Extent of insurer's liability for defective repairs and movement damage after accepted flood claim
Text of the determination
Determination
|
Case number
|
12-00-1041430
|
Financial firm
|
AAI Limited
Case number: 12-00-1041430 27 June 2025
Determination overview
Complaint
The complainant held a home insurance policy with the financial firm (insurer). In early 2019 she lodged a claim for flood damage to the property which was accepted by the insurer.
The complainant says the repairs completed by the insurer’s builder were faulty and caused further damage to the property. The insurer acknowledges there is some damage due to faulty workmanship and has paid the complainant $19,677.90 for outstanding repairs.
A dispute has arisen over the extent of the insurer’s liability for rectification costs. The insurer says cracking and movement to the house and granny flat was due to differential movement.
The complainant disputes the insurer’s decision and wants the insurer to pay her the amount shown in the scope of works prepared by her engineer, being approximately $350,000. She also seeks a reimbursement of costs incurred by her and compensation from the insurer.
Issues and key findings
Is the insurer required to pay for the movement damage?
Partially. The complainant has shown that defective works by the insurer’s builder caused or contributed to movement damage to the house. However, there is no persuasive evidence that the insurer is liable for movement damage to the granny flat.
Is the insurer required to pay further rectification costs?
Yes. There were defects with the repairs by the insurer’s builder. The cash settlement paid by the insurer is inadequate to cover the cost of rectifying all defects, and the complainant also incurred costs to complete some rectification works herself. It is fair for the insurer to pay for further rectification costs and reimburse the complainant’s out of pocket expenses.
Is the complainant entitled to any other amounts?
Yes. The insurer handled the claim poorly and is to pay $4,000 compensation for non-financial loss, $5,400 compensation for indirect loss and reimburse the complainant’s expert costs capped at $10,000. AFCA is unable to make a finding in relation to the premiums.
Why is the outcome fair?
The outcome is fair because the insurer has not met its obligations under the policy. The repairs were defective and there is outstanding damage to the property. It is fair for the insurer to cash settle the cost to rectify these issues, reimburse rectification costs incurred the complainant and pay compensation.
Determination
This determination is substantially in favour of the complainant.
Within 14 days of acceptance of this determination, the insurer is to pay the complainant:
$230,173.79 for rectification works to the main house
$13,775 for rectification works to the granny flat
$30,670.75 for repair costs incurred by the complainant plus interest under section 57 of the Insurance Contracts Act 1984 (the Act) from 23 November 2023 (date of the lodgement of the AFCA complaint) to the date of payment
$5,400 compensation for indirect loss
$4,000 compensation for non-financial loss
$10,000 for professional costs.
Reasons for determination
Is the insurer required to pay for movement damage?
Partially. The complainant has shown that defective works by the insurer’s builder caused or contributed to movement damage to the house. However, there is no persuasive evidence that the insurer is liable for movement damage to the granny flat.
History of the claim and issues in dispute
On 5 February 2019, the complainant lodged a claim for flood damage to her property. The insurer accepted the claim and arranged repairs to the main dwelling and granny flat through its builder, AZ. The repairs included replacement of internal flooring, relevelling of the floors, tiling and half height strip out of internal linings and fittings.
In May 2019, the complainant obtained a report from an engineer, EM, which stated that fast flowing water had caused damage to the paving and under the house. The insurer accepted this and authorised AZ to relevel the house and replace the roadway under the claim.
In July 2021, EM provided a further report which stated that the level of the finished driveway was causing ponding under the main house. The insurer cash settled the cost of rectification works to the driveway. The complainant says AZ was to complete further works under the house, but the insurer changed its position, and she had to do those works herself.
The complainant also says the repairs completed by AZ were poor quality. The insurer does not dispute that rectification works are required and has cash settled the complainant for some outstanding repairs. However, it disagrees regarding the extent of its liability.
The primary issue in dispute relates to the cause of cracking to the house and granny flat. The insurer says this is due to differential movement of the foundation soils and it is not liable for this damage. The complainant says it was caused by the faulty workmanship of AZ.
