Home / Allianz Australia / Determination 12-00-1054105

Determination 12-00-1054105

Cyclone damage claim settlement method, cost and repair delays

FirmAllianz Australia
Decided2025-02-07
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant
Amount awarded$784,986
Non-financial loss$6,300
Amount claimed$759,386
SourceAFCA PDF

Summary

A farm owner represented by a family member disputed how a cyclone-damaged homestead claim should be settled after repairs were delayed for over two years. AFCA ordered the insurer to pay $784,986.44 plus s57 interest, and $6,300 non-financial loss.

Once the insured refused repairs by the insurer's builder, the insurer had to pay the reasonable cost of repairs, and the sum insured and code-upgrade limits did not apply because the insurer's delays caused the cost increase.

Issues

Subjects and remedies

home or building damagenatural disasterpay claimpay interestpay non financial loss

Related

All Allianz Australia determinations · Find similar determinations

Text of the determination

Determination | Case number | 12-00-1054105 | Financial firm | Allianz Australia Insurance Limited Case number: 12-00-1054105 5 February 2025 Determination overview Complaint The complainant holds a farm insurance policy with the financial firm (the insurer). On 15 April 2021, she lodged a claim for damage caused by a cyclone. Most aspects of the claim have been settled. However, the parties disagree on how to settle the part of the claim relating to the complainant’s home. In January 2022, the insurer authorised its builder to repair the home for $106,385.31. In September 2023, repairs had not started. The builder said the cost of repairs had increased to $679,386.44, mostly because of cyclone resistance measures required under new building codes from May 2023. In October 2023, the insurer said it would cash-settle the claim. In May 2024, the insurer offered to settle the claim by:  authorising its builder to repair the home for $679,386.44; or  paying the complainant a cash settlement of $466,636.44. From January 2022 to June 2024, the complainant agreed to have the insurer’s builder repair her home. From June 2024, she said:  she does not want the insurer’s builder to repair her home  the insurer should pay a cash settlement of $759,386.44  the insurer should pay $6,300 (the most AFCA can award) for non-financial loss. Issues and key findings How should the claim be settled? The complainant is not allowing the insurer to repair the home. Therefore, the only way for the insurer to settle the claim is by paying the reasonable cost of repairs. What is the reasonable cost of repairs? The best available estimate of the reasonable cost of repairs is $784,986.44. The insurer must pay this amount. The insurer is not entitled to apply the building sum insured ($776,475) or the policy limit for the extra cost of complying with building codes ($30,000). These limits were exceeded because of the insurer’s delay in starting repairs. Is the complainant entitled to compensation? The insurer delayed repairs by more than two years (from January 2022 to May 2024). This caused stress and inconvenience for the complainant. The complainant is entitled to $6,300 compensation for non-financial loss. Why is the outcome fair? It is fair for the insurer to pay for any loss covered under the policy, and for any loss caused by its errors. I am satisfied this determination provides the fairest possible outcome, based on the information provided by the parties. Determination This determination is in favour of the complainant. The insurer must pay $784,986.44 (including GST), plus interest at the rate determined under section 57 of the Insurance Contracts Act 1984 (Cth) from 9 October 2023, for damage to the home. The insurer may adjust this payment in accordance with the policy’s GST provision. The insurer must pay $6,300 compensation for non-financial loss. Reasons for determination How should the claim be settled? The complainant is not allowing the insurer to repair the home. Therefore, the only way for the insurer to settle the claim is by paying the reasonable cost of repairs. Policy says insurer can choose how to settle claim The cover provided by the policy is set out in the policy schedule and the product disclosure statement (PDS). Relevant policy terms are quoted in section 3.2 of this determination. The policy schedule says the basis of settlement for the subject building is ‘reinstatement or replacement’. Page 19 of the PDS says, where reinstatement or replacement cover applies, the insurer can settle a claim by:  repairing or rebuilding the building ‘to the same condition as when it was new’  paying the reasonable cost of repairing or rebuilding the building ‘to the same condition as when it was new’. The PDS says the insurer, ‘acting reasonably’, can choose how to settle the claim. The insurer initially said it would repair the home, then said it would pay a cash settlement. The insurer’s latest submissions say it has chosen to settle the claim by repairing