Determination 12-00-1075196
Refusal of mould remediation liability and delays in claim handling after lightning damage
Summary
The complainants' lightning-damaged home developed mould after the insurer delayed approving an air conditioner replacement, and the insurer then refused liability for mould remediation. AFCA found the delays contributed to the mould, ordered remediation, reimbursement of affected contents and related costs, interest, and $3,000 non-financial loss.
An insurer is liable for loss caused or exacerbated by its own claim handling delays, and for non-financial loss from poor handling and communication.
Issues
- Claim denial primary · upheld
“The insurer is liable for mould remediation and the discarded mould infected contents because its claim handling delays caused and contributed to mould growth”
- Complaint handling failure secondary · upheld
“it is unclear why the insurer initially closed the complaint lodged on 6 February 2024 without a response”
- Delay secondary · upheld
“The time taken to obtain the builder's report and scope works ... is unreasonable”
- Poor communication secondary · upheld
“I am not satisfied the insurer proactively managed the complainants' claim or that it provided regular updates”
- Third-party or outsourcing failure secondary · upheld
“The insurer agreed to perform makesafe mould remediation at the property and its restorer did not complete the required works”
Subjects and remedies
health or medicalhome or building damagepay claimpay compensationpay interestpay non financial lossrepair or rectify
Text of the determination
Determination
|
Case number
|
12-00-1075196
|
Financial firm
|
Hollard Insurance Partners Limited
Case number: 12-00-1075196 4 October 2024
Determination overview
Complaint
The complainants lodged a claim with the financial firm (insurer) after the insured building and contents (items) suffered lightning damage on 30 December 2023.
The insurer partially accepted the claim. It cash settled the complainants for part of their loss and arranged repairs for the remaining damaged items. It refused liability for mould remediation as there was no water ingress into the property and because the insured event did not cause mould growth at the property.
The complainants seek the insurer to accept liability for mould remediation, mould infested items they discarded and pay compensation for its claim handling and poor service.
Issues and key findings
Is the insurer’s settlement fair?
No. The insurer took several months to authorise the complainants to proceed with replacing the air conditioner that was damaged by the lightning. The insurer is liable for mould remediation and the discarded mould infected contents because:
its claim handling delays caused and contributed to mould growth at the property
the absence of an air conditioner at the property during months with high humidity and warm days would have been conducive for mould growth
an air conditioner would have disturbed, regulated and recycled the air within the property and reduced the moisture and humidity levels preventing mould growth and spread.
Is the insurer’s compensation offer fair?
No. The insurer did not proactively manage the claim. It did not respond to the complainants’ queries and concerns in a timely manner. The insurer’s delays and claim handling caused stress, inconvenience, frustration and disappointment. The mould growth caused health issues. The insurer should increase its non-financial loss compensation offer to $3,000.
Why is the outcome fair?
The insurer is responsible for mould growth caused and exacerbated by its claim handling delays. The insurer should also pay non-financial loss compensation for its claim handling.
Determination
This determination is in favour of the complainants.
Subject to AFCA notifying the insurer of the complainants accepting this determination, the insurer should:
arrange mould remediation at the property
reimburse the complainants for mould infested non-salvageable contents, dehumidifier and Decon 30 (disinfectant) and pay interest on the settlement as detailed in section 2.1
pay non-financial loss compensation of $3,000.
Reasons for determination
Is the insurer’s settlement fair?
No. The insurer took several months to authorise the complainants to proceed with replacing the air conditioner that was damaged by the lightning. The insurer is liable for mould remediation and the discarded mould infected contents because:
its claim handling delays caused and contributed to mould growth at the property
the absence of an air conditioner at the property during months with high humidity and warm days would have been conducive for mould growth
an air conditioner would have disturbed, regulated and recycled the air within the property and reduced the moisture and humidity levels preventing mould growth and spread.
Insurer should review issues relating to lightning damage in the future
The insurer partially cash settled the complainants for some of the items including the replacement cost of the air conditioner. The complainants say that after eight months since lodging the claim, the insurer’s appointed repairer completed the approved repair works.
The complainants remain concerned that there may be further electrical/electronic items that suffered lightning damage and that the issues may arise in the future. If any issues arise that may be related to the lightning event on 30 December 2023, the complainants are free to refer them to the insurer for its review and consideration.
