Determination 12-00-1052808

Claim delays and claim-related temporary accommodation costs after water escape

FirmAuto & General
Decided2024-09-03
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$4,467
Non-financial loss$1,000
Amount claimed—
SourceAFCA PDF

Summary

A home and contents policyholder sought further temporary accommodation benefit because of repair delays after a water escape, plus non-financial loss compensation. AFCA found the repair timeframe reasonable, but ordered $4,466.77 for duplicated TA payments and $1,000 for stress and inconvenience.

The policy caps TA at 10 percent of the sum insured and the delays were not shown to be unreasonable, but duplicate payments and poor communication warrant compensation for stress and inconvenience.

Issues

Subjects and remedies

home or building damagepay claimpay non financial loss

Related

All Auto & General determinations · Find similar determinations

Text of the determination

Determination | Case number | 12-00-1052808 | Financial firm | Auto & General Services Pty Ltd Case number: 12-00-1052808 30 August 2024 Determination overview Complaint The complainant, together with his partner, holds a home and contents policy with the financial firm (the insurer). On 22 June 2023, the complainant lodged a claim following damage to his property due to an escape of liquid event. The insurer accepted the claim and commenced repairs of the property. The insurer paid the complainant the maximum temporary accommodation (TA) benefit in accordance with the terms of the policy, being 10% of the sum insured. The complainant is requesting additional TA he says is due to delays caused by the insurer’s trades in repairing the property. He seeks additional TA until the repairs are completed. The complainant also seeks compensation for the insurer’s poor claims handling and delays which he says has caused his stress and inconvenience. Issues and key findings Is the insurer required to pay additional TA costs? Yes. To a limited extent. The insurer paid TA costs, together with rental costs for the period 17 July 2023 to 28 July 2023. The insurer should not have duplicated the costs, and this contributed to the depletion of the TA allowance. The insurer should pay the complainant $4,466.77 in additional TA costs. Is the complainant entitled to non-financial loss compensation? Yes. The insurer is to pay the complainant $1,000 in non-financial loss compensation for stress and inconvenience. Why is the outcome fair? It has not been established that the complainant is entitled to further TA costs because of the insurer’s delays. However, it is fair that the insurer pays the complainant additional TA costs where it had incurred TA costs twice in a closed period. It is also fair that the insurer compensates the complainant for stress and inconvenience. Determination This determination is substantially in favour of the insurer. If the complainant accepts the determination, within 14 days of the insurer receiving written notification, the insurer is to: pay the complainant $4,466.77 for TA pay the complainant $1,000 in non-financial loss compensation. Reasons for determination Is the insurer required to pay additional TA costs? Yes. To a limited extent. The insurer paid TA costs, together with rental costs for the period 17 July 2023 to 28 July 2023. The insurer should not have duplicated the costs, and this contributed to the depletion of the TA allowance. The insurer should pay the complainant $4,466.77 in additional TA costs. Onus on complainant to establish a claimable loss The complainant is required to show, on the balance of probabilities (that it is more likely than not), that he suffered a claimable loss under the policy. This means he must show the loss was caused by a risk for which he is insured. Once the complainant proves the existence of a claimable loss, the insurer is liable for the loss unless it shows an exclusion or limiting condition applies. The insurer has the onus of proving, on balance, the application of the exclusion or condition. The terms of the policy include the Certificate of Insurance (COI) and the Product Disclosure Statement (PDS). There is no dispute the insurer sent these documents to the complainant. The policy was initially incepted on 26 April 2023, however, the complainant amended cover and a new COI was issued on 29 May 2023. The COI noted the complainant had not commenced occupation of the property. The policy covers damage caused by one of the listed events. It does not provide cover for all damage. Amongst these events is cover for escape of liquid. The parties do not dispute that the property was damaged when water escaped through water pipes in the ceiling which had been eaten by rodents. The property was extensively damaged by water throughout. I am therefore satisfied that the complainant has established that the loss or damage is a type covered by the policy. However, the coverage remains subject to the terms, exclusions and conditions of the policy. The policy covers TA subject to the policy conditions Page 41 of the PDS provides: Temporary accommodation costs Sometimes damage to your home and contents can mean you can’t stay living at your