Determination 12-00-1039798
Bank paid two progress claims to builder who did not pay suppliers
Summary
Borrowers who lost money when their builder failed to pay suppliers sought $210,415.82 plus legal costs from the bank over two progress payments. AFCA found the bank acted consistently with the loan terms and ordered no compensation.
The complainants' countersigned invoices instructed the progress payments, and the bank was not responsible for the builder's dishonest conduct or for auditing his payments to suppliers.
Issues
- Payment error primary · not upheld“The bank paid each progress claim after the complainants lodged a countersigned invoice, which was clear instruction to pay.”
- Inadequate claim investigation secondary · not upheld“The bank engaged the quantity surveyor for its own purpose, not to audit the builder's work or payments to suppliers.”
Subjects and remedies
no remedy
Related
All Commonwealth Bank determinations · Find similar determinations
Text of the determination
Determination
|
Case number
|
12-00-1039798
|
Financial firm
|
Commonwealth Bank of Australia
Case number: 12-00-1039798 4 October 2024
Determination overview
Complaint
On 15 October 2021 the complainants entered into a ‘cost-plus’ building contract (build contract) with the builder (builder A) and on the same day received an offer from the financial firm (bank) for two loans, one of which was a $1.32 million construction loan (construction loan) to fund building work to be carried out under the build contract. The building project commenced and in due course the bank made two progress payments to builder A – one on 8 February 2022 and the other on 20 April 2022. However, it turned out builder A had not paid the relevant suppliers for much of the materials the subject of those two progress payments.
The complainants say that although they countersigned the invoices for the two progress payments submitted by builder A, they thought drawdowns against their construction loan would not be made by the bank on their behalf unless the corresponding labour, materials and payments to suppliers and subcontractors had first been verified by the bank’s quantity surveyors.
The complainants want the bank to pay them $210,415.82, which is the amount awarded to them on 10 January 2023 in successful court proceedings they took against builder A. Builder A has yet to comply with the court order and the complainants have been advised, following further legal processes, that they are unlikely to recover much money from him. The complainants also want compensation for the legal expenses they have incurred in pursuing builder A.
An AFCA Senior Dispute Resolution Specialist provided a recommendation to the parties on 31 July 2024. The recommendation was in favour of the bank. A copy of the recommendation is attached to this determination. The complainants rejected the recommendation but did not provide reasons for their rejection or any further information.
Issues and key findings
Were the findings in the recommendation correct?
Based on all the relevant information, the findings in the recommendation were correct and are adopted in this determination.
Have the complainants provided further submissions that would change the outcome?
The complainants have not provided any new submissions that would change the findings or the outcome in the recommendation.
Why is the outcome fair?
The complainants have been the unfortunate victims of builder A’s dishonest conduct. However, when the bank made the progress payments to builder A, it acted consistently with the construction loan terms and conditions and its own credit policy. It would not be fair to require the bank to compensate the complainants in circumstances where their loss has arisen from the conduct of builder A rather than the bank’s management of the construction loan.
Determination
The determination is in favour of the financial firm. I agree with the Senior Dispute Resolution Specialist’s reasons for the recommendation and the recommended outcome.
The bank is not required to provide compensation to the complainants.
Reasons for determination
Were the findings in the recommendation correct?
Based on the available information, the findings in the recommendation were correct and are adopted in this determination.
The findings in the recommendation were correct
I am satisfied that the Senior Dispute Resolution Specialist’s recommendation contains an accurate summary of the complaint and the issues to be determined.
The recommendation concluded the complainants’ financial loss arose from builder A’s conduct, rather than the bank’s conduct. The recommendation found that:
the bank acted consistently with the construction loan and its own credit policy
it was not the bank’s responsibility to check that builder A had paid the relevant suppliers and subcontractors before he issued the two progress claims
the complainants were responsible for satisfying themselves that the progress claims made by builder A justified payment under the build contract.
I agree with the Senior Dispute Resolution Specialist’s reasons and findings in the recommendation and adopt them as part of this determination.
