Home / Suncorp Group / Determination 12-00-1067590

Determination 12-00-1067590

Delay in completing flood repairs and cessation of accommodation payments

FirmSuncorp Group
Decided2024-10-09
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$8,300
Non-financial loss—
Amount claimed$152,250
SourceAFCA PDF

Summary

The complainant's flood repairs ran well past the expected completion date, and the insurer stopped paying her accommodation before the home was liveable. AFCA found the insurer responsible for the delay from 30 January to 12 May 2024 and ordered $8,300 accommodation, rejecting the $152,250 delay compensation sought.

An insurer must compensate loss caused by its own delay or error, but not delay caused by factors outside its control or financial loss that is not proven.

Issues

Subjects and remedies

home or building damagenatural disasterpay compensation

Related

All Suncorp Group determinations · Find similar determinations

Text of the determination

Determination | Case number | 12-00-1067590 | Financial firm | AAI Limited Case number: 12-00-1067590 4 September 2024 Determination overview Complaint The complainant holds a home and contents insurance policy with the financial firm (the insurer). She lodged a claim after her home was damaged by a flood in February 2022. The complainant negotiated with the insurer’s builder to arrange insured works (work needed to repair the flood damage) and private works (additional work not covered under the policy). She signed a building contract in November 2022. The work was mostly complete by May 2024. The complainant says the repairs took an unreasonably long time, and the insurer should pay compensation for the delay. The complainant says the building contract gave a practical completion date of 4 March 2023. She says the insurer should pay compensation of $350 for every day practical completion was delayed. She moved back into her home on 12 May 2024, 435 days after 4 March 2023. $350 per day for 435 days is $152,250. The insurer says the delay was caused by the private works, which it was not responsible for. Issues and key findings Is the insurer responsible for a delay in repairs? Yes. The insurer is responsible for the delay in repairs from 30 January 2024 to 12 May 2024. The insurer has not provided information showing the private works contributed to this delay. Repairs did not start until August 2023. However, the delays from February 2022 to August 2023 were for reasons outside the insurer’s control. Is the insurer required to pay more for accommodation? Yes. The insurer stopped paying for the complainant’s accommodation on 4 March 2024. It should have continued to pay for her accommodation until 12 May 2024. This would have cost the insurer $8,300 (10 weeks at $830 per week). Is the insurer required to pay more for financial loss? No. The complainant has not provided information showing the delay caused her financial loss. Is the insurer required to pay more for non-financial loss? No. The delay caused the complainant non-financial loss (stress and inconvenience). Compensation awarded by this determination, together with compensation already paid by the insurer, is sufficient to compensate her for this. Why is the outcome fair? Fairness requires the insurer to compensate the complainant for any loss covered under the policy, and any loss caused by its error. I am satisfied this determination provides the fairest possible outcome, based on the information provided by the parties. Determination This determination is mostly in favour of the insurer. The insurer must pay the complainant $8,300 for accommodation from 4 March 2024 to 12 May 2024. Reasons for determination Is the insurer responsible for a delay in repairs? Yes. The insurer is responsible for the delay in repairs from 30 January 2024 to 12 May 2024. The insurer has not provided information showing the private works contributed to this delay. Repairs did not start until August 2023. However, the delays from February 2022 to August 2023 were for reasons outside the insurer’s control. Home repaired between February 2022 and May 2024 On 27 February 2022, the complainant lodged a claim for flood damage to her home. In May 2022, the insurer stripped out the home. In June 2022, the home was ready to be repaired. From July 2022 to November 2022, the insurer asked whether the complainant wanted the insurer’s builder to repair the home. The complainant negotiated with the insurer’s builder to arrange insured works and private works. In November 2022, she signed building contracts. In December 2022, the builder said repairs would likely start in the new year, after the Christmas shutdown. In April 2023, there was discussion about some of the work being paid for by the Resilient Home Fund (RHF), a government fund for owners of flood-damaged homes. The builder said it could not schedule repairs without approval from the RHF. In June 2023, the builder said the RHF had approved a scope of works. The builder said it had forwarded the scope of works to the complainant for approval. According to the insurer, the complainant was not satisfied with the scope of works. In August 2023, the repairs began. On 7 December 2023, the builder said the repairs would be finished by 30 January 2024. On 30 January 2024, the builder emailed the