the home. Indemnity provision does not apply Page 19 of the PDS says the insurer must pay the cost of restoring the building ‘to the same condition as when it was new’. However, page 20 of the PDS contains the following provision (the indemnity provision): 4. If We have chosen to repair or rebuild Your damaged Buildings and You do not wish to repair or rebuild them, We will at Our discretion (acting reasonably): pay You the reasonable cost to repair or rebuild Your damaged Buildings less an amount for depreciation based on the age and condition of the Buildings; or pay You the value of the land and Buildings at the Situation immediately prior to the occurrence of the loss or damage less the value of the land and Buildings immediately after the loss or damage occurred. The insurer says, if it has to cash-settle the claim, it is entitled to apply the indemnity provision. It has not calculated what the resulting settlement sum would be. It may be significantly less than the cost of restoring the building to the same condition as when it was new. The insurer says the indemnity provision applies if the complainant does not wish to have the building repaired or rebuilt by the insurer. That is incorrect. The indemnity provision only applies if the complainant does not wish to have the building repaired or rebuilt at all. The complainant says she wants her home to be repaired. Both parties describe the building as the ‘main homestead’. The insurer’s loss adjuster said the complainant was living in the building before the cyclone, and other family members moved in with her after the cyclone destroyed a smaller cottage on the property. The complainant says her family is still living in the building, and the unrepaired damage is causing them significant stress and inconvenience. The insurer does not dispute this. The insurer has not shown the complainant does not wish to have her home repaired. Therefore, the insurer is not entitled to apply the indemnity provision. According to the policy terms, the insurer must restore the home to the same condition as when it was new, or pay the reasonable cost of doing so. Insurer must cash-settle claim From January 2022, the complainant agreed to have the insurer’s builder repair her home. In a letter dated 12 March 2024, the complainant said she wanted the insurer to repair the home or pay a cash settlement. In a letter dated 6 June 2024, the complainant said the insurer’s offer to repair the home was ‘unacceptable’, because:  there was ‘no guarantee that the works would be done as per the quoted scope and values’ (the insurer says all work by its builder is guaranteed)  the work may be delayed by being arranged through the insurer rather than by her dealing directly with a builder  the insurer’s builder had poor online reviews, and this was consistent with her experiences with the insurer’s builder  the insurer’s builder was not local to her. She had decided to seek a local builder to do the work, because: > she was in a remote location which made it logistically challenging to arrange repairs > non-local builders did not understand the local market > non-local builders would need accommodation, which would increase costs > nearby property owners affected by the cyclone had negative experiences with non-local builders appointed by insurers. In a letter dated 25 June 2024, the complainant denied saying she did not want the insurer to repair the home. However, she went on to say the insurer’s builder had poor online reviews, and this was consistent with her experiences with the insurer’s builder, so she had ‘a local builder lined up to do the repair’. The complainant is not allowing the insurer to repair the home. The insurer cannot repair the home without the complainant’s consent. Therefore, the only way the insurer can settle the claim is by paying the reasonable cost of repairs. What is the reasonable cost of repairs? The best available estimate of the reasonable cost of repairs is $784,986.44. The insurer must pay this amount. The insurer is not entitled to apply the building sum insured ($776,475) or the policy limit for the extra cost of complying with building codes ($30,000). These limits were exceeded because of the insurer’s delay in starting repairs. Cost of repairs increased due to delay On or about 3 September 2021, the insurer’s builder quoted $106,385.31 for repairs to the home. The complainant said this was too low, but she agreed to allow the builder to start repairs. She says she was told the builder would submit a variation to the insurer if the cost of repairs was higher than quoted. She says repairs were scheduled to begin in November 2021. The insurer’s loss adjuster says:  on 28 January 2022, the insurer authorised its builder to repair the home for $106,385.31  on 28 March 2022, the builder advised they could not obtain a building permit because of a lack of detail in the engineering plans  on 1 August 2022, the builder submitted revised engineering plans to the local council  on 30 August 2022, the local