Bank processed two construction progress payments to builder, one allegedly on a forged authority

FirmNAB
Decided2025-01-23
ProductCredit · Home loan
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed$150,000
SourceAFCA PDF

Summary

A borrower disputed two construction-loan progress payments totalling $150,000 to a builder, arguing the frame stage was incomplete and the lock-up authority was forged. AFCA found the bank acted on instructions from the borrower's authorised broker and met its obligations, so no compensation is payable.

A lender acting on documents received from an authorised agent meets its contractual obligations, and the contract does not require the bank to inspect or verify construction progress.

Issues

Subjects and remedies

third party authorityno remedy

Related

All NAB determinations · Find similar determinations

Text of the determination

Determination | Case number | 12-00-1078119 | Financial firm | National Australia Bank Limited Case number: 12-00-1078119 23 January 2025 Determination overview Complaint In early 2021, the complainant engaged a builder, Company O, to construct a residential home on property in F Suburb, Victoria (Property F). On 25 August 2021, the complainant signed a building loan agreement with the financial firm (the bank) for a 30-year construction loan in the amount of $528,000 (the loan). Security for the loan was provided in the form of a mortgage over Property F. At all relevant times, the complainant had engaged a mortgage broker, Mr M, (the broker) to act as his agent and the broker had a third-party authority lodged with the bank. Under the terms of the build contract, progress payments were to be made by drawing down on the loan once particular stages of the construction had been completed. The complainant disputes two progress payments (the disputed payments) the bank made to Company O being:  a $60,000 progress payment made on 4 July 2022 for the Frame Stage, and  a $90,000 progress payment made on 25 August 2022 for the Lock Up Stage. The complainant says:  the Frame Stage was not completed (and therefore not eligible for payment), as the bank did not meet its inspection requirements before making the Frame Stage progress payment and  the Lock Up Stage progress payment was not properly authorised as his signature was forged on the request form (he does not dispute he signed the Frame Stage request form). The complainant says, had the bank properly inspected Property F and identified the fraudulent signature on the Lock Up Stage request, the disputed payments would not have been made and he would not have suffered financial loss as the builder has not completed construction and cannot be contacted. The complainant seeks:  the bank’s policy for inspections to be reviewed and amended to require inspections at all stages and  reimbursement of the disputed payments, totalling $150,000. The bank says it conducted an inspection at the Frame Stage, as per its contractual obligations. It was satisfied it was appropriate to proceed on subsequent receipt of the requests to make payments after both the Base and Frame Stages and relied on the apparent similarity in the signatures on both payment request forms to proceed with payments. Issues and key findings Did the bank breach its inspection obligations? No. While the contract provided an option to do so, the bank was not required to conduct inspections or certify completion prior to making the progress payments. Was the bank entitled to process the disputed payments? Yes. The bank received the documentation required under the loan terms and conditions from the complainant’s authorised broker. In circumstances where there was no reason for it to question the advice the broker was giving it was entitled to process the disputed progress payments to the builder. Why is the outcome fair? I sympathise with the complainant’s situation given the conduct of Company O and its failure to complete construction in accordance with the build contract. However, some works were completed and duly authorised, and whether or not the signature on the Lock-Up Stage request was forged by the builder, the request was made by a duly authorised agent of the complainant and the bank processed the payment request in accordance with the loan contract. Determination The determination is in favour of the bank. Reasons for determination Did the bank breach its inspection obligations? No. While the contract provided an option to do so, the bank was not required to conduct inspections or certify completion prior to making the progress payments. The complainant says the bank did not comply with its inspection obligations The complainant says:  the frame stage was not completed when the bank made the first disputed payment  the bank was required to have this stage approved by a building surveyor in its inspection of the frame stage in accordance with section 40 of the Domestic Buildings Contracts Act 1995 (Vic), and by neglecting to do so has not met its inspection requirements and  the bank’s policy ought to be reviewed and amended to require inspection at all stages, so this situation does not occur. As a preliminary issue, AFCA is not a regulator of the financial services industry. The role of AFCA is to consider individual complaints about loss or damage caused by a financial firm’s conduct. The applicable AFCA Rules set out the scope of the complaints we can consider. While there is scope to review whether a bank’s policy or practice has been applied properly, AFCA cannot consider complaints about a financial firm’s general settings for their policies, conduct