Home / IAG / Determination 12-00-1077383

Determination 12-00-1077383

Insurer declined claim for structural damage from builder's faulty workmanship that pre-dated policy inception; complainants also alleged misleading conduct and delay

FirmIAG
Decided2026-04-27
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss$2,500
Amount claimed$750,000
SourceAFCA PDF

Summary

Complainants claimed about $750,000 for structural repairs after storm claims; the insurer declined because the faulty workmanship pre-dated the policy. AFCA found for the insurer on the decline and misleading conduct, but required $2,500 non-financial loss compensation for delays.

Structural damage arose during construction in 2017, before the policy period, so no valid claim; delays in responding warranted the offered $2,500 non-financial loss payment.

Issues

Subjects and remedies

home or building damagenatural disasterpay non financial loss

Related

All IAG determinations · Find similar determinations

Text of the determination

Determination | Case number | 12-00-1077383 | Financial firm | Insurance Australia Limited Case number: 12-00-1077383 15 December 2025 1 Determination overview 1.1 Complaint The complainants hold a home insurance policy with the financial firm (the insurer). On 23 January 2020 and 23 May 2022, the complainants made claims for damage to the property following storm events. The insurer partially accepted the claims for internal resultant damage but has declined to cover damage from faulty workmanship by the builder and structural damage which was in existence prior to the policy inception. The complainants lodged tribunal proceedings against the builder and ultimately accepted a cash settlement in full and final resolution of those matters. However, the complainants say that settlement did not cover the full cost of repairs and seeks the insurer pay for all structural repairs to the home, less any amounts received. The complainants also say the insurer misled them throughout the claims process and caused them financial loss. The insurer says it is entitled to decline the claim. 1.2 Issues and key findings Is the insurer entitled to decline the claim for structural damage? Yes. The evidence shows the structural damage was in existence prior to the policy inception. The insurer is therefore entitled to decline the claim for structural repairs as the faulty workmanship occurred outside the policy period and prior to the complainant purchasing the property. Has the insurer misled the complainants? No. The available information does not show the insurer misled the complainants. The complainants have not established they were prejudiced by any information provided by the insurer. They were legally represented during the time of the tribunal hearing and subsequent negotiations and settlement with the builder. Are the complainants entitled to compensation? Yes. At times during the claims process there were delays by the insurer in responding to correspondence. This caused distress and inconvenience to the complainants. The insurer has offered $2,500 in non-financial loss compensation which is adequate in the circumstances. Why is the outcome fair? The insurer’s liability is determined based on the terms of the policy. The policy is clear it does not cover damage which occurred outside the policy period. Whilst the complainants did not discover the damage until they purchased the property, this does not mean it was covered. The complainants have not established the insurer’s actions led them into error. On that basis, it is fair for the insurer to decline the claim for structural damage which is the result of faulty workmanship by the original builder. The complainants have taken necessary action to claim against the builder for his negligence. The insurer is not responsible for any shortfall in funds to repair the structural faults. 1.3 Determination This determination is in favour of the insurer. The insurer is entitled to decline the claim. However, if the complainants accept this determination, the insurer is to pay the complainants a total of $2,500 in compensation for non-financial loss, within 14 days of being notified of their acceptance. 2 Reasons for determination 2.1 Is the insurer entitled to decline the claim for structural damage? Yes. The evidence shows the structural damage was in existence prior to the policy inception. The insurer is therefore entitled to decline the claim for structural repairs as the faulty workmanship occurred outside the policy period and prior to the complainant purchasing the property. Complainants bear onus of establishing a claimable loss It is accepted insurance law that an insured has the initial onus to show on balance of probabilities (that it is more likely than not), that the loss or damage claimed falls within the terms of the policy. Where this is established, the onus then shifts to the insurer to prove that an exclusion applies if it seeks to deny or limit its liability for the loss. There is no dispute the complainant was provided with the policy documents including the Product Disclosure Statement (PDS) and Certificate of Insurance (COI). On that basis, the insurer is entitled to rely on the documents. The complainants hold an accidental damage policy which covers them for sudden and unintended events that occur during the period of insurance. Circumstances of the loss The complainants originally lodged a claim for water ingress in 2020. The complainants told the insurer’s builder on 10 June 2022 that these issues were due to building rectifications from the original builder. The insurer conducted a make safe to the internal ceilings. The complainants lodged a claim against the builder with the Queensland Building and Construction Commission (QBCC). On 12 May 