council issued a building permit. The builder said it would start work in early 2023 because it could not source contractors before this  on 1 December 2022, it was announced that building codes would change from 1 May 2023. The new codes would require buildings in the complainant’s area to include cyclone resistance measures  on 20 February 2023, the builder had a ‘pre-start meeting’. The complainant asked that the repairs not start until after seeding in May 2023. The builder said they were not ready to start repairs because the engineering plans appeared to be incorrect  on 1 September 2023, the builder submitted a ‘revised’ quote for repairs. The quote was about $573,000 higher than the original quote. The builder said: ‘the majority of the variation is upgrades for legislative purposes’. The loss adjuster asked for a quote showing what work was required to comply with the new building codes. On 29 September 2023, the builder prepared a quote for $679,386.44, being:  $379,722.16 ($345,201.96 plus GST) for upgrades required for code compliance  $299,664.28 for other work. Insurer offered repairs or cash settlement Page 33 of the PDS contains a provision titled ‘Extra costs of reinstatement’. This provision says the insurer will pay up to $30,000 (in addition to the cost of repairs) for the cost of complying with building codes. On 9 October 2023, the insurer said the only way to settle the claim for damage to the home was to pay a cash settlement of $329,664.28, being:  $299,664.28 for repairs  $30,000 for the cost of complying with building codes. From 27 May 2024, the insurer offered to settle the claim by:  authorising its builder to repair the building for $679,386.44; or  paying the complainant a cash settlement of $466,636.44. It is not clear how the insurer calculated the cash settlement sum of $466,636.44. It said it was an estimate prepared by its quantity surveyor. The quantity surveyor’s report of 22 November 2023 estimated the cost of repairs at $445,361.40 ($404,874 plus GST). The insurer has not said why it is willing to pay its builder $679,386.44 for home repairs, but is only willing to pay the complainant $466,636.44 for home repairs. Insurer caused delay from January 2022 to May 2024 Repairs to the home have been extensively delayed since the insurer’s builder provided a quote for the repairs in September 2021. The insurer says it did not cause the delays. It says repairs were delayed ‘due to farming operations’ at the complainant’s request. The delay between September 2021 and January 2022 may have been due to a miscommunication. The complainant says she agreed to repairs in September 2021 and they were scheduled to begin in November 2021. However, in January 2022, the loss adjuster sent her an email saying: ‘We didn't receive your agreement to proceed so nothing was put in place for repairs to proceed.’ Delays from January 2022 to May 2024 occurred because:  there were problems with the engineering plans which were not rectified until August 2022  the builder could not source contractors between August 2022 and February 2023  there were further problems with the engineering plans which were not rectified until September 2023  the insurer did not authorise repairs between September 2023 and May 2024. The complainant said she did not want repairs done during seeding in May 2023. However, this did not cause any delay. The builder would not have been ready to start repairs until at least September 2023, and the insurer would not have authorised repairs until May 2024. Delays from May 2024 have occurred because the complainant has not allowed repairs by the insurer’s builder, and has not begun repairs with her own builder. The delays from January 2022 to May 2024 were caused by factors within the control of the insurer and its contractors, and outside the control of the complainant. The insurer is responsible for the delay in repairs from January 2022 to May 2024. Insurer must pay for increase in building costs The insurer’s loss adjuster says new building codes required cyclone resistance measures from 1 May 2023. The complainant provided an email from the Department of Fire and Emergency Services (a department of the Government of Western Australia) saying the new codes would not come into effect until 1 May 2025. The insurer says the new building codes have increased the cost of repairs by $379,722.16. This is the extra cost of complying with building codes, in addition to the cost of restoring the home to as-new condition (the required cyclone resistance measures were not part of the house when it was new). The policy covers the extra cost of complying with building codes. This cover is limited to $30,000. However, it would not be fair for the insurer to apply this limit. As stated above, the insurer is responsible for the delays in repairs from January 2022 to May 2024. If not for these delays, the complainant would not be required to comply with the new building codes. The increase in building costs was caused by the insurer’s delay in