Home / Suncorp Group / Determination 12-00-1078201
Determination 12-00-1078201
Escape of liquid claim repairs and claims handling
Summary
The complainant claimed further water damage from a 2020 repair and poor claims handling. AFCA decided the insurer must pay $2,000 non-financial loss, refund the excess, cover mould remediation and report, and rectify damage under the lifetime guarantee.
The lifetime repair guarantee in the PDS covers defective workmanship in repairs the insurer authorised, arranged and paid for, and non-financial loss is limited to what is fair for the claims handling.
Issues
- Repairs or contractors primary · upheld
“RC confirmed the toilet was incorrectly installed after initial repairs; insurer accepted all resultant damage under the 2020 claim and lifetime repair guarantee.”
- Poor claim handling secondary · upheld
“The insurer's handling of the claim was acknowledged as stressful; insurer offered $2,000 for dissatisfaction with its claims experience.”
- Delay secondary · not upheld
“Insurer acted promptly and reasonably on being made aware of the complainant's concerns; responses provided within an acceptable timeframe.”
Subjects and remedies
home or building damagepay non financial lossprovide documentsreassess claimrefund fees or chargesrepair or rectify
Text of the determination
Determination
|
Case number
|
12-00-1078201
|
Financial firm
|
AAI Limited
Case number: 12-00-1078201 26 March 2025
Determination overview
Complaint
The complainant holds a home building and contents (policy) with the financial firm (insurer). She lodged a claim for escape of liquid damage in 2020. The insurer accepted the claim, authorised repairs and provided a lifetime repair guarantee.
On 19 February 2024, the complainant lodged a further escape of liquid claim for water damage under the previously repaired bathroom. The recorded date of loss is 15 February 2024. The complainant says:
this damage is a direct result of poor workmanship of repairs performed under the 2020 claim
her overall claims experience is substandard, and the delays are unreasonable.
The insurer says:
it has agreed to all the complainants’ requests to resolve the complaint
$2,000 compensation has been offered to the complainant for her dissatisfaction with her claims experience.
Issues and key findings
Is the insurers offer to resolve the complaint reasonable?
Yes. This is because the insurer has agreed to all the complainant’s requests to resolve the claim and the complaint. The damage has been accepted under the insurer’s lifetime guarantee for works performed under the escape of liquid claim in 2020.
Is the complainant entitled to additional NFL?
No. The insurer has offered $2,000 NFL in response to the complainant’s dissatisfaction with her claims experience. The exchanged information shows the insurer acted reasonably in response to the additional damage reported in February 2024.
Why is the outcome fair?
The outcome is fair because the insurer has accepted the additional damage under its lifetime repair guarantee. All the complainant’s requests have been accepted. The offer of $2,000 in NFL is fair in these circumstances.
Determination
This determination is in favour of the insurer. Within 14 days of receiving notice the complainant accepts this determination the insurer is required to pay the complainant $2,000 NLF. It is also required to pay for the mould remediation and mould report if it has not already done so.
Reasons for determination
I note at the time this complainant was brought before AFCA; the parties were disputing matters relating to medical expenses incurred by the complainant. However, the parties agree AFCA is not the appropriate forum to consider the complainant’s claim for medical expenses due to her injury.
As such, this determination is limited to the claims handling aspect of the complaint and compensation for non-financial loss (NFL).
Is the insurers offer to resolve the complaint reasonable?
Yes. This is because the insurer has agreed to all the complainant’s requests to resolve the claim and the complaint. The damage has been accepted under the insurer’s lifetime guarantee for works performed under the escape of liquid claim in 2020.
2020 repairs covered by a lifetime guarantee
Page 75 of the PDS says;
Lifetime guarantee on home repairs
When we repair or rebuild your home, we guarantee the quality of materials and workmanship of that work for the lifetime of your home if we:
– authorise;
– arrange; and
– pay the builder or repairer directly for this work.
What we guarantee
We guarantee the material used and standard of the workmanship to be free of defects. If a defect arises in the lifetime of your home as a result of poor-quality workmanship or use of incorrect materials, then we will rectify the problem.
The complainant lodged an escape of liquid damage claim in 2020, which was accepted by the insurer. The insurer completed repairs to the property and provided a lifetime repair guarantee.
The complainant lodged a subsequent claim in February 2024. She said the damage is a direct result of poor workmanship of repairs completed under the 2020 claim.
On 27 March 2024, the insurer received notification of the referral to AFCA in which the complainant expressed her dissatisfaction with the delays relating to the progression of the claim.
The insurer completed a review and determined there was insufficient evidence to attribute all damages to poor workmanship in the repairs completed under the previous claim. However, the insurer changed its decision.
In accordance with its lifetime repair guarantee it agreed to cover all resultant building damages as rectification under the previous escape of liquid claim. Additionally, the excess paid on claim notified in February 2024 was refunded to the complainant.
Insurer has offered to resolve the complaint
The insurer has offered to resolve the complaint by agreeing to all the complainant’s requests. These are.
accepting all rectification under the 2020 claim
covering the replacement of all carpet in upstairs area
agreeing to schedule an inspection three months after completion of repairs
refunding the excess charged on the claim notified in February 2024
cash settling the cost quoted by her preferred supplier for mould remediation
reimbursing the cost for an independent mould report.
In addition, the insurer offered to pay $2,000 compensation for the complainant’s poor claims experience. The complainant has rejected the $2,000 compensation offered by the insurer.
Complainant rejects the insurer’s proposed resolution
The complainant is dissatisfied with the insurer’s proposed settlement resolution and says her house has been damaged since 2020, due to the failed repairs. The complainant is of the opinion that AFCA should review:
the whole 2020 repair that led to the escape of liquid/blackwater in February 2024
failure of the insurer’s contracted plumber to fully contain the sewer water which escaped onto the ground floor tiles causing mould in the home
unacceptable delays in the completion of rectification works.
