Determination 12-00-1042387
Storm damage roof and internal repair dispute
Summary
The complainant sought further storm-related roof, eave and internal repairs and compensation for delays and repair quality. AFCA required the insurer to cash settle some eave and fascia repairs, fix silicone and insulation issues, and pay $2,500 non-financial loss.
Damage must be linked to the storm, the insurer's repairs or its claim handling, and wear and tear and non-event damage fall outside cover for the other claimed roof items.
Issues
- Claim denial primary · upheld“insurer must repair the water damaged eave, fascia and timber work above the laundry door; other claimed roof items declined”
- Delay secondary · not upheld“two-year repair process was not unreasonable given the overall scope of works”
- Poor communication secondary · upheld“claim notes and correspondence show instances of poor communication with the complainant”
- Repairs or contractors secondary · upheld“insurer must remove the silicone left on the shower screen and ensure new insulation is laid properly”
Subjects and remedies
home or building damagenatural disasterpay claimpay non financial lossrepair or rectify
Related
Text of the determination
Determination
|
Case number
|
12-00-1042387
|
Financial firm
|
RACQ Insurance Limited
Case number: 12-00-1042387 29 November 2024
Determination overview
Complaint
The complainant held a home and contents insurance policy with the financial firm (insurer). Following a severe storm, on 1 March 2022 she lodged a claim for roof and water ingress damage to the property.
The insurer partially accepted the claim and completed external (roof) and internal repairs, mould remediation and cash settled the complainant for damaged contents.
The complainant is dissatisfied with the repairs. She says the insurer should conduct further repairs including further repairs to the roof which leaks and repairing the eaves and fascia on the south side of the property. The insurer does not dispute the roof leaks but disputes liability for that and other repairs.
The complainant also wants the insurer to remove silicone outside of main shower screen, remediate the blocked drain in the shower and seeks compensation for non-financial loss.
The complainant is represented in this dispute. For simplicity, the complainant and her representative are referred to as ‘the complainant’ in this determination.
Issues and key findings
Is the insurer liable for additional roof repairs?
Partially. The insurer is not required to cover the leaking tiles clips and obstructed tiles laps, repair the missing tile clips, two damaged tiles, veranda beam and front valley board or install sarking because the available information shows these are not event related or arising from insured repairs.
However, the insurer must repair the water damaged eave, fascia and timber work above the laundry door. It must also remove any old insulation material and adequately relay the new insulation material inside the entire roof cavity.
Is the insurer liable to investigate outstanding internal repairs items in dispute?
Yes. The insurer must remove the silicone left on shower screen. If it has not already done so, it must also arrange assessment of the blocked drain in the main bathroom and conduct repairs if the blockage was due to the storm or its repairs.
Is the complainant entitled to compensation for non-financial loss?
Yes. The insurer must pay the complainant $2,500.00 non-financial loss compensation.
Why is the outcome fair?
The outcome is fair because it requires the insurer to repair all damage that is related to the storm, its repairs or claim handling delays. It would be unfair for the insurer to be required to repair items that are not due to storm, the insurer’s actions or excluded by the policy terms.
Determination
This determination is partially in favour of the complainant.
If the complainant accepts this determination, the insurer must:
cash settle the complainant for repairs to the following elements along the southern elevation: water damaged, sagging and/or rotten: eave, timber framing and fascia above the laundry door
remove all old insulation material and ensure new insulation is laid properly throughout the roof cavity
remove the silicone on the shower screen, if it has not already done so
investigate the blocked drain in the main bathroom and conduct repairs if the blockage was due to the storm or its repairs
pay the complainant $2,500 non-financial loss compensation.
The insurer is not required to take further action.
Reasons for determination
Is the insurer liable for additional roof repairs?
Partially. The insurer is not required to cover the leaking tiles clips and obstructed tiles laps, repair the missing tile clips, two damaged tiles, veranda beam and front valley board or install sarking because the available information shows these are not event related or arising from insured repairs.
However, the insurer must repair the water damaged eave, fascia and timber work above the laundry door. It must also remove any old insulation material and adequately relay the new insulation material inside the entire roof cavity.