or operations – these are internal business settings for the respective Boards and managers to determine in the context of the financial firm’s broader legal and regulatory obligations. The requirement for inspections is a setting the bank has imposed to provide some touch points where it can assess the value of the security it has obtained in respect of the monies being lent. Some lenders may wish more frequent, or fewer, inspections than others. This is a matter for each lender and is not a matter which falls within AFCA’s authority to review. However, what can be reviewed is whether a contractual obligation to conduct an inspection has been complied with. The loan contract does not require inspections Relevant clauses of the General Home Loan Terms and Conditions (the terms) are set out in section 3.2 of this determination. Clause 2.4 of the terms relevantly says the bank may not make progress payments unless it:  receives a request from the complainant for the drawing  receives a copy of the relevant registered builder’s invoice and  it is satisfied with any inspection it carries out or requires. There is no general obligation to inspect the property in the contract, nor is there an obligation on the bank to have any particular stage approved by a building surveyor in accordance with s40 of the Domestic Buildings Contracts Act 1995. Instead, the obligations set out in s40 lie with the builder, Company O, and prohibit the builder from requesting progress payments until certain criteria have been met. I am satisfied the Domestic Buildings Contracts Act 1995 does not apply to the bank as the complainant and his solicitor suggest. The bank did not breach its inspection obligations It is important to note the bank generally would not have a ‘fiduciary’ duty or responsibility to its customer. There is no information to show that the relationship between the bank and the complainant in relation to the construction loan was anything other than creditor and debtor. The interactions between the bank and the complainant were commercial in nature related to the bank as a lender and the complainant as a borrower. None of the information provided shows the bank expressly or impliedly undertook to act in the complainant’s best interests in relation to the quality of the construction undertaken by the complainant’s builder. The bank’s conduct in regard to inspections is focused on protecting its security, not on certifying quality of the works as an agent of the complainant. This is specifically noted in clause 2.3(h) of the terms. Clause 2.3(h) states it is not the responsibility of the bank to supervise the building or any aspect of the building work, even though it may inspect the building. However, the complainant says:  the build contract states the Frame Stage is completed once: > the house frame is complete and > external windows are installed.  the bank arranged an inspection on 1 July 2022 and a photograph in the inspection report shows the external windows were not installed as at the time of the inspection  therefore, the Frame Stage was not complete at the time of the bank inspection and the inspection was invalid. As noted above:  the Frame Stage payment was not made until 4 July 2022 and  it was the responsibility of Company O not to request payment until the Frame Stage was complete. In addition, the complainant, or his agent, had the responsibility to verify works had been completed prior to arranging for the progress payment request to be made to the bank. In the circumstances of this complaint, I am satisfied the inspection completed by the bank was undertaken in order to satisfy its internal policies and not to monitor progress, or check the quality of, the build. Was the bank entitled to process the disputed payments? Yes. The bank received the documentation required under the loan terms and conditions from the complainant’s authorised broker. In circumstances where there was no reason for it to question the advice the broker was giving it was entitled to process the disputed progress payments to the builder. The complainant says he did not authorise the second disputed payment The complainant says he did not sign the progress payment authority form to authorise the bank to make the second disputed payment to the builder, and that his signature was forged by the broker. As he does not dispute signing the authority form for the first progress payment, for the reasons set out in section 2.1 above, I am satisfied the Frame Stage progress payment was properly paid. I also note:  the signatures on the two forms bear a significant similarity and it would not be reasonable to expect an untrained eye to identify any discrepancies between the two  the form was provided by a broker authorised to act on the complainant’s behalf and  the available information does not show any reason why the bank should have had any concerns about the authenticity of the signatures. The bank was authorised to act on the broker’s instructions In response to the assertion of a forgery by the broker, the bank has provided the following information:  on 10 August 2021, the complainant signed the bank’s Personal Consent Form which authorised the broker and the broker’s aggregator to act as an agent of the complainant and to provide and receive the complainant’s personal information  the broker emailed the bank: > the builder invoice for the Frame Stage progress payment, and a progress payment authority form signed by the complainant on 14 June 2022 and > the builder invoice for the Lock Up Stage progress payment, and a signed progress payment authority form on 