It is not in dispute the property was damaged due to a leak in the upstairs toilet in 2020. In February 2024, the complainant noticed water on the ground floor and water staining to the ceiling above where the water was located. The exchanged information shows she was aware of the staining to the ceiling in late 2023.
She notified the insurer of this subsequent damage. As she was dissatisfied with the initial builder (AB) she did not want the same builder to return to rectify the damage.
The insurer appointed a new rectifying builder (RC) who attended the site on 22 April 2024. In their report of the same date, RC confirmed the toilet was incorrectly installed after initial repairs were complete. It established the subsequent leak had been occurring since AB completed repairs in 2020.
The insurer accepted all resultant damage under the 2020 claim. It arranged RC to prepare a scope of works (SOW).
I am not satisfied AFCA is required to review the whole 2020 repair or the failure of the insurer’s plumber to contain the sewer water that caused further damage. This is because the exchanged information confirms these works are covered under the insurer’s lifetime repair guarantee benefit. Further, that the insurer has accepted to rectify these works and any associated additional damage under this benefit.
The insurer has authorised the necessary investigation into identifying the reason for the failed repairs from 2020, which have been successful. The insurer has also accepted to arrange the required rectification works, which I am satisfied reasonably discharges the insurer’s obligations under the lifetime repair guarantee benefit.
Is the complainant entitled to additional NFL?
No. The insurer has offered $2,000 NFL in response to the complainant’s dissatisfaction with her claims experience. The exchanged information shows the insurer acted reasonably in response to the additional damage reported in February 2024.
Complainant claims entitlement to further NFL
The complainant says she is entitled to additional compensation in recognition of delays and the overall handling of her claim. She says the:
$2,000 offered by the insurer does not adequately compensate her for the distress, trauma, loss of trust, disruption to her life and the inconvenience caused by the insurers claims handling
delays to her own plans for eight months can never be compensated by $2,000
damage has yet to be rectified.
AFCA approach to non-financial loss
Under the AFCA Rules, AFCA can award up to $6,300 compensation for non-financial loss. We will only award this type of compensation if a complainant suffers an unusual degree of stress, inconvenience, or delay because the insurer mishandling the claim.
We recognise making a claim can be stressful and time-consuming, even if the insurer handles the claim correctly. We will not award compensation for the ordinary degree of inconvenience that comes with making a claim.
We may reduce the amount of compensation we award if the loss was partially caused by the actions of the complainant, or by factors outside the insurer’s control.
Insurer’s offer is reasonable
There is no dispute there is a lifetime guarantee on repairs arranged and authorised by the insurer. It has agreed to cover the February 2024 water damage under the 2020 claim.
It is also not in dispute the complainant has experienced stress and inconvenience due to the repairs from the original claim not being completed correctly. She experienced stress, inconvenience and the time taken to finalise the repairs.
Considering AFCA’s approach to compensation for NFL and having reviewed all exchanged material, I consider the insurer’s offer, on balance, is reasonable. I do not consider further compensation is appropriate.
This is because I am satisfied the insurer acted promptly and reasonably on being made aware of the complainant’s concerns. The insurer has taken steps to rectify any error, including offering to complete all rectification works. This is despite having some reservations about whether all the damage claimed is the due to issues with the 2020 repairs.
The insurer, in line with the complainant’s concerns, has also agreed and appointed a different repairer (RC) to complete the rectification works. I am satisfied the insurer’s acknowledgement of and responses to various concerns raised by the complainant have been reasonable and provided within an acceptable timeframe.
To date, the complainant has not signed the building agreement. As the agreement has not been signed, rectification works have not commenced.
While I acknowledge the complainant's claim journey has been highly stressful, I consider the insurers offer fairly compensates the complainant’s dissatisfaction with the insurers claims handling.
I am not satisfied compensation greater than $2,000 is appropriate in the circumstances.
Given the above, within 14 days of receiving notice the complainant accepts this determination the insurer is required to pay the complainant $2,000 NLF. It is also required to pay for the mould remediation and mould report if it has not already done so.
Complainant delaying commencement of repairs
The complainant says rectification works have not commenced. The insurer wants the contract sent to the complainant in July 2024 signed so RC can start the repairs.
While I acknowledge the complainant’s trust deficit in the insurer, I am not persuaded her refusal to sign the building agreement is reasonable.
This is because:
> the insurer has made repeated efforts to respond to the complainant’s concerns. It has provided written assurances to address her unease and agreed to her additional requests. Including:
‒ accepting work not necessarily associated with the failed 2020 repairs (such as replacing the upstairs carpet) and extra inspections on completion of the repairs
‒ clearly outlining the SOW and reiterating repairs continue to be covered under their lifetime repair guarantee
‒ confirming any additional works required to rectify the damage can be submitted as a variation to the SOW by RC for further assessment.
The exchanged information shows the complainant’s ongoing refusal to sign the agreement is causing unnecessary and prolonged delays to the repair works. These delays risk further damage, increased costs and continued disruption to the complainant.
Given the above it is fair the complainant be required to sign the contract within 14 days of accepting this determination. If the complainant refuses to do so, it is fair the insurer be permitted to close the claim until such time the complainant is prepared to allow the works to proceed.
If the claim is closed, it is fair the insurer be permitted to limit its liability to the extent of damage and associated SOW’s proposed by RC i.e. the insurer will not be liable for any increase in or additional damage that may arise due to the delay in the repairs being completed.
Why is the outcome fair?
The outcome is fair because the insurer has accepted the additional damage under its lifetime repair guarantee. All the complainants’ requests have been accepted. The offer of $2,000 in NFL is fair in these circumstances.
Supporting information
The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided.
While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.