A secondary issue relates to the rectification of defects in the works by AZ. The complainant has completed some works herself including getting the building certified and concreting under the house. She has also repeatedly asked the insurer to complete rectification works.
In October 2023, the insurer paid the complainant $19,677.90 (inclusive of a 20% uplift) for outstanding repairs. The complainant says she never accepted the settlement sum.
In February 2024, the insurer acknowledged that some items were missed from the SOW upon which its settlement was based and offered to pay an additional $12,214.62, or alternatively, do a dilapidation report. The complainant rejected the settlement offer.
The insurer appointed an engineer, IL, to report on the cause of the structural damage at the property. Based on IL’s findings the insurer says it has no further liability to the complainant.
The complainant arranged for her engineer, EM, to prepare a SOW to repair the movement damage and rectification issues to the house and granny flat.
The complainant wants the insurer to pay the amounts shown in the SOW by her engineer:
$118,027.72 for repairs to the granny flat
$230,173.79 for repairs to the house
The complainant also seeks a reimbursement of costs incurred by her to complete works at the property and get it certified, engineering and other professional fees, and compensation for non-financial loss and loss of rent.
She also claims that the insurer increased its premiums unfairly while the claim was on foot.
Coverage of the policy
The full details of the policy coverage, conditions, limitations, and exclusions are contained within the Product Disclosure Statement (PDS) and Certificate of Insurance (COI). There is no dispute that these documents were provided to the complainant.
The policy schedule shows the complainant holds the ‘Accidental damage at home’ optional cover. There is no dispute that a claimable loss occurred due to a flood event in early 2019.
The policy includes some ‘Additional Features’ which apply if the insurer accepts a claim for loss or damage due to an insured event. Page 27 of the PDS relevantly states:
When we are rebuilding or repairing damaged parts of your home, we will pay the reasonable and necessary costs: …
– for the services of professionals, such as architects or surveyors, to repair or rebuild at the insured address;
– to make the damaged parts of your home comply with the current building regulations and laws.
The policy also includes a ‘Lifetime Guarantee’ on repairs. Page 75 of the PDS states:
Lifetime guarantee on home repairs
When we repair the home, we guarantee the quality of workmanship of that work for the lifetime of your home if we:
– authorise
– arrange; and
– pay the builder or repairer directly for his work.
What we guarantee
We guarantee the standard of the workmanship to be free of defects. If a defect arises in the lifetime of your home as a result of poor quality workmanship then we will rectify the problem.
The complainant says the insurer is liable to complete rectification works to the house and granny flat under the Repair Guarantee and reimburse the costs incurred by her.
Complainant says insurer’s trades caused further damage
The complainant says there is significant outstanding damage to the property caused by the faulty workmanship of the insurer’s trades. The complainant bears the onus of proving this.
A large volume of expert evidence has been exchanged in this matter (see section 3.2).
The complainant’s engineer, EM, provided four reports between May 2019 and January 2022 (under the trading name FM):
on 10 May 2019, EM reported that the flat suffered some minor footing movement in the past, but this was addressed. There are new cracks in the walls of the flat and the main house. EM also reported damage to the paving and under the house caused by fast flowing water and stated that, as the site is Class P, AS 2870 requires the building platform to be raised and graded to prevent ponding of water. EM provided a SOW which included relevelling the house, replacing the roadway and installing road base under the house
on 7 July 2021, EM identified issues relating to the finished level of the driveway including road reinstatement works causing ponding under the main house and reactivating the site clay soils. EM reported that ‘The lack of adequate drainage and or completion of the building platforms has caused excessive movement in the buildings’
on 5 October 2021, EM found that many of the movement cracks previously reported had been repaired by AZ but there were some minor cracks present in the internal plaster. EM stated that the soil is Class M and the movement has two possible origins - the changing of normal site conditions causing a softening of the foundation soils and the stumps sink, or the stumps were not levelled correctly in the first instance
on 31 January 2022, EM recommended repairs to the main house driveway, front exposed aggregate paving, relevelling of the building platform and realignment of the stairs.