Complainant has onus to establish a valid claim
When making a claim, the complainant has the onus of establishing, on the balance of probabilities (i.e. that it is more likely than not), that they suffered a loss which is covered by the insurance policy).
There is no dispute the storm damaged the complainant’s roof causing water ingress and resultant internal damage. However, a dispute has arisen about the extent of the roof damage and whether the insurer should be liable to cover additional roof repairs.
The onus rests with the complainant to establish the damage was either caused by the claimed event, inadequate make-safe, the insurer’s delays with the repairs or the quality of its repairs.
If a claimable loss is established, the onus shifts to the insurer to establish, on the balance of probabilities, it is entitled to rely on an exclusion to decline the claim. The relevant sections of the policy are set out at section 3.2 of this determination.
Insurer agreed to repair the roof
The complainant lodged a claim on 1 March 2022 following the February 2022 storms involving significant rainfall, resulting in water ingress inside the home.
The insurer completed a make-safe between March 2022 and June 2022. Its builder, JL, applied sealant on two broken tiles and the front junction ridge capping and taped the capping at the back of the house.
The insurer’s roofer, NL, inspected the house on 28 June 2022 and found:
the roof to be in a poor condition
cracked and deteriorated pointing on ridge capping throughout the roof
one damaged tile above the living room towards the gutter and two damaged tiles above the bathroom
wet batten and trusses underneath ridge capping and damaged tiles
the internal damage is due to deteriorated and cracked pointing on ridge capping and three damaged tiles allowing water ingress to the roof cavity.
The insurer accepted liability for internal damage and declined cover for the roof saying the damages were not the result of the storm. It later acknowledged the tile damage was likely due to falling branches during the storm and offered to cash settlement for that damage. It maintained its claim decline for the ridge capping saying this was due to wear and tear and not event related.
To assist the complainant and avoid further delays with the internal repairs, on 4 November 2022, the insurer agreed to perform the tile repairs and, outside the policy terms, repair the deteriorated ridge capping.
Insurer undertook roof repairs
The roof repairs (the first repairs) were completed on 21 February 2023. On 23 March 2023 JL completed a further roof inspection and reported:
the roof is in average overall condition
one slightly raised tile under mortar ridge cap near front valley
one cracked barge tile at rear of right and side gable below solar panel
extensive wood rot to front valley board that appears very aged and deemed slow and gradual
heavy silicone application where the valley joint dissects.
JL recommended:
removing roof tiles in valley iron joint dissection point vicinity and investigating this as well as valley board pitch and
replace two barge tiles.
The insurer completed the following additional roof repairs (the second repairs) between 23 March 2023 and 19 May 2023:
replace barge capping and
fix leak in the valley tiles.
After the completion of the second repairs JL told the insurer the roof was ‘watertight’ and internal repairs could commence. The insurer informed the complainant accordingly by email on 26 May 2023. I note that the external roof repairs were adequately completed.
Complainant is not satisfied with the insurer’s repairs
The complainant is not satisfied with the repairs. She says the roof never leaked before the storm and wants the insurer to complete additional repairs to prevent it from leaking again. The complainant has pointed out issues with the roof but has not specifically advised what works are required. She relies on issues raised by, and the expert report from, the owner and operator of a fencing and property maintenance business, MP. MP is licensed by Queensland Building and Construction Commission (QBCC) who has worked in the building industry for over 15 years.
Complainant has not established a valid claim for further tile damage
The complainant says that there is one outstanding cracked tile above the bathroom area which is not on the bottom row. She provided undated photographs showing a diagonal crack in the bottom left corner. MP says there are broken tiles left on the roof and has provided photos of two damaged tiles. It does not say where these tiles are or when the photos were taken.
The insurer’s most recent roof report was provided by plumber, TB, who inspected the property in September 2023 (before MP’s report). TB shows there is a broken tile lap with bottom right corner missing near the bathroom and laundry area on the bottom row. There is insufficient information to establish if the bottom tile identified in each report is the same or a different tile.
On balance, I am satisfied there are two damaged tiles above the bathroom laundry area, a broken one on the bottom row and a cracked one above the bottom row.