2022, the complainants received the maximum payable under the QBCC scheme of $200,000. The QBCC identified there was a shortfall of $578,635, based on a quote from a builder (DW) lodged as part of that application. After this, the complainants lodged an application in the Queensland Civil and Administrative Tribunal (QCAT). After mediation, the complainants agreed to an amount of $750,000 in full and final settlement of the dispute. The complainants signed a deed of release. The complainants say the settlement amount does not cover all of the damage and seeks that the insurer indemnify them for the difference (of about $750,000). The damage occurred before the period of insurance The complainants lodged a claim under the policy for accidental damage after water entered the property. The insurer says the complainants have made a valid claim for accidental damage for internal resultant damage, but have not made a valid claim for structural defects because this damage did not occur during the period of insurance. It is not in dispute that the structural damage occurred during construction in 2017. The policy was not incepted until 2019 when the complainants purchased the property. On the basis that the structural defects occurred in 2017, they did not occur during the period of insurance, to satisfy the insuring clause. The complainants seek to rely upon two exclusions in the policy, as follows: This policy does not insure you against: 2. damage directly or indirectly caused by or arising out of: · A structural fault, faulty design or faulty workmanship if you knew, or ought to have about the structural fault, faulty design or faulty workmanship and failed to fix it or arrange to have it fixed before the damage occurred or commenced to occur … 15. damage that is recoverable under the terms of a warranty, guarantee, maintenance, service or lease agreement. Essentially, the complainants argue because they were not aware of the structural faults at the time they purchased the property, they should be covered. However, exclusions only apply in circumstances where the complainants have made a valid claim. Because the complainants have not established that the damage occurred during the period of insurance, there is no need for the panel to consider whether any exclusions apply. It does not matter when the complainants noticed the damage. It matters when the damage actually occurred, which in this case was during construction in 2017. It is acknowledged that the complainants were not aware of the structural problems with the property until after the storm event in 2020. The builder’s faulty workmanship became apparent during the assessment of the claim and following engagement of a number of experts including engineers. It is also acknowledged the complainants made a claim through the home warranty insurance scheme and were settled their entitlement. The complainants say since the question of warranty has been removed, they should now be entitled to any shortfall to repair the structural damage and rely on clause 15 under the policy. However, the exclusions are not applicable because the complainants have not established a valid claim under the policy for the structural damage resulting from the builder’s faulty workmanship. On that basis, the panel is satisfied that the insurer is entitled to decline the claim. 2.2 Has the insurer misled the complainants? No. The evidence does not show the insurer misled the complainants. The complainants have not established they were prejudiced by the information provided by the insurer. They were legally represented during the time of the tribunal hearing and subsequent negotiations and settlement with the builder. Complainants’ submissions do not advance their position The complainants say the insurer misled them during telephone conversations, written correspondence, and by failing to respond to email correspondence. The complainants also say the insurer directed them not to use the original builder if not under the direction of QBCC or the policy would be void. They say the builder was refused entry to the property on or about 10 May 2021 because QBCC had closed its files on 5 May 2021. Furthermore, the complainants say the lack of response to their emails about the situation meant the insurer has failed in its duty of care. The complainants were concerned that without clarification from the insurer, the policy would be voided if the builder was allowed back on site. They also claim the insurer indicated they would be covered under the policy because they were not aware of the structural faults and were instructed to pursue a claim through the home warranty insurance scheme first before the claim would be further considered. Available information does not support misleading conduct by the insurer There has been ample correspondence and telephone communication in relation to the denial of the claim and subsequent complaint. The insurer has provided all available telephone recordings, which the panel has listened to. The panel is not satisfied that the insurer has engaged in misleading conduct, as alleged by the complainants. In the original decline letter dated 29 October 2020, the insurer indicated that the damage was not recoverable under the policy because the damage occurred before the policy was incepted. It reiterates this position in its internal dispute resolution response letter dated 8 September 2021. Timeline of events does not assist the complainants In their submissions to AFCA, the complainants say the misleading conduct occurred between August 2020 and September 2021. The complainants say the insurer told them not to allow the original builder back on site to undertake the repairs or the policy would be void. They also say that when settlement negotiations were