The complainants rejected the recommendation
The complainants rejected the recommendation and asked for the complaint to progress to a determination. The complainants did not provide any reasons or additional information that would change the outcome in the recommendation.
Have the complainants provided further submissions that would change the outcome?
The complainants have not provided any new submissions that would change the findings or the outcome in the recommendation.
The complainants authorised the progress payments
I have independently reviewed the available information submitted by the parties and I agree with the assessment in the recommendation.
Under the build contract the complainants, not the bank, were liable to make the progress payments to builder A. The bank was not a party to the build contract nor does that contract make the bank responsible for supervision of the building work.
The bank paid each of the two progress claims (both were for $134,928.30) after the complainants lodged an invoice issued by builder A, which they had countersigned adjacent to the words ‘Client Authorisation’. This active authorisation was consistent with the requirements of the terms and conditions of the construction loan. The amount claimed on each of the two invoices reflected the first two stage progress payments specified in the special condition at Appendix II of the build contract.
I am satisfied the bank was entitled to take the countersigned invoices as clear instruction from the complainants that they were content for the bank to make the two progress payments on their behalf by drawing down on the construction loan. I do not consider that any process change the bank may subsequently have instituted after the complainants engaged a new builder affects the instructions the complainants gave in connection with builder A.
Bank engaged the quantity surveyor for its own purpose
The bank engaged the services of an independent quantity surveyor to assist with its initial decision about the viability and costings of the building work and whether its security would be proportionate to the credit risk. This was consistent with the bank’s approach to cost-plus building contracts in its credit policy. The quantity surveyor’s 1 October 2021 report advised the bank that the project costings and timings were reasonable. The construction loan was granted to the complainants a fortnight later and the first progress payment was paid by the bank to builder A on 8 February 2022.
The bank subsequently obtained two progress assessments from a different quantity surveyor. The first of these, dated 14 February 2022 and based on an inspection carried out the same day, recommended the bank pay the first invoice in full, though by this time that payment had already been made. The second of these, dated 19 April 2022 and based on an inspection carried out the same day, was received by the bank after the complainants lodged builder A’s second progress payment invoice on 12 April 2022. This assessment also recommended the bank pay the invoice in full.
Both assessments mentioned the builder had not provided a statutory declaration to affirm payments made to employees, subcontractors or suppliers and both assessments confirmed the quantity surveyor had not seen a signed copy of the build contract. It is speculative to try to predict what difference this might have made (if any) to the quantity surveyor’s reports or the bank’s response. In any event, neither the terms and conditions of the construction loan nor the schedule to the construction loan required the bank to satisfy itself that all materials had been supplied and suppliers paid before making a progress payment.
Cost-plus building contract does not change who is responsible
The complainants have stressed the stage payments specified in the build contract do not make sense in the context of a cost-plus contract and were inserted at the bank’s request. Irrespective of the logic used to specify a set of target progress payments, the first two being 10% of the ‘agreed target budget for the construction works’ ($1,349,283), this does not make the bank liable for builder A’s failure to make appropriate payments to suppliers or subcontractors.
Bank was not responsible for the complainants’ financial loss
Based on the available information, the complainants have not established the bank was responsible for the complainants’ financial loss, including the money they have spent pursuing builder A in court. It follows that the bank is not required to pay compensation.
Why is the outcome fair?
The complainants have been the unfortunate victims of builder A’s dishonest conduct. However, when the bank made the progress payments to builder A, it acted consistently with the construction loan terms and conditions and its own credit policy. It would not be fair to require the bank to compensate the complainants in circumstances where their loss has arisen from the conduct of builder A rather than the bank’s management of the construction loan.
The outcome is fair in all the circumstances
The outcome is fair in all the circumstances because the bank met its obligations under the construction loan and did not make any error when it paid the two progress claims to builder A. The bank was not responsible for, nor was it on notice, that builder A had failed to make various payments to suppliers. It is noteworthy that the complainants have successfully obtained judgment against the person who was responsible for their financial loss – namely, builder A. As the bank’s actions did not cause the complainants financial loss, it would not be fair to require the bank to pay compensation to the complainants.