The insurer says the damaged tiles are not event or repair related. The complainant says this could be due to the storm or the insurer’s trades when they were on the roof.
The bathroom was one of the most severely damaged internal areas. The bottom row broken tile was not identified by the insurer’s experts during any of the three roof inspections/assessments or during the repairs until TB’s inspection in September 2023. The other cracked tile above the bottom row was never identified by any of the insurer’s experts or trades.
Leak detection specialists, NL, inspected the roof on 28 June 2022 and found one broken tile above the bathroom area. That tile was replaced during the first roof repairs completed around February 2023. There is no mention of any damaged tile above a bathroom in any of the insurer’s roof attendances or the insurer’s trades who were completing repairs at the property except for TB’s report which identifies the bottom row broken tile.
Further, there is no information about it when the complainant discovered the cracked tile above the bottom row. It was never identified by any of the insurer’s experts or trades even though they knew the bathroom was one of the most water damaged rooms. This indicates that the tile cracked after the original event and the insurer’s experts and trades’ subsequent attendances.
On balance, I am not satisfied the complainant has established that the two tiles were damaged either as result of the storm, during the repairs or roof inspections. Rather, I accept these tiles were damaged after the completion of the second repairs. Given the overall age and condition of the tiles, it is more likely than not that these tiles cracked and broke due to wear and tear.
Accordingly, the complainant has not established a valid claim for the broken tiles and the insurer is not required to repair that damage.
Storm or claims handling not shown to have damaged main roof structure
The complainant relies on MP’s report which says the inadequate make-safe, tiles left unrepaired and delays with repairs caused ongoing water exposure leading to the trusses sagging throughout the roof. She also says this caused damage to the eave (preventing the laundry screen door opening and closing) and veranda beam.
The insurer appointed engineer, IL, to investigate any structural damage to the roof. IL inspected the property and says:
‘the lack of any distress to the nail plates and the lack of any distinct separation of the timber trusses at the nodes would further confirm that any sag in the trusses has not been caused as a result of any structural failures, especially a one-off wetting’
roof framing timber components naturally deflect over a long period of time due to a process of creep which is the natural deflection over time inherent to timber material
the extent of the timber trusses deflection observed is consistent with long term timber creep
‘there was no evidence that any structural damage or distress had occurred to the timber trusses as a result of the water ingress into the roof cavity during the February 2022 storms. Rather any or minor slight curvature in the timber trusses can be attributed to long-term creep’
the minor creep of the trusses, in combination with the localised settlement of the foundations at the west end of the dwelling (in particular to the south-west corner) and misalignment of the fascia has likely resulted in reduced clearances between the top of the doors and external fascia, which has caused the laundry fly-screen door to catch
the veranda perimeter beam exhibited a minor warp and rotation. No separation or displacement of the rafters was evident at the junction with the dwelling. The minor warping is not due to the storm event but rather to its exposure to the elements on account of its location
floor level survey shows floor levels are slightly uneven with lower floor level to the southwest corner of the house where master bedroom is located with overall 50mm variation observed
‘given there was no distinct cracking to any of the external brickwork and internal finishes […] the foundation settlement in this area has also occurred gradually over a long period of time and there is no indication that this was caused as a result of a one-off wetting from the heavy rain in February 2022.’
MP disagrees with IL’s findings and includes the following points:
there is an obvious sag in the bottom row of tiles nearly the whole way along. MP supports this with a photo of the bottom row of tiles on the southern side of the property
IL’s report focuses on the trusses at the centre of the roof rather than the area near the bathroom and ensuite where the water caused the ceiling to collapse
the amount of daylight shown in IL’s photos is significant and not something that would ordinarily be found in a sealed and repaired roof
the detached tile clips referred to by IL show that the insurer did not properly repair the roof
IL’s methods of measuring the vertical trusses was highly questionable. MP refers to its own measurements, however, these were not provided
MP disagrees with IL’s observations about the ground levels around the house and referred to its own measurements. These were not provided either.
