Cash settlement offer for water damage claim and loss of rent

FirmIAG
Decided2025-04-28
ProductGeneral Insurance · Landlord
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The complainant claimed for water damage to a rental property and loss of rent. AFCA found the insurer's $6,000 cash settlement offer fair and reasonable and found no entitlement to loss of rent.

The complainant bears the onus to establish a valid claim, the policy excludes gradual deterioration and wear and tear, and loss of rent requires that the property could not be lived in by tenants due to the claimed damage, which was not established.

Issues

Subjects and remedies

financial hardshiphome or building damageno remedy

Related

All IAG determinations · Find similar determinations

Text of the determination

Determination | Case number | 12-00-1063095 | Financial firm | Insurance Australia Limited Case number: 12-00-1063095 17 April 2025 Determination overview Complaint This complaint relates to a landlord insurance policy with the financial firm (insurer) for a property owned by the complainant in South Australia. The policy period was from 14 November 2021 to 14 November 2022. The property was insured for $240,674. The policy had a basic excess of $300 for all building claims. The policy included a loss of rent benefit up to $17,160. On 15 March 2023 the complainant lodged a claim for the repair of damage which she said was due to water leaking from the bathroom on 28 June 2022. The complainant obtained a quote from C, a builder and renovator, dated 4 July 2023 to do a full ‘bathroom renovation’ in the amount of $40,040 (GST inclusive). The insurer partially accepted the claim and sought to cash settle the claim. After a period of negotiation, its final offer was $6,000 (GST inclusive) on 10 September 2024. The complainant acknowledged she is not entitled to the full amount of C’s quotation. However, she says the insurer’s offer is not sufficient although she cannot quantify the amount sought. She also wants loss of rent benefit for 10 weeks at a rental of $350 per week. Issues and key findings Was the insurer’s offer fair and reasonable? Yes. Based on the information available, the insurer’s offer of $6,000 was fair and reasonable. Is the complainant entitled to loss of rent? No. The complainant has not established that she was entitled to the loss of rent benefit under the policy. Why is the outcome fair? The outcome is fair because the insurer is entitled to rely upon the exchanged material and the terms and conditions of the policy to determine its obligations regarding the claim and made a fair and reasonable offer to resolve the claim. Determination The determination is in favour of the insurer. Within 14 days of receiving notice of the complainant’s acceptance of the determination, the insurer shall:  pay the complainant $6,000 (GST inclusive) in full and final settlement of the claim Reasons for determination Was the insurer’s offer fair and reasonable? Yes. Based on the information available, the insurer’s offer of $6,000 was fair and reasonable. Coverage of the policy The complainant’s policy provided cover for insured events during the period of insurance. The coverage provided by the policy is subject to conditions, limitations, and exclusions. This means that not all loss and damage is automatically covered. Rather, only loss and damage caused by an insured event, during the period of insurance and subject to the conditions, limitations and exclusions, is covered. The full details of the policy coverage, conditions, limitations, and exclusions are contained within the Product Disclosure Statement (PDS) and Schedule of Insurance (Schedule) (together referred to as the policy). I am satisfied that the PDS and Schedule have been provided to the complainant. Therefore, the insurer is entitled to rely upon the terms of the policy to determine its obligations to the complainant. Complainant has initial onus to establish a valid claim The initial onus is with the complainant to establish on the balance of probabilities (that is more likely than not) that the loss or damage claimed falls within the insuring provision of the policy. This is known as a ‘valid’ (or prima facie) claim. Once the complainant has established a valid claim, the onus shifts to the insurer to establish, on balance, the application of a policy exclusion or that it is otherwise entitled to decline or limit the claim under the policy. Cover for accidental damage subject to exclusions The policy provided cover for accidental damage (page 13): Accidental Damage Cover Your Buildings and/or your Contents as set out on your Policy Schedule are covered