The complainant appointed EM again in 2024 to inspect the house and granny flat, confirm what rectification works were required and to prepare a scope of works to repair the damage.
EM provided a report dated 30 July 2024 (under the trading name EC) which states:
AZ’s semi completed works had a considerable portion of incomplete works namely the building platforms under the two buildings, the driveway, and an extensive list of defects to the interior of both buildings
AZ has conducted some minor repairs of the plasterboard. The repairs consist of applying a coat of plaster compound to the crack and sanding and repainting. This is not a correct method of crack repair of plasterboard, particularly so for re-entrant crack at the corners
the deck was damaged by AZ. The boarding used on this deck is no longer made and insufficient quantity is unavailable to repair the damaged boards according to AZ. The only form of repair is to replace the entire deck sheeting with a new compatible floorboard
the wet areas of the house and flat have suffered racking. The method to repair this is to strip out the floor and wall tiles and replace them
AZ allowed water to pond under the building during construction for weeks on end recreating abnormal site conditions again after the claim related flood
AZ has not provided a survey detailing the house and flat have been levelled correctly after the second inundation event caused by incomplete works.
EM prepared a SOW to re-level the house and flat including repairing the current damage inside to the plasterboard walls. The SOW also contains costing to repair all wet areas. EM estimated the total cost of repairs at $348,201.51.
EM provided a further report dated 21 October 2024 which addresses concerns raised by the insurer’s building coordinators and maintains the conclusions in its original report and SOW.
The complainant has provided a geotechnical report by BG dated 1 March 2007 from when the home was constructed, which indicates that the site may be classified as Class P.
The complainant has also made numerous submissions which I have considered. Amongst other things, she says the main house has sunk into the ground at different levels, and if the rectification works had been completed earlier, this extra damage would not have occurred.
Insurer says damage is due to ground movement
The insurer says the movement to the dwelling is not due to the flood or faulty workmanship and is expressly excluded from cover of the policy. It says further that AZ is unable to undertake rectification works, and its cash settlement offer is fair and reasonable.
The insurer appointed an engineer, JH, when the claim was first lodged. JH identified internal cracking and movement damage to the house and reported that moving water had eroded foundation soil and exposed concrete footings. JH concluded that:
the damage to the house was both recent and aged, and recommended another hydraulic survey after a 6-month drying out period to determine the cause of the damage
the damage to the granny flat was aged and caused by long term foundation movement.
The insurer subsequently accepted the findings in the reports by the complainant’s engineer, EM, between May 2019 and January 2022 and reimbursed the cost of these reports.
In 2024, the insurer appointed another engineer, IL, to report on the cause of cracking at the property and other rectification issues. IL’s report dated 14 March 2024 relevantly states:
the subfloor was uneven and promoted sporadic water pooling beneath the dwelling. Staining along the concrete indicated evidence of long-term water pooling
hydrostatic floor levels were measured during our inspection. The dwelling survey showed higher levels along the northern walls of the lounge room, kitchen and office with a total variation of up to 15mm from the centre of the lounge room to the northeastern corner
the dwelling survey of the upper floor showed higher levels to the eastern edge of the dwelling at bedroom 1, with lower levels being recorded at the western edge at bedroom 2. A total variation of 28mm was measured from bedroom 1 to bedroom 2
dagonal cracking observed throughout the dwelling is attributed to differential movement from the ongoing natural seasonal movement of the moderately reactive founding soils. There has been a documented history of internal cracks, uneven flooring, as well as relevelling to the dwelling and granny flat which act as testament to movement at the site
the fact that the soils are considered stable as it has been three years since the event, and it is still exhibiting cracking indicates that it is ongoing and not related to workmanship or the flood event
the poured concrete surface was uneven and was not providing provision for water to drain away from underneath the structure to prevent saturation of the founding soils
the subfloor drainage issues should be remediated as current conditions can encourage water to pond underneath the subfloor.