Having considered the exchanged information, I am not persuaded that the storm or insurer’s claim handling caused significant movement of the timber framework in the main part of the roof. That is because:
I generally accept IL’s report over MP’s. IL is independent, has relevant qualifications and experience and includes analysis and photos supporting its findings. MP is a friend and neighbour of the complainant, and the report is from MP personally, rather than from a contracting organisation
I accept IL’s findings that the movement of the trusses through the main roof is consistent with timber creep
IL confirms that the nail plates were still attached, and the measurements and photos did not indicate structural damage or distress to the timber trusses
I accept NL’s findings that the ridge capping was deteriorated and cracked throughout the entire roof. On balance, I accept that damage would have been present for some time before the storm, allowing water to enter the roof cavity. The complainant has not shown that the insurer’s inadequate make safe or delay caused damage to the timber framework
the timber creep found by IL is minor. The exchanged information does not show this has adversely affected the functionality or appearance of the roof or caused it to leak. Rather the information shows the roof will continue to leak because of leaking tile clips and obstructions within the tile laps as identified in TB’s report.
Therefore, I am satisfied that the complainant has not established damage to the main timber roof frame is due to storm, the insurer’s repairs or its claims handling.
Ongoing roof leaks not due to storm
After completion of the second roof repairs, the complainant complained that the roof was leaking. She says that it must be due to the storm, the insurer’s repairs or its delay because the roof did not leak before. Having carefully considered the exchanged information I am satisfied that the complainant has not established a valid claim for this damage. That is because:
the broken tiles caused by the storm were repaired by the insurer
following the insurer’s repairs, on 5 September 2023 TB carried out leak detection tests on the roof. TB found that the roof is not sarked and will continue to leak during heavy rain due to old blow insulation debris obstructions in the tile laps and [absence/detachment of] tile clips. The location of the leak is below the ridge from the middle of the roof towards the bathroom and laundry area
IL reported missing tiles clips in its report and the information shows they should be remediated to avoid tiles lifting during strong weather conditions
the available information does not show whether the missing tiles clips were ever installed or if they were, when they detached or went missing. On balance, I am satisfied that the insurer is not responsible for this. The insurer’s roof repairs were limited to replacing approximately five damaged tiles away from that area and repairing the ridge capping. The areas with the detached/missing tiles clips, are located in a different area from where the insurer completed its repairs
the blow in insulation pre-dates the insurer’s roof repairs. The exchanged information does not show that the storm or the insurer did anything that would have caused that material to obstruct the tile laps
I do not accept the complainant’s position that the insurer needs to rectify any leaks in the roof because the roof did not leak prior to the storm. I am not satisfied the complainant has shown any factor causing the roof to leak that was caused by the storm or the insurer’s claim handling
I do not accept MP’s position that the insurer was responsible for rectifying the tile clips because it had ‘possession of the property for the rectification work’.
Accordingly, the insurer is not required to remediate the leaking tiles clips and obstructed tiles laps or any further roof repairs other than set out in this determination.
Insurer is required to repair water damage on southern part of property and remediate insulation
The complainant says the insurer should repair the damaged eave, fascia and water damaged timber framework. She says that damage was caused by the storm and the insurer’s delay. The complainant relies on MP’s report that says:
the fascia and eave by the bathroom/ laundry area were damaged during the storm
there is a large diagonal crack across the eave near the laundry door, and provides a photo
this damage worsened due to the insurer’s delays with repairing the roof, causing the roof trusses to sag
the insurer did not repair the eave or sagging fascia despite the complainant’s requests
the eave still has moisture due to the original event and the insurer left old insulation material above the eave that has rotted
MP removed the eave near the laundry and bathroom and found mouldy old insulation material and dry rot at the end of the trusses and framing – supported by photographic evidence
there is dry rot at the end of the trusses and framing consistent with the insurer leaving water damaged blow insulation material above the eave for 2 years
MP says that that the bottom row of tiles on the southern elevation is clearly warped and provides a photo showing that.
the insurer did not adequately investigate or assess this area despite accepting the storm damage and completing roof and internal repairs.
The insurer has not commented on MP’s report.