if they are accidentally destroyed, accidentally lost or accidentally damaged. They are covered only if you own them, or are liable for their destruction, loss or damage. .. We will cover your Buildings and/or your Contents as set out on your Policy Schedule for accidental destruction, accidental loss or accidental damage. However, some instances of destruction, loss and damage are only covered under specific conditions as set out below: .. If the damage or loss was caused to the Buildings or Contents by liquid escaping, we will also cover the cost of finding where the liquid escaped from, including the cost of repairing any damage that occurs while looking for the cause if there is resultant damage. We will not however cover the cost of repairing the defective item that caused the escape of liquid or liquid escaped from. We do not cover loss caused by a gradual process of bursting, leaking, splashing, dripping or overflowing over a period of time when you could have reasonably been expected to be aware of this condition. Cover was subject to general exclusions under the policy The policy provided (page 13): We will not pay for your Buildings or Contents which are destroyed, lost or damaged by: - Rust, corrosion, gradual deterioration, depreciation, wear or tear Complainant’s agents’ inspection reports prior to the claim The complainant purchased the investment property in 2017. According to the Schedule, the property had been built between 1914 and 1945. The complainant obtained a pre-purchase inspection report dated 17 July 2017 which was prepared by I. I reported that the bathroom’s overall condition was ‘average’ but that several taps had seized and recommended the replacement of tap fittings. The complainant obtained routine tenancy inspections and reports prepared by her agents (R and B):  Report by R dated 5 August 2020 which showed bubbling of paint to a section of the hallway  Report by R dated 28 June 2022 which showed marks to the hallway walls (including peeling of paint) which the agent noted appeared ‘in the same condition as previous inspection’. The report also stated that ‘The bathroom was in an overall clean and tidy condition inspection. The bath, vanity and toilet all appeared in a clean condition. Paint peel to floor.’  Report by R dated 13 October 2022 which showed: > ‘the bathroom was in an overall satisfactory and tidy condition. The bath, vanity and toilet all appeared in a clean and fair condition. Paint peeling off to floor, appears to be in the same condition as previous inspection’. > the hallway (including peeling of paint) was noted by the agent to be ‘in the same condition as previous inspection’  Report by B dated 13 February 2023 reported: The Landlord to Consider: The Landlord is looking into the Repair of the Bathroom/ Salt Damp at the Property, as per Phone Conversation Kitchen .. Salt Damp to walls (with supporting photographs) Bathroom .. Paint peeling off to floor, and in the Bath, appears to be in the same condition as previous inspection Hallway The hallway was neat and tidy. Marks to walls appear in the same condition as previous inspection. Large amount of Salt damp present on outside of Bathroom Wall, Being attended too. Complainant engaged a plumber on 2 March 2023 The complainant engaged a plumber, P, who prepared a leak detection report dated 2 March 2023 (22 pages, including supporting photographs). P concluded:  an inspection of the hallway and kitchen walls adjacent to the main bathroom showed water damage present throughout as well as containing high levels of moisture  the concrete slab underneath the bath was also very wet and had mould present to the walls  under the bath, there was no floor waste gully or grate present to exit the water which meant all the water overflowing from the shower was running down through the bath waste  a pressure test was conducted to the shower breacher which failed as water could be heard spraying into the wall  an inspection of the fibre washers showed that they were sound and the leak was confirmed to be coming from the breacher  a pressure test to the bath breacher, domestic hot and cold water services all showed static results  a spray test to the shower walls has failed due to deteriorated grout seals and no visible waterproofing membrane as well as water being able to leak underneath the bath onto the concrete slab as there was no seal between the bath and wall tiles  a flood test to the bath failed because when the plug was released, water started to gurgle up from the bath waste penetration and leak onto the concrete slab  there was a break in the bath waste drain under the slab which was not able to be cctv inspected