occurring with the builder, they reached out to the insurer to confirm if any shortfall would be covered and were not provided with a reply. The builder was refused access to the site on 10 May 2021 so as not to void cover under the policy. The complainants state: …in hindsight it is easy to see the matter would have been resolved by letting the builder back on site once a new scope of works was signed off. However, the information exchanged does not support the complainants’ position that misleading conduct by the insurer caused them to act to their detriment or suffer financial loss. The financial loss appears to have resulted from faulty workmanship by the builder, which the complainants sought to rectify to their satisfaction at a cost exceeding the funds received from QBCC and the settlement with the builder. It is acknowledged that the correspondence is extensive and that the complainants were seeking for the insurer to accept liability for damage unrelated to the storm event—namely, structural defects that existed prior to the property’s purchase and the inception of the policy. The denial letter and final decision letter clearly state that the policy does not cover structural damage or faulty workmanship by the builder occurring outside the policy period. The complainants have not provided evidence that the insurer advised the policy would be void if the builder returned to the site after QBCC closed its file. Further, the complainants’ own engineer confirmed that the builder was willing to rectify the structural defects in 2020; however, the complainants rejected the proposed rectification plan because it would alter the property’s aesthetics. This led them to pursue the matter with QBCC and subsequently commence legal proceedings. Allowing the builder back on site in May 2021 does not appear relevant to any loss suffered, as this occurred after the parties had failed to agree on a rectification plan and after the QBCC dispute was lodged and the builder failed to comply with QBCC’s Direction to Rectify. The matter with the builder was ultimately resolved by a deed of settlement on 12 July 2023. The complainants were legally represented at that time and signed a deed of release in full and final settlement against the builder. The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. The panel is not satisfied that the insurer misled the complainants to cause them any loss or provided them with any indication that the claim would somehow be covered. From the available information, the insurer’s position has always been that the claim is not covered. 2.3 Are the complainants entitled to compensation? Yes. At times during the claims process there were delays in responding to correspondence. This caused inconvenience and distress to the complainants. The insurer has offered $2,500 in non-financial loss compensation which is adequate in the circumstances. AFCA can award compensation Under AFCA’s Rules, AFCA may award compensation for non-financial loss where there has been an unusual amount of physical inconvenience, time taken to resolve a situation, or interference with the complainant’s expectation of enjoyment or peace of mind. All claims have a level of stress and inconvenience which can reasonably be expected. In assessing whether to award compensation, AFCA expects complainants to be moderately robust, bear the normal degree of inconvenience experienced when a problem occurs, and take reasonable steps to minimise the inconvenience suffered. AFCA considers the severity and impact of the financial firm’s conduct on the particular complainant. Insurer is required to pay compensation for non-financial loss The complainants say the insurer failed to respond to correspondence in a timely manner on more than one occasion. Of concern was the lack of response to requests for telephone call recordings and responses which at times did not address their concerns. This matter was protracted for a period of time with the claim lodged in early 2020 and the AFCA complaint lodged in March 2024. The delays with the claims are not entirely the result of the insurer’s actions but rather the complexity of the situation which involved QBCC and legal action against the builder. However, in its offer of resolution the insurer has offered $2,500 in non-financial loss compensation. The panel considers this amount to be appropriate and adequate in the circumstances. 2.4 Why is the outcome fair? The insurer’s liability is determined based on the terms of the policy. The policy is clear it does not cover damage which occurred outside the policy period. Whilst the complainants did not discover the damage until they purchased the property, this does not mean it was covered. The complainants have not established the insurer’s actions led them into error. On that basis, it is fair for the insurer to decline the claim for structural damage which is the result of faulty workmanship by the original builder. The complainants have taken necessary action to claim against the builder for his negligence. The insurer is not responsible for any shortfall in funds to repair the structural faults. 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to: · the legal principles · applicable industry codes or guidance · good industry practice · previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. A panel determined this matter Due to the nature of this complaint, we referred it to a panel for determination. The panel includes: · an ombudsman · a member with significant experience in consumer and small business advocacy · a member with extensive experience in insurance. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider: · available documents · the recollections of the parties · all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.