On balance, I am satisfied that the proximate cause of this damage is the storm and the insurer’s claim’s handling delays. It should therefore be repaired by the insurer. That is because:
two of the three cracked roof tiles identified in JL’s June 2022 report, and accepted as storm related, were above this area
I accept the eave was initially damaged by the original event as it is directly adjacent to the most severely damaged rooms inside the house
I accept the eave area was left unrepaired with old wet insulation material above it as this is shown by MP’s photos
the sagging materials and dry rot at the end of the trusses and framing is consistent with the insurer leaving water damaged blow insulation material above the eave for two years
I accept that the second photo in MP’s report shows sagging in the bottom row of tiles on the southern side of the property. IL’s photo 7 shows this area and reports no sag to the roof line or tiles. I do not find photo 7 helpful as it is taken from the ground and at a greater distance
IL notes the misalignment of the fascia at this location has caused the top of the laundry fly-screen door to catch on the bottom of the fascia. IL says the reduced clearance is due to ‘minor creep of the trusses, in combination of the localised settlement of the foundations at the west end of the dwelling (in particular the south-west corner) and misalignment of the fascia’. I am not persuaded by IL’s explanation because:
> it does not account for the cracked and sagging eave immediately between the door and the fascia, and near the worst of the water ingress damage from the storm, nor does it contemplate the old insulation that was left in the area
> it does not explain why settlement of the foundations would cause the differential movement in the property insofar as the door height remained the same level (or rose) and/or the fascia dropped relative to the height of the door
> it does not explain how and why the fascia is misaligned, and
> it does not consider that the timing of this damage was the same as the other accepted storm damage.
JL’s June 2022 report shows that during heavy rains, some leaking will occur below the ridge on this side of the roof due to the obstructed tile laps and detached/missing tile clips. However, I am persuaded the greater water ingress was from the storm-caused cracked tiles. Further, the exchanged information does not show that this damage was present before the storm.
Therefore, I am satisfied the complainant has established a claimable loss for this damage. I am not satisfied that the insurer is entitled to rely on exclusions to decline cover for this part of the claim. The insurer is required to remediate the damage to the roof timbers, eaves and fascia outside the bathroom and laundry and to the extent it is damaged along southern side of the property. This includes:
remediating the rot at the end of the trusses and any other water damaged timber framing
repairing the eaves on the southern side of the property, including the part removed by the complainant
repairing the fascia on the southern side of the property where misaligned or otherwise damaged
remove any old blow insulation material left within the roof cavity
I note that the complainant has not reported water ingress since she moved back into the property in January 2024. However, as the information shows heavy rain may cause the roof to leak on this side of the property, repairers may not be able to warranty this discrete work. It is reasonable, in the circumstances, that the insurer can choose to cash settle this work.
Insurer’s laying of insulation material to be rectified
The insurer’s repair work included replacing the insulation material. It is clear from photographic evidence of the roof cavity provided by TB and IL that the new insulation material has not been laid properly throughout the overall surface of the roof cavity. Therefore, the insurer must ensure the insulation is laid in an adequate manner.
Complainant has not shown veranda perimeter beam damaged by the storm
I am not persuaded that the veranda perimeter beam was damaged by the storm or the insurer’s delay. IL’s described it as having a minor warp but still connected to the pier. Its photos 8 and 9 show the beam is toward the outer edge of the veranda and therefore exposed to the elements. MP disputes IL’s description as a ‘minor warp’ and provides a photo showing significant deflection in the timber. It is not clear the beam in MP’s photo is the same one IL reports on. From the exchanged information, I am satisfied that, the warp is minor and, given the location of the beam, the complainant has not established that the veranda beam was damaged by storm.
Complainant has not shown front valley board was damaged by storm
MP says that, when doing the repairs, the insurer should have replaced the front valley board in order to meet Australian Standards. JL’s roof inspection report dated March 2023 says the front valley board show signs of extensive wood rot that appears very aged. Given the extent of the wood rot and considering the age of the building, I am satisfied this damage is consistent with gradual deterioration over time and is not related to the event, make safe or delays with the repairs. Therefore, I am satisfied the insurer is not liable to cover this damage.