insured address. If your home becomes unliveable and we agree to pay your claim, we pay up to 10% of your home and contents sum insured for temporary accommodation. We will pay the costs of reasonable and appropriate accommodation for you, your family, and your pets while your home is being repaired or rebuilt. This is in additional to your home or contents sum insured. When you have Home Insurance and live in the insured home, the amount we will pay will be based on the weekly rentable value of your home. The insurer says: it has paid the complainant his full TA benefit under the policy of $27,500 the complainant was informed of his TA benefit as early as 4 July 2023 the complainant was provided with an estimate time for the repairs of approximately 6 months in early July 2023 the complainant was advised to seek a rental property for the duration of the repairs to minimise costs the complainant’s preferred suburb of A was more expensive than where his insured property was located the complainant advised that he wanted TA in A to be close to family- TA was approved on this basis the complainant was advised that his TA benefit would be more quickly exhausted in A. The insurer made a final payment to the complainant of TA on 10 November 2023. The complainant remained in TA while the repairs continued. Complainant seeks further TA The complainant says that: he was advised by the insurer that the repairs would be completed in November or December 2023 if the work was completed as suggested, he would not have incurred rent more than the policy limit a further leak identified in the master bedroom on 18 July 2023 contributed to the delays the insurer failed to commence repairs after the restoration works were completed on 23 August 2023 and the hygienist attendance on 29 August 2023 no construction started on the property until 20 October 2023 which was some 52 days after the restoration works were completed the builder caused further delays with work not completed until 15 March 2024, despite being told that they would be completed on 1 March 2024 as the insurer has caused delays, it should pay him additional TA until the repairs are completed. Insurer completed remediation and repairs The insurer says that the repairs have been completed in a timely manner. They say that it was a complex and large loss claim. The insurer appointed a builder PB to conduct initial make safe works which included make safe electrical repairs as the property’s electrical switchboard had been damaged in a separate event. On 17 July 2023, the insurer approved PB’s quote for restoration of the property which included strip out and drying. PB advised that on commencement of strip out, extensive mould had been found. A further leak located in the master bedroom. Drying times were noted to be slow. Restoration works were completed on 28 August 2023 and a hygienist was engaged to assess the remediation. On 8 September 2023, the insurer sought to obtain a second quote from PB. On 14 September 2023, the insurer accepted the quote from PB. The insurer at this time offered a cash settlement to the complainant. However, the complainant wanted the insurer to undertake the repairs. On 5 October 2023, the insurer authorised PB to commence repairs. The repairs have now been completed with the complainant moving back into the property on or around 15 March 2024. The insurer says that the timeframe for the completion of the repairs was reasonable and that there are no extenuating circumstances that would warrant the insurer paying TA costs outside of the terms of the policy. Insurer not required to pay additional TA due to delays The escape of liquid event was reported on 22 June 2023. It was unknown how long the water had been leaking as the property was vacant at the time. PB’s report noted that there were several sources of leaks as the rodents had created holes in numerous locations. The restoration works encompassed many rooms and the property was affected by mould. Drying was initially delayed as the property had also been subject to a theft claim with the electricity switchboard affected. Based on the available information, I am satisfied that on 18 July 2023 PB found additional moisture from an undetected leak in the master bedroom. This meant that additional drying was required. It was also noted by PB that it was difficult to dry the property and it installed a 3-phase generator in the garage to run a desiccant dehumidifier. This was also unexpected, and a variation was provided to the restoration quote. I am satisfied given the extent of the loss that it was reasonable for the insurer to obtain a second quote to ensure that the quote was accurate. This meant that there were some delays in the commencement of the repairs, however, I do not consider that this caused extensive delays. Given that the property was only completed in April 2023, it was reasonable that the insurer offered to cash settle the complainant, to allow him to engage his own builder to undertake the repairs. The complainant declined and the insurer engaged the builder PB shortly after. As the property was significantly damaged by water with mould present, it is reasonable to accept there would