starting repairs. Therefore, the insurer should pay for the increase in building costs. Reasonable cost of repairs is $784,986.44 The insurer’s builder provided quotes to repair the home. The latest quote is dated 29 September 2023 and totals $679,386.44. Neither party provided repair quotes from any other builder. The insurer’s quantity surveyor estimated the cost of repairs at $445,361.40 and said the builder’s quote was ‘excessive’. However, the insurer offered to authorise its builder to repair the home in accordance with its quote and did not obtain another builder's quote. The quote of $679,386.44 did not include the cost of replacing the detached laundry/shed. The builder said the provisional sum allowance for this work would be $80,000, excluding builder’s margin and GST. The complainant says the insurer should pay a cash settlement of $759,386.44 ($679,386.44 plus $80,000 for the laundry/shed). However, the allowance of $80,000 did not include the builder’s margin or GST. The builder did not say what their margin was, so I have assumed a typical margin of 20%. $80,000 plus a 20% builder’s margin and 10% GST is $105,600. $105,600 plus $679,386.44 is $784,986.44. The information provided by the parties indicates the reasonable cost of repairing the home is $784,986.44. This is higher than the building’s sum insured of $776,475. However, the cost of repairs has exceeded the sum insured because of delays the insurer is responsible for. Therefore, it would not be fair for the insurer to limit its liability to the sum insured. No allowance for transfer of risk When an insurer settles a claim by repairing damage, it guarantees the quality of the repairs. If the repairs are unsuccessful, or cause additional damage, the insurer is responsible for the cost of rectification. When the insurer settles a claim by paying the cost of repairs, it transfers this risk to the customer. Furthermore, the customer may find it more difficult and expensive to arrange repairs, because they do not have the insurer’s industry knowledge and bargaining power. AFCA considers that if an insurer cash settles a claim, it should consider paying an allowance for the transfer of risk. Generally, AFCA considers that a reasonable allowance is likely to be between 5% and 25% of the quoted cost of repairs. The complainant has declined the insurer’s offer to repair the home. She has chosen to take responsibility for the repairs and forgo the insurer’s guarantee on repairs. Therefore, in this instance, the insurer is not required to pay an allowance for the transfer of risk. Insurer must pay interest Section 57 of the Insurance Contracts Act 1984 (Cth) says an insurer must pay interest on a claim settlement payment from the time it was unreasonable to have withheld payment. In the circumstances, I consider this to be 9 October 2023, the date it considered the builder’s latest quote and decided to offer a cash settlement of $329,664.28. The insurer must settle the claim for damage to the main house by paying $784,986.44, plus interest at the rate determined under section 57 of the Insurance Contracts Act 1984 (Cth) from 9 October 2023. Is the complainant entitled to compensation? The insurer delayed repairs by more than two years (from January 2022 to May 2024). This caused stress and inconvenience for the complainant. The complainant is entitled to $6,300 compensation for non-financial loss. AFCA can award compensation for non-financial loss Under the AFCA Rules, we can award up to $6,300 compensation for non-financial loss if a complainant suffered an unusual degree of stress, inconvenience, or delay because an insurer mishandled a claim. We will only award this type of compensation if there has been an unusual degree of stress, inconvenience, or delay. We will not award compensation for the usual amount of inconvenience involved in making a claim. We will not award compensation for delays caused by a complainant, or other factors outside the insurer’s control. Complainant entitled to $6,300 compensation for non-financial loss The insurer and its contractors were responsible for delays in repairs from January 2022 to May 2024. The complainant says the house is leaking in several locations, the ceiling fans are not working, and some of the ceilings are bulging and at risk of collapse. She says the poor condition of the house has severely compromised her quality of life for the last three years. The complainant’s home and farm were severely damaged by a cyclone. This would have caused severe stress and inconvenience even if the insurer did not mishandle the claim. However, the delays caused by the insurer and its contractors caused a significant degree of additional stress and inconvenience for more than two years. In my view, this warrants compensation of $6,300. Why is the outcome fair? It is fair for the insurer to pay for any loss covered under the policy, and for any loss caused by its errors. I am satisfied this determination provides the fairest possible outcome, based on the information