Daylight visible from within roof cavity not event or repairs related
MP says there is daylight visible from within the roof cavity, which is inconsistent with a ‘sealed and repaired’ roof. However, I am not satisfied that the insurer is required to cover this because:
the complainant has not shown this was caused by the storm, the insurer’s repairs or the insurer’s claims handling
the insurer’s reports confirm the insurer’s first and second repairs were completed to satisfaction and in accordance with Australian Building Standards. This is supported by photographic evidence from the first roof repairs and TB’s report that identified no leaks in the areas repaired by the insurer including the valley area which was an area of concerns where daylight could be seen from the roof cavity
JL says that seeing daylight from the roof cavity is not unusual when the roof is not sarked and is not an issue in itself.
Accordingly, the insurer is not liable to remediate this (including by installing sarking).
Information shows storm caused mould has been remediated
The complainant says that she needs to be sure that no further mould or moisture is present in the house. She relies on environmental scientists, CD’s post remediation verification report 30 October 2023 that says:
gyprock in the north-west corner of the dining room recorded moisture meter concentration reading of 18.3%. Based on that, it says the base plates in that area may not have been properly dried before the insurer relined the walls
it was unable to test the toilet area, but the base plates under there may also be damp
where baseplates have not been dried, there is a high probability that the area will be impacted by wood rot or corrosion
its evaluation of five air samples had a normal mould ecology
surface sampling could not be completed as walls had been reinstated
The insurer’s restoration consultants, RI, says that its certified microbial investigator provided a certificate of post remediation verification, during the site assessment on 12 October 2023. It says no elevated moisture content recorded to retained materials in these areas. It says this indicates that adequate remediation has been completed to the living room, kitchen dining room and toilet. Further, it says that any elevated moisture in the dining room base plate is unrelated to the storm.
RI also reports on factors likely to lead to an elevated moisture level in the base plates in these areas that are unrelated to the storm or the insurer’s repairs. These include lack of site drainage, condensation and inadequate drainage of the roof valley over the veranda.
On balance, I am satisfied that the exchanged information shows the insurer adequately remediated the property for storm-related moisture and mould. That is because:
RI’s certificate of post remediation verification shows that the remediation met the appropriate standards including surface sampling showing acceptable biological surface cleanliness
CD’s air samples had a normal mould ecology
I have given limited weight to RI’s information about site drainage and roofing as it has not explained its expertise in these fields. However, I am satisfied the complainant has not established the insurer’s repairs have not adequately dealt with the claim related mould and moisture. Accordingly, the insurer is not required to do anything further in relation to this other than the work set out in this determination.
Is the insurer required to remediate its repairs?
Yes. The insurer must remove the silicone left on the shower screen. If it has not already done so, it must also arrange assessment of the blocked drain in the main bathroom and conduct repairs if the blockage was due to the storm or its repairs.
Insurer must complete investigations and attend to outstanding issues
The complainant raised issues with the repair quality of numerous internal repairs items. These have been resolved except for the silicone on the shower screen and the blocked drain in the main bathroom which was raised late in the complaint.
The insurer said it would investigate the blocked drain and with a view to remediating it. If the insurer declines to remediate the blocked drain or complete the repairs but these are unsatisfactory, the complainant can lodge a new complaint if the dispute cannot be resolved.
The complainant says the silicone outside the main shower must be removed as it was not wiped off by trades. The insurer must attend and remediate any silicone left on the main shower door, if it has not already done so.
Is the complainant entitled to compensation for non-financial loss
Yes. The insurer must pay the complainant $2,500.00 non-financial loss compensation.
AFCA can award up to $5,400 compensation for non-financial loss
AFCA may award compensation for non-financial loss (capped at $5,400 for complaints received before 1 January 2024) where the insurer’s actions have caused an unusual amount of:
physical inconvenience
time taken to resolve the situation
interference with the complainant’s expectation of enjoyment or peace of mind.
We take a conservative approach to compensation and expect a complainant to bear a normal degree of inconvenience during a claim.