Supporting information
The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided.
While the parties have raised a number of issues in their submissions, we have restricted our determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.
Recommendation
|
Case number
|
12-00-1039798
|
Financial firm
|
Commonwealth Bank of Australia
Case number: 12-00-1039798 31 July 2024
Recommendation overview
Complaint
In October 2021, the financial firm (bank) approved a $2.375 million home loan (loan) for the complainants for the construction and renovation of an existing property (property). The property was the sole security for the loan. In February 2022 and April 2022, the bank paid progress payments (each for $134,928) to the complainants’ original builder (builder A) from the loan.
The complainants say:
the building contract with builder A was a ‘cost plus’ contract
builder A submitted fraudulent progress claim requests. For the works relating to these requests, he had not paid multiple suppliers for materials. As a result, the suppliers had not provided all the materials required for the build
the progress payments were approved by the bank’s quantity surveyor, and the bank paid these amounts to builder A from the loan
in September 2022, they terminated their building contract with builder A and requested information from him to reconcile their project expenses
the bank engaged the quantity surveyor who was to inspect the building site at every drawdown, to ensure the appropriate work was completed, and to justify the progress payments. However, this process was not followed
they obtained a Court judgment against builder A in January 2023 for the amount of $210,415. However, builder’s A’s registration has since been revoked, and given his financial situation, the recovery of their losses from him is unlikely
they have since entered into a cost plus contract with a new builder (builder B), and construction of the project has resumed. However, due to their financial losses, they are unlikely to have sufficient funds to finalise the build
under the new building contract, the bank’s process for verifying work completed has been more thorough. Had these procedures been in place and enforced by the bank while in contract with builder A, the fraudulent progress claims may not have been approved
to resolve their complaint, they would like the bank to:
> advise why its drawdown procedures differed for each of the builders and explain why procedures were not in place to protect them
> advise why the payments to builder A were not quantified by the quantity surveyor
> provide them with compensation of $210,415 for their losses plus interest
> compensate them for their legal costs accrued from proceedings against builder A.
A timeline of events outlining key events is contained in section 3.1 of this recommendation.
Issues and key findings
Did the bank make any error when it paid the progress claims to builder A?
No, the bank did not make any error when it paid the progress claims to builder A. While the bank engaged the services of a quantity surveyor, it did so for its own benefit, and it was not required to conduct an audit of the work completed by builder A. The complainants authorised the bank to pay the progress claims to builder A when they provided it with the signed invoices.
The complainants were responsible for ensuring the work completed by builder A was of a satisfactory standard before authorising the bank to pay progress claims. The bank was not responsible for builder A’s decision to not pay the suppliers. The complainants are therefore not entitled to compensation from the bank for their financial losses or legal costs.
Why is the outcome fair?
The events the complainants have described are unfortunate and I understand they have suffered financial difficulties due to reasons beyond their control. But when it paid the progress claims to builder A, the bank met its obligations, complied with its credit policies and the loan terms and conditions, and acted in line with good industry practice. So, it would not be fair to require it to compensate the complainants.
Recommendation
This recommendation is in favour of the bank. The bank is not required to provide compensation to the complainants.
Reasons for recommendation
Did the bank make any error when it paid the progress claims to builder A?
No, the bank did not make any error when it paid the progress claims to builder A. While the bank engaged the services of a quantity surveyor, it did so for its own benefit, and it was not required to conduct an audit of the work completed by builder A. The complainants authorised the bank to pay the progress claims to builder A when they provided it with the signed invoices.
The complainants were responsible for ensuring the work completed by builder A was of a satisfactory standard before authorising the bank to pay progress claims. The bank was not responsible for builder A’s decision to not pay the suppliers. The complainants are therefore not entitled to compensation from the bank for their financial losses or legal costs
The complainants signed a cost plus building contract with builder A
On 15 October 2021, the complainants signed a building contract with builder A to complete renovations and extensions to the property. The building contract was a cost plus contract which allows a builder to obtain materials and services throughout the building process, and to pass these on to the customer along with an agreed margin. This is in contrast to fixed price building contracts which contain a fixed price with agreed amounts payable at various stages of the build.