complainant saying ‘the job had been pushed back 3 weeks’. The complainant said this was the first time she had been told the repairs would not be finished by 30 January 2024. On 12 May 2024, the repairs were mostly complete, and the complainant moved back into the home. Not all repairs complete Not all repairs were completed when the complainant moved back into the home. The incomplete repair items included the solar system, garage door, and fire alarm. The solar system was damaged during the strip-out in 2022. The insurer agreed to replace it as part of the insured works. In a phone call with AFCA on 18 July 2024, the insurer said it had not replaced the solar system, or even obtained a quote for the work. The insurer knew (or should have known) about the need to replace the solar system from 2022. The insurer has not explained why it did not replace the solar system. The complainant said towel rails and hooks were uneven and loose, with some defects in the plaster and paint behind them. The insurer says it rectified these issues. Insurer not responsible for delay in starting repairs The complainant lodged the claim in February 2022, but repairs did not begin until August 2023. The delay appears to have been caused by: the need to strip out the home before repairs could begin negotiations between the complainant and the builder about what private works would be completed in addition to the insured works a delay in obtaining approval from the RHF. The insurer says the RHF delay was out of its control. The complainant has not provided any information showing the insurer or the builder could have done anything about this delay. I am not satisfied the insurer made an error that delayed the start of the repair work. Insurer responsible for delay in completing repairs Repairs began in August 2023. On 7 December 2023, the builder said the repairs would be finished by 30 January 2024. The home was not liveable until May 2024, and some of the repairs were still not finished by July 2024. The insurer says the repairs were delayed because of the private works. The complainant disputes this. She says she was told the private works would not delay the insured works. The insurer admits: ‘At the time the Customer requested these works, the builder didn’t foresee any additional time requirements and advised the Customer accordingly.’ In an email to the insurer on 19 February 2024, the complainant said she could not see how any of the private works delayed the insured works. She asked the insurer to explain how the private works delayed the insured works. The insurer has not answered this question. The insurer says: ‘Private works can always run the risk of impeding claim works.’ This is true, but the insurer has not explained how the private works delayed the insured works in this specific case. The insurer failed to arrange the replacement of the solar system, which was part of the insured works. The insurer has not offered any explanation for this. Having considered the information provided by both parties, I am satisfied the insurer or its builder caused the delay from 30 January 2024 to 12 May 2024. I am not satisfied the private works contributed to the delay. Is the insurer required to pay more for accommodation? Yes. The insurer stopped paying for the complainant’s accommodation on 4 March 2024. It should have continued to pay for her accommodation until 12 May 2024. This would have cost the insurer $8,300 (10 weeks at $830 per week). Insurer stopped paying for accommodation on 4 March 2024 The insurer paid for the complainant’s accommodation from 15 March 2022 to 4 March 2024. On 19 February 2024, the insurer said it would not pay for any further accommodation because the repair delays were caused by private works. In April 2024, the insurer offered to pay for accommodation until the complainant moved back into her home. However, by that point, the complainant had already moved out of the accommodation the insurer was paying for. The complainant says she stayed with a friend from 4 March 2024 to 12 May 2024 She says she agreed on rent of $400 per week, but had no money, and has not paid anything to her friend. She wants the insurer to pay her friend $4,000 for ten weeks’ accommodation. Insurer should have paid for accommodation until home was liveable As stated above, I am satisfied the delay from 30 January 2024 was caused by the insurer or its builder. Therefore, the insurer should have continued to provide accommodation until 12 May 2024, when the insured property was liveable. The complainant did not pay for accommodation after 4 March 2024. It would not be fair for the insurer to save money because it wrongfully stopped paying for accommodation. The insurer should pay the complainant what it would have paid for accommodation from 4 March 2024 to 12 May 2024, had it not wrongfully stopped paying for accommodation. Until 4 March 2024, the insurer was paying $830 per week for accommodation. It should pay the complainant this amount for the period of 4 March 2024 to 12 May 2024 (10 weeks). This amount totals $8,300. Is the insurer required to pay more for financial loss? No. The complainant has not provided information showing the delay cause her financial loss. Insurer agreed to pay increased electricity costs at insured address The complainant says she