The insurer also had several internal building co-ordinators (BCs) review the expert reports exchanged in this matter. The insurer’s BCs disagree with the findings in the 2024 reports by the complainant’s engineer, EM, and endorse the findings by IL.
The BCs concluded that:
the damage noted in the IL report is not considered rectification
the cracking is occurring regardless of the recent repairs completed
efforts to reduce water ponding under the house are insufficient
there is no requirement for AZ to carry out building works due to inherent building defects
the settlement sum paid is adequate to cover the cost of repairing defective works.
Ground movement exclusions do not apply
The insurer relies on two policy exclusions regarding ground movement:
a general exclusion on page 60 of the PDS
a specific exclusion under the insured event of ‘Flood’ on page 17 of the PDS.
I am not persuaded that either of these exclusions apply in the circumstances. There is no dispute that the property was damaged by flood and the insurer paid for relevelling works as part of the initial claim repairs. To the extent that additional damage has occurred due to ground movement following those works, this damage was not caused by the flood.
Although the general exclusion for ground movement is broadly worded, I do not consider it excludes any entitlements the complainant has under the Repair Guarantee. It also is not possible to exclude any liability the insurer may have at common law.
Insurer’s expert evidence is not persuasive
The insurer has provided invoices from QC for works to relevel the main house dated 24 May 2020 ($6,990.50) and 22 September 2020 ($14,080). I accept based on the exchanged information that AZ completed relevelling works in 2020 as part of the initial claim repairs.
The exchanged material shows that the house is no longer level and has movement damage. The evidence shows this damage was present as early as 7 July 2021 and the complainant says it has worsened over time.
The key question for determination is whether the complainant has shown that the recent movement damage was caused by the insurer’s trades. The insurer acknowledges that some of AZ’s workmanship required rectification. EM reported that the height of the driveway was causing water to pond under the house, and the lack of adequate drainage caused excessive movement in the buildings. IL also identified evidence of water ponding under the house.
I accept that the defects with the driveway constructed by AZ caused water to pond under the house. However, there is no persuasive evidence that this impacted the granny flat.
The experts disagree on the cause of the movement damage to the buildings.
The insurer’s BC reported in August 2021 that the movement was consistent with expected seasonal movement. I do not accept this. The BG report indicates predicted surface movement due to seasonal changes of 20-40mm and recommended bored piers under both buildings. I accept EM’s comments that this would reduce seasonal movement.
EM was initially engaged by the complainant, but the insurer accepted the findings in the first four EM reports and reimbursed the complainant for the cost of those reports. The insurer is now rejecting the findings by EM in favour of its own engineer, IL.
I do not consider the report by IL persuasive because:
IL states the 2019 flood drying out period would be 6 - 12 months. However, there is no dispute that water was ponding under the house after this time due to the height of the driveway, which would have prevented drying out
IL found that, because the cracks to the house have re-appeared, they must be due to normal differential movement rather than defective workmanship. However, IL failed to address the impact of water ponding under the house following the initial repairs
IL assumed the soil at the site was Class M and based its findings on this despite not have sighted the BG report, which states that the site is Class P.
Both engineers failed to accurately determine the soil type. There is, however, no dispute that the soil was reactive and changes in moisture conditions may cause building movement.
The insurer’s BCs were critical of the EM reports. However, they are not independent experts or qualified engineers, and I do not consider their reports advance the insurer’s position.
Overall, I consider that the movement to the house was caused by a combination of:
differential movement from ongoing movement of the reactive founding soil
ponding of water under the house due to the faulty works on the driveway
uneven concrete under the house which is not allowing water to drain away
Both experts agree that the granny flat had some movement damage prior to the flood. There is no persuasive evidence regarding the cause of recent movement to the granny flat.
Fair for insurer to pay for movement damage to the house
The defect with the driveway and water ponding under the house was reported in July 2021. The insurer settled the cost of rectifying the driveway in late 2022 but failed to complete works under the house as agreed, leaving those works to be completed by the complainant in 2023. I consider there was a significant and unreasonable delay by the insurer rectifying the issue with the driveway which meant that water was ponding under the house for over two years.