Information shows there were claim delays and issues with repairs The complainant is dissatisfied with the overall claim delays and the quality of the repairs, including internal repairs for which a number of items required further attendances. She says the overall process has caused her and her family a significant amount of stress and inconvenience and has put pressure on the marital relationship. The insurer has provided limited information about the make safe and acknowledges that, other than the make safe, it did not do a formal roof inspection until four months after the storm.
The overall repair process took approximately two years. I accept two years is a long time, however when considering the overall scope of works it is not unreasonable. Additionally, the insurer covered temporary accommodation well over the policy limits to mitigate this.
I accept not all the internal repairs were completed to satisfaction and the complainant had to raise this with the insurer. Most have been rectified either by the insurer or the complainant herself.
I have also reviewed the claim notes and the correspondence between the parties, and I am satisfied they were instances of poor communication with the complainant.
The insurer acknowledges the complainant’s claim experience and offered to pay $2,500 in compensation for the overall claim experience. Considering our conservative approach, and the fact that the insurer covered temporary accommodation well above the policy limit, I am satisfied this amount is fair and reasonable in the circumstances.
Accordingly, the insurer should pay the complainant $2,500 for compensation for non-financial loss.
Why is the outcome fair?
The outcome is fair because it requires the insurer to repair all damage that is related to the storm, its repairs or claim handling delays. It would be unfair for the insurer to be required to repair items that are not due to storm, the insurer’s actions or excluded by the policy terms.
Supporting information
The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all the information the parties have provided.
While the parties have raised several issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.
Supporting information
Relevant policy wording
The policy is a listed events policy, page 28 of the of the Product Disclosure Statement (PDS) says:
Insured events
We cover loss or damage to your home or your contents that is caused by certain events, these events are set out in table ‘Insured events’ on page 29.
For us to cover you for loss or damage the event must happen:
• at the insured address, and
• during the period of insurance.
The general exclusions shown on pages 76-80 apply to all areas of this section.
Page 36 of the PDS sets out the cover for storm:
You are covered for:
Loss or damage to your home or your contents caused by a storm. For example, a cyclone.
This cover is subject to specific and general exclusions.
The General Exclusions are set out at page 75 and following of the PDS and include:
Loss not linked to event
You are not covered for:
Loss or damage to your home or your contents which can’t be linked to any identifiable insured event (but we do cover you if you have an optional benefit under ‘Items away from home’ – see page 67).
Items which you have misplaced (but we do cover you if you have an optional benefit under ‘Items away from home’ – see page 67).
…
Wear and tear
You are not covered for:
Loss or damage caused by wear and tear through normal use.
…
Your responsibility
You are not covered for:
Loss or damage caused by you not maintaining your home and contents in good condition, or not keeping your home and your contents safe and secure.
The PDS defines good condition at page 110 -111 as follows:
Good condition
Good condition means your insured home and contents are well maintained, free from material damage, decay, and defects that could reasonably be expected to increase the risk of loss or damage that contributes to or is caused by an insured event. This includes but is not limited to the home having:
• a sound and solid structure with no leaks, holes, or rot,
• roof and gutters that are securely attached to the building with no damage, rust, signs of deterioration or excess debris,
• exterior walls, windows, paths, paving and outdoor structures that have no peeling or damaged paintwork, settlement cracks, shifting or subsidence, deteriorating timber or cladding, missing / broken glass, or missing grout or cement in brickwork,
• stairs, railings and fences that are intact with no missing panels, deteriorating timber or visible damage,
• no damage from or infestation of termites, ants, birds, or vermin,
• no squatters or unauthorised persons living in the home.
The policy provides a lifetime warranty on repairs completed by the insurer subject to exclusions. This cover is set out at page 53 of the PDS:
You are covered for:
The cost to fix any faulty workmanship resulting from repairs if:
• you made a claim with us, and
• if the repairs were completed by a repairer authorised by us, and
• you or your family still own your home or your contents.
You are not covered for:
The repairs to your home or your contents fail because of:
• wear, tear, and gradual deterioration,
• movement of your home.
Damage that is caused by your or someone else’s negligence after the repairs were completed.