22 August 2022. From the consent form, I am satisfied the complainant intended to, and did, authorise the broker to act on his behalf in respect of the construction loan in so far as being able to lodge documentation containing the complainant’s personal information. The complainant did not authorise the broker to act independently of the complainant in respect of the loan account, however. In this context, I am also satisfied the emails received by the bank were from the duly authorised broker and contained the broker’s instructions to the bank to make the progress payments to the builder. The bank’s requirements to process the second disputed payment were met Even if I accepted the complainant’s submissions the broker had forged his signature on the Lock Up Stage progress payment request, as noted above:  the signatures on both requests were very similar  the requests had been emailed from the same email account, being the broker’s and  the broker was duly authorised to relay a payment instruction on the complainant’s behalf. I am satisfied no information has been provided to show the bank was aware the builder had fraudulently signed the progress payment authorisation form for the Lock-Up Stage or that it was aware the building works were not completed to that point. In the particular circumstances of this complaint, it was reasonable for the bank to accept the payment request. The bank was not required to verify progress under the build contract Setting aside the unsubstantiated potential issue with the signatures, the complainant says the bank also should have known there was an issue with the Lock-Up Stage payment request because it was submitted only 6 weeks after the Frame Stage payment request. He says this was insufficient time for this stage of the building works to have been completed and the bank should have recognised this and not processed the payment. The bank says there is no requirement on it under the loan contract to monitor the progress of the works. Its obligation is to make progress payments in accordance with duly authorised requests received from those authorised to act on the account. I am satisfied the terms only require the bank to make the progress payment on request, although it had the right to require certain documentation prior to doing so. However, as noted above, there was no contractual obligation for the bank to inspect the property independently of the advice received by authorised persons and so the apparent speed of the progress was not a required consideration for the bank’s processing decision. Given the bank:  met its requirements under its internal policy and the terms by receiving a builder’s invoice and a signed progress payment authority form from the broker for the Lock-Up Stage progress payment, and  acted on the authorised instructions relayed by the broker I am satisfied the bank met its obligations when authorising and releasing the Lock-Up Stage progress payment. Why is the outcome fair? I sympathise with the complainant’s situation given the conduct of Company O and its failure to complete construction in accordance with the build contract. However, some works were completed and duly authorised, and whether or not the signature on the Lock-Up Stage request was forged by the builder, the request was made by a duly authorised agent of the complainant and the bank processed the payment request in accordance with the loan contract. The complainant has other sources of remedy for his loss As a final point, it is important to note the available information provided by the parties indicates the complainant was aware the progress payments had been made by the bank to the builder. Despite this, the complainant did not raise any concerns at the time about the payments being made. I do accept however, during this period, the complainant was attempting to contact the builder to ascertain the status of the project. It is clear from the messages provided by the complainant he intended the builder to continue the works under the build contract and to complete the project. While I am satisfied this did not occur and the complainant has been forced to terminate the build contract for non-performance and try to source another builder, this is not due to the conduct of the bank. I note the complainant’s solicitor advises the complainant has submitted a claim on the builder’s insurance on the basis of the disappearance of the builder. This is the appropriate forum for the complainant to seek compensation for the breach of the build contract. Supporting information The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established. Relevant contractual clauses Home Loan General Terms and Conditions How we provide a home loan with building loan conditions 2.3 If your home loan has building loan conditions the following applies to you. (a) We lend you the home loan in a series of advances as the building work progresses; […] (h) We are not responsible for the supervision of the building or any aspect of the building work, even though we may approve an alteration to or inspect the building What must happen – home loan with building conditions 2.4 In addition to the requirements in clause 2.3, we need not lend any part of the home loan until: (a) […] (b) we have received any document or certificate that we require and it is satisfactory to us (including council approved plans and permits, a request form from you for the drawing and a certificate from your architect or builder showing the cost of works covered by the certificate) (c) we are satisfied with any inspection that we may carry out or require; […]