All experts agree that changes in moisture content can cause building movement, and any seasonal changes therefore would have been exacerbated. This is confirmed by section 1.3.3 of ‘AS 2870-2011 Performance of Building Footings’ the which states ‘Buildings constructed on sites subject to abnormal moisture conditions have a higher probability of damage.’
IL says the concrete under the house is uneven and this may be contributing to the damage. and require rectification. I acknowledge the complainant completed the concreting works. However, I am satisfied that she undertook these works in circumstances where the insurer had previously agreed to complete works under the house and later declined to do so. This is supported by emails between the complainant and the insurer in September 2022.
The complainant says the concrete works under the house were completed based on advice from EM and approved by the insurer. She has provided documents in support of this. The insurer’s claim notes confirm that $13,790.70 was approved for concreting in November 2022. The insurer also made an offer in December 2022 to pay the complainant $29,864.45 based on quotes to concrete under the house ($28,666) and obtain a building permit ($1,198.45). The insurer later made an offer to pay the cost of relevelling the ground under the house.
The exchanged material shows that AZ previously installed a cement slurry under the house (this is confirmed by the insurer’s assessor, G, and the complainant’s photos taken in 2021). I accept the complainant’s submission that this made it necessary to concrete under the house as part of the rectification works in 2023.
In any event, there was movement damage to the house before the concreting works. Whilst the uneven surface may be contributing to the damage, it is not the proximate cause. I also consider it would be unfair to hold the complainant responsible in circumstances where she was compelled to undertake rectification works herself due to AZ’s inaction.
For the above reasons, I consider it fair for the insurer to pay the cost of relevelling the house. There is no persuasive evidence that faulty workmanship by the insurer’s trades caused movement damage to the granny flat. I consider a fair outcome in the circumstances is for the insurer to pay the amount shown in the EM SOW to repair the house only.
Is the insurer required to pay further rectification costs?
Yes. There were defects with the repairs by the insurer’s builder. The cash settlement paid by the insurer is inadequate to cover the cost of rectifying all defects, and the complainant also incurred costs to complete some rectification works herself. It is fair for the insurer to pay the outstanding rectification costs and reimburse the complainant’s out of pocket expenses.
Evidence shows rectification repairs are required
The insurer does not dispute that rectification works are required and has cash settled the complainant $19,677.90 (inclusive of a 20% uplift) for outstanding repairs.
The insurer’s settlement covered various rectification works as set out in a Defects SOW prepared by AZ. The Defects SOW was first prepared in 2022 and estimated the cost of rectification works at $16,073.75. A revised Defects SOW was prepared in February 2023 which estimated the cost at $16,398.25. The insurer applied a 20% uplift, bringing the total settlement sum to $19,677.90 (although the insurer says it paid $19,835.30).
The insurer arranged for an assessor, G, to inspect the property on 17 January 2023. G provided a report which states that he will reattend with AZ to formulate a rectification SOW. G provided a further report on 24 January 2023 which lists the outstanding rectification works to the main house and granny flat. These items differ from the list in the Defects SOW by AZ in 2022. A list of ‘Adjustments to the Scope of Works’ is attached which includes additional rectification works to the mod wood deck and the under-house drainage and supply piping.
AZ submitted an updated SOW dated 9 February 2023 in the amount of $16,398.25 (which the insurer’s cash settlement is based on).
G provided a further report on 21 March 2023 which addresses additional concerns raised by the complainant. G initially reported that no works were undertaken to the sewer lines in the granny flat. However, the complainant provided evidence that AZ did perform these works and G then stated ‘An allowance to address the sewer pipe issue is to be added to the SOW.’
The complainant says she approved the rectification works identified by G and wanted AZ to complete them, but this did not occur. Instead, the insurer cash settled the rectification costs based on the Defects SOW by AZ dated 9 February 2023.
I am not satisfied that the insurer’s cash settlement was sufficient to cover all outstanding rectification works. In particular, it does not include sufficient allowance for the mod wood deck and no allowance was made for the granny flat sewer lines.
