P on completion of these maintenance works, P completed the internal stormwater ingress damage repairs on 22 February 2022, Claim 2 was lodged for stormwater ingress damage where the complainant advised that the building was experiencing similar damage subject of Claim 1, and he was unsure if this was a warranty issue or potentially new damage the insurer has declined the claim on the basis the building damage stems from the non-compliant v-gutter and this is excluded under the policy. Complainant arranged maintenance works based on insurer’s instructions The insurer arranged for P to assess the damage claimed under Claim 2. P appointed roofing specialists ‘ND’ to inspect the roof. In its report from 4 March 2024, ND concludes that the water ingress and associated damage is due to the non-compliant v-gutter (that does not meet the requirements of Standard SA HB39). In its report dated 4 March 2024, P reiterates the findings provided by ND and concludes that the recent water ingress damage relates to the pre-existing non-compliant v-gutter. Further, that it appears the previous repairs to the roof were not completed correctly and/or have failed. P points out that the previous repairs were completed by the complainant and not the insurer. I have carefully considered the information relating to Claim 1. This includes reports from P, T, C and communication between the insurer and the complainant. I am satisfied that none of this information shows that the insurer or any of its appointed consultants identified the issue with the v-gutter as being non-compliant. Neither did any of these parties inform the complainant the v-gutter was non-compliant. Rather, I am satisfied all of the reports and communication with the complainant consistently identify a need for maintenance works that include replacement of the three valley gutters. I am satisfied that the wording in the reports from P, T and communications to the complainant from the insurer is consistent, if not identical, in this regard. I am also satisfied this very same wording is then included in the scope of works and quote provided by C dated 14 February 2022. That is, C’s scope of works is based on and consistent with the recommendations to the complainant by P, T and the insurer. I accept the complainant proceeded to arrange all the maintenance works he was recommended to complete by these parties. It is fair that the insurer be required to cover internal water ingress damage I accept the insurer’s position that the recommended maintenance works were completed by C through a private arrangement with the complainant and were not authorised under the claim. I also accept in most circumstances, this would mean the insurer is not responsible for any issues that may arise from such works. However, I am not satisfied it is fair to apply that approach to these particular circumstances because: the complainant is not an insurance professional or qualified tradesperson and as such he was guided by the actions and information provided by the insurer and its consultants the complainant was upfront with the insurer about the age of the property and previous attempts to repair it as well as the need to undertake further maintenance works the insurer and its consultants, who are experts in their fields, did not identify the v-gutter as being non-compliant during their multiple assessments nor was the complainant at any time placed on notice regarding this issue the reports from the consultants do include reference to other issues considered non-compliant and/or unwarrantable, but not the v-gutter the list of recommended maintenance works from T, P and the insurer are consistent C’s scope of works and therefore repairs completed were based entirely on these consistent recommendations from P, T and the insurer had the insurer and its consultants identified the v-gutter as being non-compliant and requiring rectification, it is more likely than not the complainant would have arranged for this in 2021-2022 although C and the complainant did enter into a private arrangement for the maintenance works, the complainant was introduced to C through T. It is fair to accept given this, the complainant will have drawn confidence that C was a reliable option. I am satisfied it is fair in all the circumstances to accept the insurer and its consultants failed to identify that the v-gutter was non-compliant under Claim 1. Given this, the insurer and its consultants failed to inform the complainant of the non-compliant v-gutter and requirement to have this issue rectified. It is also reasonable that the complainant accepted and was of the opinion in arranging all the recommended maintenance works, he would meet the requirements of cover under the policy. I accept that if the insurer had informed the complainant of the issue, the v-gutter would have been rectified in 2021-2022 and the water ingress damage the subject of Claim 2 would most likely not have occurred. Insurer is to cover the water ingress damage under Claim 2 Given the insurer’s failure to identify and inform the complainant of the non-compliant v-gutter under Claim 1, I am satisfied it is fair the insurer cover the complainant for the cost to repair the water ingress damage which is the subject of Claim 2. However, to avoid any confusion, this is a one-time allowance only. The complainant is now on notice regarding the non-compliant v-gutter, and it is his responsibility to arrange for its rectification. A failure to do so, and associated further water ingress damage moving forward, is excluded from cover in line with the policy. Within 21 days of receiving notice of the complainant’s acceptance of this determination, the insurer is to make arrangements for the assessment of, scope of works and costing to repair the water ingress damage. Within 7 days of receiving the scope of works and quote, the insurer (at its discretion), is to either authorise the repairs or cash settle the complainant for the cost of repairs. If the claim is cash settled, the insurer is to increase the cash settlement by a further 10% to allow for contingencies and a loss of the policy’s repair guarantee. Why is the outcome fair? The outcome is fair because the insurer, despite having arranged assessments of the roof (including the v-gutter) by multiple consultants under the 2021 claim (Claim 1), failed to identify and inform the complainant that the v-gutter was non-compliant. The complainant arranged all the maintenance works recommended by the insurer through its consultants’ T and P. It is fair in all the circumstances to accept that had the insurer made the complainant aware of the non-compliant gutter, he would have had it rectified in 2021-2022 (and the present damage would not have occurred). However, it would be unfair to require the insurer to cover the costs associated with ensuring the v-gutter is rectified to meet the relevant standards. This responsibility rests with the complainant. Supporting information The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to: the legal principles applicable industry codes or guidance good industry practice previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all the information the parties have provided. While the parties have raised several issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider: available documents the recollections of the parties all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.