Determination 12-00-1082603

Missed internal water damage repairs and storm claim handling

FirmSuncorp Group
Decided2025-01-03
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$1,000
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

A homeowner complained about handling of a storm claim, including missed internal water damage repairs and utility costs during repairs. AFCA found the insurer handled the claim reasonably overall, but ordered it to pay $1,000 compensation because its builder missed some internal damage and the utility costs were incurred.

The insurer is responsible for its builder's missed scope of work, but delays were caused by the complainant's roof repairs and travel, so only a modest compensation award is fair.

Issues

Subjects and remedies

home or building damagenatural disasterpay compensation

Related

All Suncorp Group determinations · Find similar determinations

Text of the determination

Determination | Case number | 12-00-1082603 | Financial firm | AAI Limited Case number: 12-00-1082603 25 November 2024 Determination overview Complaint The complainant lodged a claim with the financial firm (insurer) under his home insurance policy. This is for the damage sustained to the property as a result of a storm. The insurer accepted the claim and repaired the internal water damage to the property. The complainant is dissatisfied with the insurer’s handling of the claim and seeks compensation. Issues and key findings Is the insurer liable for compensation? The insurer is required to pay the complainant $1,000 compensation. Why is the outcome fair? Compensation is warranted due to the missed internal repairs and electricity and water usage during the repairs. Determination This determination is in favour of the insurer. The insurer is required to pay the complainant $1,000 in compensation. Reasons for determination Is the insurer liable for compensation? The insurer is required to pay the complainant $1,000 compensation. No dispute the storm caused internal damage to the property The following relevant facts are not in dispute: the complainant lodged a claim for storm damage to his property in February 2024 the insurer accepted the claim for the internal damage caused by the storm the complainant’s builder rectified the warranty related issues with the roof the insurer carried out the make safe repairs to the roof. The complainant is dissatisfied with the insurer’s handling of the claim. Amongst other things, the complainant says the insurer missed damaged areas causing unnecessary repairs. The complainant is seeking compensation for the electricity and water used during the repairs. Further, he is seeking compensation for the stress and inconvenience caused by the insurer’s poor claim handling. The insurer handled the claim reasonably overall AFCA may award compensation for non-financial loss if there has been an unusual degree or extent of physical inconvenience, time taken to resolve a complaint or interference with the complainant’s expectation of enjoyment or peace of mind. AFCA takes a conservative approach to awarding compensation. We do not award compensation because the complainant has suffered some inconvenience and delays. AFCA expects complainants to be moderately robust and to bear the normal degree of inconvenience experienced when a problem occurs and to take reasonable steps to manage the situation. The exchanged evidence shows: on 13 February 2024, the complainant lodged the claim on 11 March 2024, the insurer provided the assessment report to the complainant in its letter dated 3 April 2024, the insurer asked complainant to address the non-claim related repairs to the roof on 9 April 2024, the complainant advised the insurer the make safe repairs failure and further water ingress on 11 April 2024, the insurer confirmed that its builder (BB) completed further make safe repairs the complainant’s builder finalised the roof rectification in May 2024 the complainant left for overseas on 14 May 2024 the insurer completed the repairs, including the carpet cleaning in July 2024. The exchanged evidence shows the complainant contacted the insurer after the repairs were finalised, due concerns with missed repairs. The insurer’s builder (BB) assessed the property in August 2024 and concluded that the damage is due to water ingress. The insurer agreed to cover this damage as it was missed off the original scope of work. I accept the initial internal water repairs were delayed until the complainant attended to the non-claim related roof repairs. I accept these delays were outside the insurer’s control. I accept the insurer handled this aspect of the claim reasonably and provided him with the assessment report of the roof. Further, I accept the repairs were delayed by the complainant’s travel arrangements when the repairs could not start until his return. The builder did not have any available dates prior to the complainant’s travel arrangements. There is no persuasive evidence that the habitability of the property has been affected by the extent of the storm-related damage. The scope of work shows that the damage is mostly to plastering and painting. The complainant says the insurer’s make safe repairs failed, causing damage. The exchanged information shows the insurer carried out further make safe repairs and attended to the internal damage. I accept the insurer attended to these issues in a timely manner. I equally accept it is the complainant’s responsibility to attend to any workmanship issues with the roof including any resultant damage. In noting that, the insurer does not dispute that its builder has missed some of the internal water damage which it agreed to rectify. Further, there is no dispute that the complainant incurred electricity and water usage during the course of repairs. I accept there is no persuasive evidence to establish the extent of the cost incurred. For finality, I accept it is fair the insurer pays the complainant $1,000 in compensation. Otherwise, I am satisfied the insurer handled the claim reasonably overall. Why is the outcome fair? Compensation is warranted due to the missed internal repairs and electricity and water usage during the repairs. Supporting information The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to: the legal principles applicable industry codes or guidance good industry practice previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all the information the parties have provided. While the parties have raised several issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider: available documents the recollections of the parties all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.