I acknowledge there were other disputed items raised by the complainant. In May 2023, the insurer provided a response explaining why these items are not rectification works. The complainant has not provided any persuasive evidence showing they should be covered.
The insurer subsequently offered to obtain a comprehensive dilapidation report, and a further inspection took place on 28 February 2024. However, no updated SOW was obtained.
In February 2024, the insurer offered to pay a further $12,214.62 for additional rectification costs not previously included in the cash settlement. This included works to relevel under the house, reset post collars for uniform height and repairs to the front landing.
Fair for the insurer to cash settle the rectification costs
The insurer is liable to rectify the defective repairs under the Repair Guarantee in the policy, which is a contractual obligation. The contract of insurance is between the insurer and the complainant, and the insurer is therefore liable to compensate the complainant for the defects (not the builder or QBCC). This determination does not consider any rights the complainant may have to pursue a claim against the builder or QBCC.
AZ already attempted to rectify some of the defects without success, and the complainant has lost confidence in its workmanship. In circumstances where the relationship has broken down, I consider it fair for the insurer to cash settle the cost of the rectification works. This will facilitate a prompt resolution of what has been a very protracted dispute.
The insurer says the complainant’s SOW is excessive because it covers relevelling both buildings and other items that are not rectification issues. However, it has not provided an updated SOW for all accepted rectification issues or to refute the amounts allowed by EM.
The two SOWs prepared by EM are very comprehensive and include the cost of relevelling the house and the granny flat, plus the items which the insurer previously determined to be maintenance issues following the assessments by G. Allowances have been made for the cost of replacing the decking with a new product and rectifying the granny flat sewer lines.
I consider a fair outcome in the circumstances is for the insurer to pay:
$230,173.79 for rectification works to the house based on the EM SOW. Given the insurer has already paid $19,677.90 and there is some overlap, no contingency is warranted.
$13,775 for sewer works to the granny flat. This is based on the EM SOW for external drainage and includes a 20% contingency.
Insurer is to reimburse rectification costs incurred by complainant
The complainant says the insurer failed to obtain certification for the initial repairs and the building permit expired. It is unclear why the repairs were not certified. However, I accept that there were outstanding rectification items, and she completed some works herself.
The complainant has provided the following invoices:
invoice from JD dated 14 December 2022 for building permit ($1,198.45)
invoice from NS for concreting under the house ($23,166.00)
invoice from EM dated 19 June 2023 for consulting services ($6,306.30).
Prior to completing these works, the complainant provided the insurer with quotations.
I consider it fair for the insurer to reimburse these costs in full on the basis that they were reasonably incurred in circumstances where the insurer should have completed the works in accordance with the terms of the policy. The insurer is required to pay interest on these costs under section 57 of the Act from 23 November 2023 (date of AFCA complainant) to the date of payment.
For the avoidance of doubt, the insurer is not liable for the cost of rectifying the concreting.
To the extent the complainant incurred costs for professional services in relation to the rectification dispute, these fall outside the terms of the policy. I have considered whether the insurer is required to contribute to these costs in section 2.3 below.
I acknowledge the complainant provided the insurer with quotes from an electrician ($964.59) and plumber ($1,479.50) in November 2022. I am satisfied that the amount I have awarded to repair the house is sufficient to cover any liability the insurer has for those items.
Is the complainant entitled to any other amounts?
Yes. The insurer is to pay $4,000 compensation for non-financial loss, $5,400 compensation for indirect loss and reimburse the complainant’s expert costs capped at $10,000.
Complainant is entitled to compensation for non-financial loss
Under AFCA’s Rules, AFCA may award compensation for non-financial loss where there has been an unusual amount of physical inconvenience, time taken to resolve a situation, or interference with the complainant’s expectation of enjoyment or peace of mind.
AFCA takes a conservative approach to compensation for non-financial loss. In assessing whether to award compensation, AFCA expects complainants to be moderately robust and bear the normal degree of inconvenience experienced when a problem occurs. AFCA considers the severity and impact of the financial firm’s conduct on the particular complainant.
