Denial of flood-related internal water damage claim

FirmAuto & General
Decided2024-09-12
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

Homeowners claimed for internal water damage after a February 2022 storm and sought non-financial loss compensation. AFCA found the damage was more likely caused by excluded floodwater and rejected compensation, but directed the insurer to pay for two storm-damaged air conditioning units with the policy excess waived.

Once floodwater mixes with rainwater it is treated entirely as floodwater, so the flood exclusion applied to the internal damage, while the insurer's handling was within the standard timeframe.

Issues

Subjects and remedies

home or building damagenatural disasterpay claim

Related

All Auto & General determinations · Find similar determinations

Text of the determination

Determination | Case number | 12-00-1077887 | Financial firm | Auto & General Services Pty Ltd Case number: 12-00-1077887 12 September 2024 Determination overview Complaint The complainant and his wife hold home building and contents insurance with the financial firm (insurer). The complainant lodged a claim after their home was inundated by water during a severe weather event in late February 2022. The insurer accepted that damage to two air conditioning units located outside the home on the ground was storm related. However, it says the internal damage to the home and its contents was due to flood, which is excluded under the policy terms. The complainant maintains that the initial inundation up to six inches above the home’s floorboards was by ponding rainwater. He wants the insurer to cover the resultant damage (disputed damage) and pay him compensation for stress and inconvenience. The complainant is represented by lawyer L. For brevity’s sake, the complainant and L are referred to below as ‘the complainant’ unless context requires otherwise. Issues and key findings Is the insurer entitled to deny the disputed damage? Yes. The insurer has established it is more likely than not that the disputed damage was caused by floodwater. Is non-financial loss compensation payable? No. I acknowledge that the complainant has experienced stress and inconvenience. However, I am not satisfied that the insurer unreasonably delayed or otherwise mishandled the claim. Why is the outcome fair? It would be unfair to require the insurer to accept the disputed damage given it was more likely than not caused by flood, which the policy excludes from cover. As the insurer handled the claim reasonably overall, it would also not be fair to expect it to pay the complainant non-financial loss compensation. Determination This determination is in favour of the insurer. The insurer is entitled to deny the disputed damage claim. If it has not already done so, the insurer is to in accordance with the policy terms pay the complainant for the two damaged air conditioning units, except that it is to waive the applicable policy excess as it previously offered to do. Reasons for determination Is the insurer entitled to deny the disputed damage? Yes. The insurer has established it is more likely than not that the disputed damage was caused by floodwater. Complainant has shown claimable loss under the policy The complainant is required to show on the balance of probabilities (that it is more likely than not), that he suffered a claimable loss under the policy. This means he must show the loss was caused by a risk for which he is insured. Subject to the terms and conditions set out in the product disclosure statement (PDS), the policy covers damage to the complainant’s home and contents caused by a listed insured event. One of those events is ‘Storms and rainwater’, which includes cover for loss or damage from surface run-off rainwater that occurs within 24 hours of a storm. While the complainant could have added ‘Flood’ to the policy as an insured event, he did not do so. The PDS defines ‘flood’ as ‘the covering of normally dry land by water that has escaped or been released from the normal confines of [relevantly]…a river…[or]…a creek…’. On 14 March 2022, the complainant lodged the claim. He told the insurer that during a storm on 28 February 2022, ponded rainwater inundated the home up to six inches above the floorboards. The home was subsequently more significantly inundated by floodwater. The insurer does not dispute that two air conditioning units located on the ground outside the home (below the level of the floorboards) were completely inundated by ponded rainwater run-off on or about 28 February 2022. It accepted the claim to that extent. I am therefore satisfied that the complainant has a shown a claimable loss under the policy. Once the complainant proves the existence of a claimable loss, the insurer is liable for the loss unless it shows an exclusion or limiting condition applies. The insurer has the onus of proving on the balance of probabilities the application of the exclusion or condition. Insurer denied the disputed damage claim Builder RP inspected the home on 25 March 2022, and reported to the insurer that the water level within the home had reached approximately one metre in height. No ‘top down’ water damage was observed. On 6 April 2022, the insurer’s expert hydrologist WM inspected the property. In its report dated 30 June 2022, WM said: the home is located on B Street, just downstream of the junction of W River with R River. R River is 150m east of the home, S Creek is 1.8km west, and the town drain is 800m west a rain gauge about 3.2km from the home showed 318mm of rain fell in the 24 hours from 9am on 27 February 2022. 203mm of rainfall was recorded between Midnight 27 February 2022 and Midnight 28 February 2022 during the evening on 27 February 2022, the complainant noticed water under the home, about 0.1m below the floorboards. The house is raised 0.85m above the ground, with an estimated floor level of 5.9m Australian Height Datum (AHD). This indicates the water level was at 5.8mAHD the road crest of B Steet near the home is 5.6mAHD. Noting the rainfall volume and given B Street may act as a hydraulic control, the water identified under the home on 27 February 2022 may have been rainwater ponding on B Street at 2am on 28 February 2022, C station gauge 200m downstream from the home recorded the water level at above 5mAHD, which would have led to water breaking out of R River at the northern end of S Creek the complainant’s indication that water came from the property’s front towards the home supports the conclusion that S Creek broke its banks and flowed towards the property as levels continued to rise at the C station gauge into the day on 28 February 2022, the water breaking out of S Creek became muddier due to increased flow coming from R River at S Creek’s northern end at about 9am on 28 February 2022, C station gauge was at 