be unknown delays and variations to the scope of works. While an estimate was initially provided by PB of six months, it is not unusual for repairs to take longer, particularly in a large loss claim. The repairs were completed in March 2024 which is some 9 months after the insured event. However, significant time was taken to remediate the property prior to the commencement of the repairs. Having reviewed the exchanged information, I am satisfied that the insurer has conducted repairs in a reasonable timeframe. I am satisfied that the complainant was made aware of the limited TA benefit he had under the policy. The insurer emphasised to the complainant that his choice of a more expensive location for both TA and a rental property would deplete his TA benefit faster. The policy wording is clear and unambiguous. The complainant has the onus to ensure that the policy terms, including TA, were suitable for his needs. The complainant has not satisfactorily demonstrated why he is entitled to additional TA. I am not satisfied that there are any exceptional circumstances that would warrant the insurer paying additional TA beyond its policy terms. Insurer caused duplicate payments of TA As the building sum insured for the complainant’s home was $275,000, the maximum amount payable for TA costs was $27,500. The complainant was initially placed in TA. On 3 July 2023, approval was given by the insurer to extend TA until 28 July 2023 to enable the complainant to obtain a rental property. On 14 July 2023, the complainant provided the insurer a copy of a lease agreement for a property in A. The insurer raised a payment to the complainant of TA for the period 17 July 2023 to 17 August 2023. The claim notes record that despite the complainant obtaining a rental property, the insurer continued to pay TA until 28 July 2023. The insurer processed the invoice from HR, a third party who arranged the accommodation on 3 August 2023. This was for TA for the period 6 July 2023 until 28 July 2023 in the amount of $8,933.54. That is $406.07 per night. The complainant did not require both TA and rental accommodation. I accept that the complainant was also not able to cancel the TA. In the circumstances, I am satisfied that it is reasonable that the insurer should reimburse the complainant for these duplicate costs. That is, from 17 July 2023 to 28 July 2023, being a total of 11 nights at $406.07/night. A total amount of $4,466.77. Is the complainant entitled to non-financial loss compensation? AFCA can award compensation for non-financial loss Under the AFCA Rules, we can award up to $6,300 compensation for non-financial loss if a complainant suffered an unusual degree of stress, inconvenience, or delay because an insurer mishandled a claim. Insurer has caused stress and inconvenience The complainant says that the insurer’s poor claims handling has caused him stress and inconvenience. He says that he has incurred additional financial costs that have caused stress and financial hardship. He also says that the insurer has failed to communicate with him in a clear and timely manner. He says that he was required to continually chase the builder PB to obtain updates and timeframes for completion of works. The insurer says that it has already paid the complainant $1,500 in non-financial loss compensation on an ex-gratia basis in recognition of its claims handling. I am satisfied that the insurer has been transparent in its communication with the complainant. However, noting the complainant’s circumstances of paying his own TA, more regular updates would have assisted the complainant. I accept that because the insurer duplicated payments of TA this caused the complainant undue stress and inconvenience. It meant that the TA was depleted faster than anticipated and the complainant incurred rental costs. I am also satisfied that poor communication regarding the completion date of the repairs has caused further stress and inconvenience to the complainant. In these circumstances, the insurer should pay the complainant $1,000 in non-financial loss compensation. Why is the outcome fair? It has not been established that the complainant is entitled to further TA costs because of the insurer’s delays. However, it is fair that the insurer pays the complainant additional TA costs where it had incurred TA costs twice in a closed period. It is also fair that the insurer compensates the complainant for stress and inconvenience to the complainant. Supporting information The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to: the legal principles applicable industry codes or guidance good industry practice previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. I have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, I have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider: available documents the recollections of the parties all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established. Claims in relation to building defects not considered The complainant has raised complaints in relation to building defects as part of his submissions to AFCA. These issues have not been considered in this determination.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.