There is no dispute that the claim commenced in 2019 and has been on foot for over five years. The insurer paid the complainant $5,400 compensation for non-financial loss on 27 June 2023. I have considered whether the complainant is entitled to additional compensation due to the insurer’s conduct since then.
The complainant has identified vulnerabilities including domestic violence. She says the insurer knew that she needed to have the homes repaired and certified quickly to enable her to sell and move away to safety. She moved into a safe house in late 2023 and her mother later purchased her a new home. The property has remained vacant for over 18 months.
The complainant says that:
the insurer has unreasonably withdrawn their promised repairs and reimbursements
the insurer failed to consider the complainant and her very young children, failed to settle the claim in a timely manner, and ignored their known vulnerabilities
she has been unable to sell the property due to the ongoing dispute
I am satisfied the claim was not handled as well as it could have been and there were delays and errors made by the insurer since June 2023.
Significantly, the insurer failed to pay for all defects caused by its builder, failed to reimburse costs incurred by the complainant completing works under the house, and failed to obtain an updated SOW following the dilapidation report. I am satisfied that the insurer’s actions caused the complainant an unusual degree of stress and inconvenience.
It is fair for the insurer to pay the complainant a further $4,000 for non-financial loss.
Complainant is entitled to compensation for indirect loss
Under paragraph D.3.2 of the AFCA Rules, we may require an insurer to compensate a complaint for indirect financial loss (also known as consequential loss). For complaints made prior to 1 January 2024, this is capped at $5,400.
Many insurance policies exclude cover for indirect loss. If this is the case, we will not award this type of compensation for loss caused by the event giving rise to the claim. However, if the complainant has suffered an additional loss because the insurer mishandled the claim, we may require the insurer to compensate the complainant for the additional loss.
The policy does not cover loss of rent. The complainant sought cover for loss of rent to the granny flat when the claim was first lodged in 2019 and the insurer declined this by letter to the complainant by letter dated 5 March 2019. The complainant does not dispute the insurer’s decision following the original claim. However, she says the insurer should cover loss of rent arising from the defective works and significant delays caused by the insurer.
The claim has taken significantly longer than expected due to the defective repairs, and the evidence shows that there are outstanding defects with the granny flat. This includes a defect with the sewer lines which did not form part of the insurer’s cash settlement despite G reporting in March 2023 that it should be included in the SOW.
I accept that this prevented the complainant from renting out the granny flat for several years. The complainant says the granny flat generates $350 a week in rental income and the insurer does not refute this. I am therefore satisfied that the complainant incurred a loss due to the insurer’s conduct that exceeds the $5,400 jurisdictional limit.
I acknowledge that the complainant has an obligation to mitigate her loss, but she already incurred significant out-of-pocket expenses rectifying other defects with the insurer’s repairs and I accept she did not have the capacity to do so. In the circumstances, I consider it fair for the insurer to pay the complainant $5,400 for indirect financial loss.
Insurer to reimburse complainant for expert costs capped at $10,000
Under its Rules, AFCA may require an insurer to contribute to a complainant’s professional costs incurred (usually capped at $5,000) in bringing their complaint. This may include legal costs or expert reports. AFCA will consider the complexity of the complaint, whether the costs are reasonable and whether they helped resolve the complaint.
The complainant has provided the following invoices for engineering reports by EM:
EM Invoice dated 29 July 2024 in the amount of $25,044.80
EM Invoice dated 21 October 2024 in the amount of $3,841.20
She has also provided an invoice dated 16 September 2022 for claims handling services in the amount of $3,300. These costs were incurred prior to the AFCA complaint.
The reports from the complainant’s engineer were required because they assisted to establish the cause and extent of the movement damage to the house and provide a SOW for repairs in circumstances where the insurer had not proved an updated SOW.
It is fair for the insurer to reimburse the reasonable costs for these reports which have been paid by the complainant. Unless special circumstances under AFCA Rule D.5 apply, the insurer is not usually required to contribute more than $5,000 to such costs.