is incurring higher electricity costs because her home does not have a working solar system. She says the insurer should pay her full electricity bill each month until the home has a working solar system. The insurer says it will not pay the complainant’s full electricity bill, but will pay her the rebate she would have received if she had a working solar system. This is fair. Complainant has not established other financial loss The complainant has asked the insurer to pay for: increased cost of materials for the private works increased water, electricity, and travel costs psychological treatment for her children. The insurer said it would consider these requests if the complainant provided ‘documentation and clarification’. The complainant has not explained how the delay in the insured works increased the cost of the private works. The insurer asked for documentation showing the increase in the cost of the private works, but the complainant has not provided it. The complainant paid for water and electricity at her temporary accommodation. However, she would have had to pay for water and electricity at her home if she was living there. She has not provided information showing she paid for water and electricity at her friend’s home. The complainant says her travel costs increased because her temporary accommodation was further from her older child’s school than her home. However, she said she could not provide records of kilometres travelled. The complainant said she would provide invoices for psychological treatment, but she has not done so. The complainant has not provided information showing she suffered a financial loss because of the delay in completing repairs (other than increased electricity costs due to the lack of a working solar system). Therefore, the insurer is not required to pay further compensation for financial loss. Is the insurer required to pay more for non-financial loss? No. The delay caused the complainant non-financial loss (stress and inconvenience). Compensation awarded by this determination, together with compensation already paid by the insurer, is sufficient to compensate her for this. AFCA can award compensation for non-financial loss Under the AFCA Rules, we can award up to $6,300 compensation for non-financial loss if a complainant suffered an unusual degree of stress, inconvenience, or delay because an insurer mishandled a claim. We will only award this type of compensation if there has been an unusual degree of stress, inconvenience, or delay. We will not award compensation for the usual amount of inconvenience involved in making a claim. We will not award compensation for delays caused by a complainant, or other factors outside the insurer’s control. Determination awards compensation for accommodation issues The repairs were delayed, and the insurer stopped paying for accommodation. Because of this, the complainant had to move out of her accommodation and into a friend’s home. This would have caused significant stress and inconvenience. This determination requires the insurer to pay the complainant $8,300 for accommodation she did not pay for. If the complainant pays her friend $4,000 (as she said she agreed to), this still leaves her with $4,300 for accommodation expenses she did not incur. In my view, this is sufficient to compensate her for the stress and inconvenience of moving. Insurer’s compensation sufficient for incomplete repairs The insurer failed to complete repairs to the solar system, garage door, and fire alarm before the complainant moved back into her home. The insurer has agreed to rectify these issues, but the failure to rectify them earlier has caused the complainant stress and inconvenience. The insurer says it has paid the complainant $1,000 as a ‘claims experience compensatory payment’. In my view, this is sufficient to compensate her for the stress and inconvenience of the incomplete repairs. The insurer is not required to pay further compensation for non-financial loss. Why is the outcome fair? Fairness requires the insurer to compensate the complainant for any loss covered under the policy, and any loss caused by its error. I am satisfied this determination provides the fairest possible outcome, based on the information provided by the parties. Complainant may lodge new complaint about incomplete insured repairs The most recent correspondence from the parties indicates some of the insured repairs are still not complete. The insurer must take all reasonable steps to resolve these aspects of the claim as soon as possible. If the parties cannot agree on how to resolve these aspects of the claim, the complainant may lodge another AFCA complaint. Supporting information The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to: the legal principles applicable industry codes or guidance good industry practice previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. I have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, I have restricted this determination to the issues that are relevant to the outcome. Complainant represented by family member or friend The complainant was represented by a family member or friend. In this determination, statements by the complainant’s representative are treated as if they were made by the complainant.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.