due to the grate in the bath  due to all the above issues/leaks it was believed that a lot of moisture was present underneath the bathroom slab  cause of leak was due to a combination of issues, these include; > ‘A leaking shower breacher allowing water to soak into the wall whilst showering, deteriorated seals in the wall tiles and no visible waterproofing membrane, no seal between the bath and wall tiles allowing water whilst showering to leak onto and pool on the bathroom floor as well as the bath waste pipe being broken underneath the slab’  it was recommended that: > a building contractor be engaged in order to renovate/repair the area in accordance with AS3740 waterproofing standard > a plumbing contractor be engaged to repair the broken bath waste and the leaking shower breacher Insurer assessed property in March 2023 after the complainant made a claim The complainant made a claim on 15 March 2023. The date of the claimant’s loss was said to be 28 June 2022. This was the date of the report by R dated 28 June 2022 which showed marks to the hallway (including peeling of paint). The insurer has not disputed that was the appropriate date of the first damage to the hallway and has accepted that its policy (which provided cover between 14 November 2021 to 14 November 2022) was the applicable one during which it was on risk for the claimed damage. Subsequently, on 21 March 2023 U, a builder, attended the property and prepared an Assessment Report (8 pages, including supporting photographs) on behalf of the insurer. U concluded that:  damaged areas to the hallway and kitchen to be consistent with 80% plumbing failures and 20% waterproofing failures  waterproofing (grouting, tiles and seals) had allowed water to penetrate into surrounding areas  tapware to wall cladding seal had allowed water to penetrate into wall cavity  tapware in the shower leaked while in the ‘on’ position only (O’Rings)  shower breacher leaked during use or under test  due to the age/construction method of the dwelling, rising damp may also be a contributing factor  the complainant should bring the shower alcove/ wet area up to Australian Standard AS3740-2010 in association with The Ministers Specification S.A. F1.7 2004 by removing and replacing the shower alcove wall linings/tiles, shower floor tiles and puddle flange and apply a waterproof membrane  [U] found the resultant damages consistent with 80% plumbing failures and 20% waterproofing failures. [U said it was] covered under [the] policy. Due to the extensive owner repairs and the possibility of rising dampness being a contributing factor [U could not] warrant repairs [and recommended a cash settlement] Complainant obtained a quote for a bathroom renovation and terminated the tenancy On 4 July 2023 the complainant obtained a quotation from C, builder and renovator, for a full ‘Bathroom Renovation’ in the amount of $40,040 (GST inclusive). C’s quotation did not provide any opinion regarding the cause of the damage to the bathroom. C’s quotation was not itemised. It was inclusive of full bathroom demolition and removal of the concrete slab, carpentry (new door), electrical, new drains, shower, toilet and vanity, $4,000 allowance for bathroom fixtures, termite mesh, concreting, plastering, tiling, painting and shower screen. At the time the complainant obtained a quote for the full bathroom renovation in July 2023 there were tenants in the property. The complainant had entered into a lease agreement with the tenants on 16 October 2022 for 6 months. Despite having made the claim on 15 March 2023, on 14 April 2023 the complainant also entered into an ‘Extension of Lease Agreement’ for a further 6 months to 16 October 2023 at a rental of $350/ week (with a rental increased by $10/ week). On 18 July 2023 the complainant’s agent, B, gave notice of termination of the tenancy to the tenants and sought vacant possession on 16 October 2023. Cash settlement offers by the insurer for the kitchen and hallway The insurer prepared a Scope of Works on 25 September 2023 (prepared by U):  for repairs to the kitchen in the amount of $2,395.47  for repairs to the hallway in the amount of $667.59. The SOW for the hallway specifically required the complainant to attend to repairs to ‘the shower alcove / wet area must be brought up to Aust Standard AS3740-2010 in association with The Ministers Specification S.A. F1.7 2004. This work includes but is not limited to removal and replacement of the shower alcove wall linings/tiles, shower floor tiles and puddle flange including the application of a waterproof membrane as required’. On 26 September 2023 the insurer advised the complainant it would ‘cover