In this case, I consider special circumstances do apply. The dispute was extremely complex and involved two separate dwellings. The insurer relied on voluminous expert reports and there were questions of causation and defective workmanship. The complainant was ultimately successful in establishing the insurer was required to pay further rectification costs.
These circumstances satisfy the requirements for special circumstances under Rule D.5.2. I consider it fair for the insurer to reimburse the complainant’s costs up to a limit of $10,000.
AFCA is unable to make a finding in relation to premiums
The complainant has raised concerns regarding the premiums she has paid since the claim was lodged. In short, she says that the premiums have increased each year, and she has had no choice but to pay it because she cannot sell the property or change insurers.
She lodged an internal complaint with the insurer about this in July 2023 and the insurer declined to refund any premiums. After the present dispute was lodged with AFCA, she emailed the insurer outlining her concerns and asked for a review of paid premiums.
The insurer’s Notice of Response dated 6 February 2024 notes that the complainant sought a reduction in premiums due to the claim but states ‘As this is not relevant to the matter to hand, the Insurer will provide no further comment on this interaction.’ No further submissions or information have been provided by the insurer in relation to the premium increases.
The complainant has provided a list of her premiums and says they have increased from $3,197.76 in 2019 to over $10,000 in 2025. No supporting evidence has been provided by either party in relation to the amount or reasonableness of the premiums charged.
AFCA has limited jurisdiction in relation to the consideration of premium-related complaints. In this instance, I do not have sufficient information to make a finding in relation to the increase to the premiums paid. If the complainant wishes to pursue this issue further, she can lodge a separate complainant with AFCA for consideration.
Why is the outcome fair?
The outcome is fair because the insurer has not met its obligations under the policy. The repairs were defective and there is outstanding damage to the property. It is fair for the insurer to cash settle the cost to rectify these issues, reimburse rectification costs incurred the complainant and pay compensation.
Supporting information
The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided.
While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.
Summary of expert evidence
|
|
Insurer’s expert evidence and key documents
|
|
Action JH Engineering Report dated 5 March 2019
FE Attendance Report by restorer dated 27 March 2019
Assessment reports dated 3 July 2019 and 6 August 2019
BC Technical Review dated 6 August 2019
AZ Scope of Works and Provisional Sums Schedule dated 19 March 2020
Invoices from QC for works to relevel main house dated 24 May 2020 ($6,990.50) and 22 September 2020 ($14,080)
Survey Report by VS dated 18 November 2021
BC Reports by BR dated 3 August 2021, 2 September 2021 and 15 February 2022
Defects SOW by AZ dated August 2022
Rectification Report by internal assessor, G, dated 17 January 2023
2nd Rectification Report by internal assessor, G, dated 24 January 2023
Defects SOW by AZ dated 9 February 2023
Assessment Report by internal assessor, G, dated 21 March 2023
Reinspection Report by G dated 28 February 2024
IL Engineering Report dated 14 March 2024
BC Report by CH dated 19 March 2024
BC Responses by CV dated 11, 15 and 29 October 2024
|
|
Complainant’s expert evidence and key documents
|
|
Geotechnical report by BG dated 1 March 2007
FM Quantified Scope of Works dated 1 May 2019
FM Preliminary Report No. 1 dated 10 May 2019
FM Report No. 2 Investigation of Under House dated 7 July 2021
FM Report No. 3 Inspection of Incomplete Works dated 5 October 2021
FM Report No. 4 New Access Road and Building Platform Design 31 January 2022
EM Response Email dated 4 May 2022
Building Platform Repair SOW by EM dated 5 October 2022
Extract of AS 2870-2011 Performance of Building Footings
Development Approval - Building Permit by JD Consulting (undated)
Extract of AS/NZS 3500.2:2021 Plumbing and Drainage
FM Scope Extracts for Granny Flat and Main House dated 26 July 2024
EM Scope of Works to Repair House dated 29 July 2024
EM Scope of Works to Repair Flat dated 29 July 2024
EM Engineering Report dated 30 July 2024
EM Response Report dated 21 October 2024