Complainants hold insurer responsible for mould growth at the property
On 26 February 2024, the complainants raised concerns about the claim with their personal banker R (an agent of the insurer). On 28 February 2024, R had indicated the issue had been raised with the relevant manager and that the complainants should receive a response. The complainants say they informed R the following:
A lack of ducted air conditioning for the two hottest months of the year in sub-tropical Queensland during various heat waves combined with high humidity has made the house somewhat uninhabitable on several days. The lack of air conditioning (which reduces humidity as well as the temperature) has likely contributed to mould growing in our wardrobe and heat rashes. To try to address this issue we have tried to maximise flow into the house and investigated purchasing a dehumidifier (costs $500 for a suitable one).
The complainants hold the insurer responsible for mould growth at the insured property and say:
after they notified the insurer of mould growth at the insured property, the insurer initially agreed to complete mould remediation at the property and subsequently denied liability
the restorer did not perform makesafe mould remediation works agreed to or indicated as completed by the insurer
the insurer’s restorer’s report did not accurately reflect the works performed at the property and this report was amended after they raised concerns about its works. The restorer only remediated the front door and a bookcase at the entrance of the property
no drying equipment was left, and the restorer left a small air purifier in one room and removed it after three days
they cleaned the home and all contents and discarded the items which could not be salvaged
they have been diagnosed with mould and dust mite allergies and suffered from rashes
they purchased a dehumidifier and Decon 30 disinfectant to perform the mould remediation works themselves.
The insurer denied liability for mould remediation on the basis the insured event did not cause mould growth at the property. It relied on its restorer’s findings:
all walls throughout entire house were showing elevated moisture levels
no evidence of water entry
elevated readings are due to environmental conditions and high humidity
elevated hygrometer readings throughout, entire house had appropriate conditions for mould growth
all environmental mould had been caused by extreme humidity in the area
it had acted in good faith and completed mould makesafe to the property despite it being caused from environmental aspects and not caused from an insured event
the initial lighting/storm has not caused the mould to grow within the property and the air conditioning has not leaked causing water ingress.
The insurer states the mould growth at the property was not caused by the initial insured event but by environmental mould from extreme humidity. The policy excludes cover for any loss, damage or liability caused directly or indirectly by or in any way connected with:
15. condensation, mould, mildew, wet or dry rot, rising damp or dampness, that has not been caused by an Insured Event.
Insurer should accept liability for mould remediation/mould infested items
I have reviewed the exchanged information between the parties and accept there was no evidence of water ingress into the property after the storm/lightning on 30 December 2023. The restorer’s findings confirm the elevated humidity levels at the property caused environmental mould growth.
I also accept the policy excludes cover for loss or damage caused by the mould unless it was caused by an insured event.
In the complainants’ case, the insurer’s builder assessed the property on 11 January 2024. The air conditioner sustained irreparable damage and required replacement. The insurer/builder took several months to release the scope of works and to approve the complainants’ quote for air conditioner replacement.
During this period, the property suffered from heat waves and high humidity levels which became conducive for mould growth. The mould most likely further spread around the property due to no action being taken by a professional to remediate the mould.
I accept the complainants’ submission that the insurer’s delays in approving a replacement functional air conditioner contributed to mould growth at the property. This is because in addition to regulating the temperature within the property, air conditioners also recycle the airflow within the property. Since the property had a ducted air conditioner system, this would have efficiently managed the airflow in several areas of the property and not limit its effect to a particular room/area as a dehumidifier.
Further, the complainants have presented evidence from their pest control expert that there was no evidence of mould at the property during their inspection for termites in early December 2023. There were no issues with moisture readings recorded at the time. This was most likely due to a functional air conditioner operating at the time.
I am satisfied that air conditioning can prevent mould growth within a home. Whilst it assists with regulating the internal temperatures, it can also reduce indoor moisture and its action of recycling the airflow within the home can disturb the moist warm stable environment, which is generally conducive for mould growth and spread.
Given the above, I am satisfied that it is fair in all the circumstances that the insurer is liable for mould remediation at the property including non-salvageable mould infested items. The insurer should arrange mould remediation at the property. The complainants should submit a list of the discarded items with supporting information for the insurer’s review and settlement.