the cost of repairing the wall in the hallway caused by the escape of liquid in [the] bathroom and the resultant damage to the kitchen wall caused by the leaking tapware and shower breecher. However, the cost to repair any long-term damage [was] not covered under [the policy] including the failure/no waterproofing, failed sealant, leak in the shower breecher, leak in the bath waste and rising damp due to the age and construction of the bathroom as these are the result of poor maintenance, unrectified water leaks, faulty workmanship and long-term gradual deterioration’. The insurer offered a cash settlement to the complainant based on a Scope of Works by U comprising $3,063.06 (kitchen $2,395.47 and hallway $667.59) less two excesses $800 ($400 x 2) = $2,263.06. The initial cash settlement offer deducted 2 excesses at $400 (but the excess under the policy was $300). The initial cash settlement offer did not include an uplift. In its offer on 26 September 2023 the insurer explained that it had deducted two excesses because there were: ‘two escape of water events that caused resultant damages. The first one being resultant damage to the hallway wall identified in August 2020 and the second one caused by the leaking tapware and shower breecher resulting in the damage to the kitchen wall in June 2022.’ On 13 October 2023 the insurer revised its offer and offered the full amount of the SOWs ($3,063.06) plus an uplift of 15%, a total of $3,522.52 (minus the two excesses). After a further period of negotiation, on 10 September 2024 the insurer offered $6,000 (GST inclusive) in full and final settlement of the claim. Complainant said that she was also entitled to removal of slab and loss of rent On 5 March 2025 (and again on 11 April 2025) the complainant also said she was entitled to damage to the ‘broken subfloor piping and unsealed waste penetration gap’ and loss of rent. On 28 March 2025 the insurer maintained its position to not provide any cover for 'Loss of Rent' for the claim and reserved the right to re-consider the previous offer of $6,000.00. In support of her claim for damage to the broken subfloor piping and loss of rent, on 11 April 2025 the complainant said that ‘[i]nvestigation by [P] reported pipes in the bathroom walls and under the slab had become damaged/cracked’, that mould caused increased moisture levels in the subfloor, which had to be removed which required the tenants to be vacated (and loss of rent). However, the complainant acknowledged that ‘[g]iven the lapse in time, and the fact that repairs are already completed, it [was] not possible to confirm the extent of the moisture damage in the subfloor and which part was caused by the broken piping versus wear and tear’. On 11 April 2025 the complainant said that she did not ‘claim for the cost of subfloor repairs, (mould remediation costs cannot be estimated now as repairs are complete) but state[d] that the broken pipe caused the mould growth which necessitated the removal of the slab to remediate’. Insurer’s offer was fair and reasonable To resolve the claim on a cash settlement basis, the insurer offered more than the total of its itemised (and costed) SOWs for agreed damage to the hallway and kitchen in its final settlement offer of $6,000 (GST inclusive). The agreed SOWs totalled $3,063.06. Together with a 15% uplift for a cash settlement, the total would be $3,522.52. The insurer was entitled to deduct one excess at least i.e. $300. That total would be $3,222.52. The insurer offered $6,000 which was $2,777.48 more than the amount for the hallway and kitchen damage. Based on the information, including the lapse in time and the ‘bathroom renovation’ completed by the complainant, it was appropriate for the complainant to acknowledge the extent of moisture damage in the subfloor caused by broken piping compared to wear and tear could not be confirmed. Her acknowledgement was consistent with the report from P, on her behalf, which also did not make any such allocation. P had recommended a plumbing contractor be engaged to repair the broken bath waste but, unfortunately, provided no quotation for that specific work. As referred to above, the complainant originally claimed for a full ‘bathroom renovation’ - demolition and removal of the concrete slab, carpentry (new door), electrical, new drains, shower, toilet and vanity, bathroom fixtures, termite mesh, concreting, plastering, tiling, painting and shower screen. Based on the information, those items were extensive and, in practical terms, repaired the broken bath waste. However, they were not itemised by the complainant or its bathroom renovator. The insurer’s position on 26 September 2023 