5.9mAHD and rising rapidly later on 28 February 2022, the R River broke over the levee bank, further inundating the town from the east the peak estimated water level in the home, 6.9mAHD, matches well with the peak water level recorded at C station gauge, being 6.8mAHD at 1am on 1 March 2022 while the inundation to 5.8mAHD at the property was due to ponded rainfall run-off, the inundation over the floor was due to floodwaters originating from R River and S Creek. WM subsequently confirmed the timings outlined in the unsigned complainant’s affidavit dated 6 February 2024 were consistent with its report. The report recorded that the complainant said he had evacuated at around 9am on 1 March 2022 and his affidavit stated that occurred at around 8.30am on 28 February 2022. However, the report had also noted the complainant may have been a day out in his recollection given the gauge readings. As the complainant did not purchase optional flood coverage, the policy excludes loss or damage caused by flood. The insurer says the flood exclusion applies to the disputed damage. It notes that once rain and floodwaters mix, they are regarded as floodwater. Complainant says disputed damage should be accepted In his unsigned affidavit dated 6 February 2024, the complainant says: on 27 February 2022, there was a large amount of rain and some pooling on the property that evening more rain fell, and the water level reached about 0.1m below the floorboards. The water level briefly slightly subsided through drainage into drains, but then increased due to further heavy rainfall in the early hours of 28 February 2022 the pooling water came through the floorboards at about 8.30am on 28 February 2022 when the water level reached about six inches above the floorboards, he evacuated to his caravan the water was clear when it first entered the home and when he evacuated to his caravan at about 3pm, he had to move his car and caravan away. He noticed the water was muddy there are stormwater drains on either side of his property, connected by a 600ml pipe, and a drain on his property. Since 1987, he has lodged several complainants with the local council about lack of effective drainage and stormwater build up. The complainant has also provided a letter dated 14 December 2023 from a former local councillor stating the complainant’s town is known to have inadequate drainage. In addition, the complainant has also provided a report dated 30 November 2022 by the CSIRO into the 2022 flooding of the region. The complainant notes that report indicates: the largest rainfall bursts occurred at 3am and 10am on 28 February 2022 soil wetness impacts the amount of water the soil can store before run-off is generated soil moisture levels in the region were particularly high just prior to the flood. The complainant submits that WM’s report is vague and reliant on estimations only, including because ‘mAHD is approximate and there is scope for discrepancy with this data’. Noting WM recorded the ponded rainwater at about 5.8mAHD and his recollection it was clear and continued to rise until it was over the floorboards, the complainant says the insurer has not met its onus to establish on the balance of probabilities the flood exclusion applies. Insurer is entitled to deny disputed damage Based on the exchanged information, I am satisfied that the insurer has established it is more likely than not that the disputed damage was caused by floodwater. This is because: whether rainwater ponded under the home and whether the area has drainage problems is not determinative. Rather, the outcome depends on whether the water that entered the home was floodwater or rainwater WM’s report contains detailed analysis, referencing rainfall and water level recordings, images, graphs and maps. In the absence of any contrary site-specific expert opinion, I find WM’s commentary and conclusions persuasive even acknowledging that some measurements are estimations, WM is of the view that the available data unequivocally supports a finding the home was inundated by flood the onus on the insurer is to show it is more likely than not the inundation was by floodwater, not to prove beyond reasonable doubt that was the case the timing of the largest rain bursts referred to by the CSIRO (3am and 10am on 28 February 2022) relative to when water entered the home (around 8.30am to 9am) supports a finding that the water was not ponded rainfall run-off even if rainwater also contributed to the inundation, it is a well-established principle of insurance law that once floodwater mixes with stormwater, it is all regarded as floodwater. Therefore, the insurer is entitled to deny coverage for the disputed damage. Is non-financial loss compensation payable? No. I acknowledge that the complainant has experienced stress and inconvenience. However, I am not satisfied that the insurer unreasonably delayed or otherwise mishandled the claim. ​AFCA can award compensation for poor claim handling ​​​Under paragraph D.3.3 of the AFCA Rules, we may award compensation for non-financial loss (capped at $6,300) where the insurer’s actions have caused an unusual amount of physical inconvenience, time taken to resolve the situation, interference with the complainant’s expectation of enjoyment or peace of mind. Insurer is not required to pay non-financial loss compensation The complainant seeks a maximum award for non-financial loss due to stress and delay caused by the insurer. Having reviewed the exchanged information, I am not satisfied that the insurer unreasonably delayed or otherwise mishandled the claim. The insurer first informed the complainant of its claim decision on the disputed damage on 12 July 2022. That is within the standard four-month timeframe from claim lodgement referred to in the General Insurance Code of Practice. Accordingly, while I acknowledge that the complainant has experienced stress and inconvenience, the insurer is not required to pay non-financial loss compensation. Why is the outcome fair? It would be unfair to require the insurer to accept the disputed damage given it was more likely than not caused by flood, which the policy excludes from cover. As the insurer handled the claim reasonably overall, it would also not be fair to expect it to pay the complainant non-financial loss compensation. Supporting information The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to: the legal principles applicable industry codes or guidance good industry practice previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. I have reviewed and considered all the information the parties have provided. While the parties have raised several issues in their submissions, I have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider: available documents the recollections of the parties all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.