The insurer agreed to perform makesafe mould remediation at the property and its restorer did not complete the required works. The complainants’ actions of purchasing a dehumidifier and conducting basic mould remediation works with Decon 30 controlled and avoided further spreading of mould at the property. In the circumstances, it is fair the insurer reimburses the cost of the dehumidifier and Decon 30 after the complainants submit the purchase/ payment details for same.
Finally, the insurer should pay interest on the settlement pursuant to section 57 of the Insurance Contract Act 1984 from the date it refused liability for mould remediation until the date of payment.
Is the insurer’s compensation offer fair?
No. The insurer did not proactively manage the claim. It did not respond to the complainants’ queries and concerns in a timely manner. The insurer’s delays and claim handling caused stress, inconvenience, frustration and disappointment. The mould growth caused health issues. The insurer should increase its non-financial loss compensation offer to $3,000.
AFCA may award compensation in certain circumstances
Under paragraph D.3 of the AFCA Rules, we may award compensation for non-financial loss (capped at $6,300) where the insurer’s actions have caused an unusual amount of:
physical inconvenience
time taken to resolve the situation
interference with the complainants’ expectation of enjoyment or peace of mind.
We take a conservative approach to compensation and expect complainants to bear a normal degree of inconvenience during a claim. When considering non-financial loss compensation AFCA looks at what is reasonable and fair in all the circumstances. In considering what is fair in all the circumstances, it is appropriate to factor the overall claims experience, rather than focusing on specific individual events.
Insurer should increase its non-financial compensation offer
The complainants expect the insurer to pay compensation as they suffered from stress and inconvenience due to its poor communication, overall claim handling and service. They say:
they spent time trying to communicate and resolve issues with the insurer
not having an air conditioner and the negative flow on effects. They suffered from sleepless nights and health issues
it took nearly three months for the insurer to obtain the builder’s report and scope of works/quote
they were notified that the insurer would arrange makesafe mould remediation and the insurer subsequently refused liability. It did not act in good faith
their concerns lodged with the insurer on 6 February 2024 were not acknowledged or addressed in a timely manner and the insurer’s complaint handling caused confusion
there were further delays authorising approved repairs after the insurer denied liability for mould remediation, requiring their intervention.
The insurer says its overall claims management was satisfactory and there were no major delays. It had followed up its builder for its report and the scope of works on 6,13 and 27 February 2024. It partially accepted liability for the claim on 28 March 2024. On the same day it requested the builder to arrange a mould remediation report.
The insurer refused liability for mould remediation as the policy would not extend cover for this loss/damage. It refunded the complainants the $2,000 excess. It also offered to pay $1,000 compensation to resolve the complaint. It approved a scope of works variation request as soon after it was raised. It says it provided regular updates to the complainant.
Upon reviewing the claim notes and correspondence between the parties, I am not satisfied the insurer proactively managed the complainants’ claim or that it provided regular updates without the complainants prompting a query. The insurer did not address the complainants’ concerns and queries in a timely manner. The time taken to obtain the builder’s report and scope works, which was three months since the builder completed the site inspection at the property, is unreasonable.
The insurer’s claim handling and completion of repairs improved after August 2024. However, the insurer’s initial delay in authorising the air conditioner replacement resulted in mould growth and health issues to the complainants.
For the reasons explained above, the insurer is liable for mould remediation. It is not fair the complainants had to perform mould remediation works to the building and contents whilst suffering from health issues.
The insurer’s response times and complaint management could have been better, and the insurer’s overall claim handling caused stress, inconvenience, frustration and disappointment to the complainants. The insurer’s complaint handling caused confusion, and it is unclear why the insurer initially closed the complaint lodged on 6 February 2024 without a response and issued a new complaint number in March 2024.
I am satisfied the insurer could have expedited the claim process and regularly kept the complainants informed of the progress with the claim. I acknowledge the claim notes show there were some instances the insurer was unable to contact the complainants. The complainants responded to the insurer’s queries in a timely manner.
Given the above and having regard to the insurer reimbursing the policy excess of $2,000, I consider it fair in all the circumstances that the insurer should increase its non-financial loss compensation from $1,000 to $3,000.
Why is the outcome fair?
The insurer is responsible for mould growth caused and exacerbated by its claim handling delays. The insurer should also pay non-financial loss compensation for its claim handling.
Supporting information
The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all the information the parties have provided.
While the parties have raised several issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.