provided by the parties. Supporting information The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. I have reviewed and considered all the information the parties have provided. While the parties have raised several issues in their submissions, I have restricted this determination to the issues that are relevant to the outcome. Complainant represented by family member or friend The complainant was represented by a family member or friend. In this determination, statements by the complainant’s representative are treated as if they were made by the complainant. Relevant policy terms Policy Schedule | Your Insurance Schedule (page 3) | Type of Policy Farm Pack | Section One - Home Property | Building 1 | [insured address] | Cover Type | Accidental Damage | Basis of Settlement | Reinstatement or replacement | Part A – Buildings and/or Contents | Sum Insured | Buildings | $776,475 | … | … Product Disclosure Statement | Section One – Home Property (pages 17 – 38) | Cover options The following cover options are available under Policy Section One: Part A – Buildings and/or Contents Under Part A, You may choose either Accidental Damage or Defined Events cover. Your Schedule will specify which Cover Option You have selected. If You have selected Accidental Damage cover, Your Schedule will show “Accidental Damage” If You have selected Defined Events cover, Your Schedule will show “Defined Events” Part B – Personal Effects; and Part C – Domestic Workers’ Compensation. | How We will settle Your Buildings claim 1. Reinstatement or replacement cover Where it is stated in Your Schedule that reinstatement or replacement cover applies. At Our discretion (acting reasonably) We will: repair or rebuild any damaged part(s) of Your Building to the same condition as when it was new; or pay You the reasonable cost of repairing or rebuilding any damaged part of Your Building to the same condition as when it was new; or pay You up to the amount of the Sum Insured. If We pay You the reasonable cost of repair or rebuilding, this means the cost of repairing or rebuilding. We will adjust Your claims payment in accordance with the GST provision under “General conditions – applicable to all Sections of this Policy”, “GST notice” on pages 13 to 16. When it is not possible to use original materials during the repair or rebuilding process, We will make best efforts to use the nearest available equivalent to the original materials. We will not pay to repair or rebuild property which has not been physically damaged. 2. Indemnity cover Where it is stated in Your Schedule that indemnity cover applies, We will at Our discretion (acting reasonably): pay You the value of Your Building which would have applied immediately prior to the loss or damage occurring, taking into account the cost of wear, tear and depreciation; or repair or rebuild any damaged part(s) of Your Building; or pay You the reasonable cost of repairing or rebuilding any damaged part of Your Building; or pay You up to the amount of the Sum Insured. We will not pay to repair or rebuild property which has not been physically damaged. We will extend this period to the extent that We caused or contributed to the delay. 3. Unless We have agreed in writing, repair or rebuilding of Your Building(s) must commence within six months of the loss or damage. We will extend this period to the extent that We caused or contributed to the delay. If rebuilding or repair of Your Building(s) has not commenced within this time or extended period to which We have previously agreed in writing, We will not be liable for any costs beyond the repair or rebuilding costs as at the date the loss or damage occurred. 4. If We have chosen to repair or rebuild Your damaged Buildings and You do not wish to repair or rebuild them, We will at Our discretion (acting reasonably): pay You the reasonable cost to repair or rebuild Your damaged Buildings less an amount for depreciation based on the age and condition of the Buildings; or pay You the value of the land and Buildings at the Situation immediately prior to the occurrence of the loss or damage less the value of the land and Buildings immediately after the loss or damage occurred. … | Other benefits We will pay under Part A – Buildings and/or Contents … 30. Extra costs of reinstatement (Applicable only if You have Buildings cover shown on Your Schedule) If Your Building(s) is damaged as a result of an event insured under this Policy, and We agree to pay a claim, We will pay up to $30,000 for the extra costs necessary to meet the requirements of any statutory authority in connection with re-constructing or repairing Your Building at the site. If only part of the Building is damaged, We pay only the extra costs You incur in repairing that part. We do not pay any extra costs which resulted from any notice which a statutory authority served on You if You were required to comply with the notice, and had not done so, before the Building suffered loss or damage. …

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.