was that the cost to repair any long-term damage was not covered under the policy including the failure/no waterproofing, failed sealant, leak in the shower breecher, leak in the bath waste and rising damp due to the age and construction of the bathroom as these are the result of poor maintenance, unrectified water leaks, faulty workmanship and long-term gradual deterioration. However, it offered $6,000 on 28 March 2025 which was $2,777.48 more than the damage to the hallway and kitchen. Based on the information, I am satisfied that the insurer’s offer of $6,000 in full and final settlement was fair and reasonable. This is particularly in light of the complainant’s admission that ‘it [was] not possible to confirm the extent of the moisture damage in the subfloor and which part was caused by the broken piping versus wear and tear’ and that she did not claim for cost of subfloor repairs. The policy did not provide cover for wear and tear. The complainant’s plumber, P, said that the causes of the damage included ‘deteriorated seals in the wall tiles and no visible waterproofing membrane, no seal between the bath and wall tiles allowing water whilst showering to leak onto and pool on the bathroom floor’ which was gradual deterioration, depreciation, wear or tear. There was no obligation on the insurer to pay for damage which was caused by gradual deterioration, depreciation, wear and tear. However, it was fair the insurer did offer an amount in excess of the agreed damage for the hallway and kitchen. The insurer’s offer of $6,000 in those circumstances was fair and reasonable. In the event that the complainant accepts this Determination, the insurer should pay the amount offered by it ($6,000 (GST inclusive)) to the complainant within 14 days of receiving notice of the complainant’s acceptance of the determination and in full and final settlement of the claim. Cover for loss of rent in certain circumstances The policy provided for ‘Loss of Rent’ (page 14): If your Buildings are tenanted at the time the destruction, loss or damage occurs, and cannot be lived in by tenants after the destruction, loss or damage has occurred, we will pay up to 20% of your Building’s sum insured for your loss of rent or rentable value. Based on the information, the damage which was said to have first occurred in June 2022 (and during which time there were tenants in the property) did not result in the property being in a state where it could not be lived in by them. On the contrary, the complainant entered into a tenancy with the tenant in October 2022 and extended it in April 2023 for a further six months. The complainant therefore had a tenancy for a full six months from October 2022 to April 2023 and then extended it for a further six months to October 2023. In addition, on 18 July 2023 the complainant’s agent, B, gave notice of termination of the tenancy to the tenants and sought vacant possession on 16 October 2023 on the complainant’s behalf. The Form 3 (Notice of Termination) did not state (on behalf of the complainant) that the termination was necessary due to the need to conduct ‘repairs or renovations that cannot be carried out conveniently while the tenant remains in possession of the premises’. That was an expression which was expressly referred to in the Form 3. The complainant provided no information from the tenants advising the property was uninhabitable by them. Further, the Notice of Termination dated 18 July 2023 stated that a final inspection had been booked for 16 October 2023. However, the complainant did not provide an inspection report post the termination of the tenancy on 16 October 2023. The complainant said on 25 February 2025 that a provision of the Residential Tenancies Act 1995 (SA) meant that during repairs, the property did not meet minimum housing standards and could not be legally tenanted or rented. However, based on the information, that submission is not of any weight as it was the complainant who was the one who had terminated the tenancy in order to do a full bathroom renovation. Based on the information, the complainant has not established that at the time of the damage the property could not be lived in by the tenants due to claim related damage. In the circumstances, it would not be fair for the insurer to have to pay for loss of rent under the policy. Why is the outcome fair? The outcome is fair because the insurer is entitled to rely upon the exchanged material and the terms and conditions of the policy to determine its obligations regarding the claim and made a fair and reasonable offer to resolve the claim. Supporting information The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.