While the complainants’ building contract with builder A was on a cost plus basis, the contract did contain an appendix containing progress stage claim amounts for the build. The complainants say this appendix was prepared and attached to the contract upon the bank’s request. Both parties have provided AFCA with a copy of the complainants’ building contract with builder A, and I have no reason to doubt it contains an accurate record of the agreement between the complainants and builder A.
The complainants signed the loan contract
The loan contract is dated 15 October 2021 and is for a loan amount of $2.375 million. It was signed by the complainants, and neither party has disputed the signing. As the complainants signed the contract, they are bound by the terms and conditions contained within it.
The bank appointed a quantity surveyor
The bank engaged the services of an independent quantity surveyor to inspect the property and prepare it with a costing report prior to each progress claim being paid to builder A (and later to builder B). The role of the quantity surveyor was to monitor and estimate the costs associated with the construction. The costing reports were a requirement under the bank’s credit policy due to the cost of the build and the type of building contract involved. This requirement is in line with standard industry practice for this type of property.
The complainants authorised the progress payments to builder A
Builder A provided invoices to the complainants for two progress claims. The complainants signed the invoices and provided them to the bank, who then paid builder A from the loan. Details of these progress claims are below:
invoice dated 26 November 2021 for $134,928.30 for the ‘undercroft slab instal’ building stage. This was paid by the bank on 8 February 2022
invoice dated 21 March 2022 for $134,928.30 for the ‘undercroft plate height’ building stage. This was paid by the bank on 20 April 2022.
For each of the progress claims, the quantity surveyor attended the property and prepared an updated costing report for the bank. However, the complainants say by signing the invoices and providing these to the bank, they understood:
this only recognised that they had seen the invoices
the invoices would be sent to the bank who would then engage the next stage of the process, being the quantity surveying
the bank would not pay the progress claims until the work completed by builder A had been quantified by the quantity surveyor
this did not represent their authorisation for the bank to pay the builder for the invoices.
The complainants say the work conducted by builder A was not appropriately reflected in the quantity surveyor’s reports. They also say the bank’s progress payment process changed after they signed the new building contract with builder B. For builder B’s progress claims, they advised in addition to signing the invoice, the bank required them to write on it: ‘we authorise payment of this invoice to the builder.’ A copy of the invoice from builder B has been provided – it is dated 13 December 2022 and does contain this additional instruction.
In its response, the bank says the complainants’ provision of the signed invoices represented their authorisation to pay builder A. The bank provided a copy of its credit policy which required that any requests for progress payments be signed by a customer. The bank also provided a copy of the loan terms and conditions which relevantly state:
‘We fund the construction loan by paying the loan drawings in accordance with the amounts shown on your progress payment scheduled in the building contracts. Before we make a payment we require a copy of the invoice from your builder signed by you […]’
The bank confirmed that from 18 April 2022, its process for accepting progress claims did change. From this date, in addition to a customer signing the builder’s invoice, it required them to write ‘I/We authorise payment of this invoice.’ As the progress payments to builder A were received by the complainants before this change came into effect, the new wording was not required on those invoices.
In any event, I have reviewed the signed invoices provided by the complainants to the bank for builder A. Each invoice contains a ‘client authorisation’ signature section along with the wording: ‘please pay to’ followed by builder A’s account details. The complainants each signed the invoices before providing them to the bank.
I acknowledge the bank changed its progress payment procedures to include additional wording from 18 April 2022. However, given the provisions in the loan terms and conditions, and the information contained in the signed invoices for builder A, it is my view the complainants did instruct the bank to pay builder A when they provided it with the two invoices.
The complainants also say the bank and the quantity surveyor did not take adequate steps to quantify the work done before authorising the payments to builder A. This claim will be addressed in the next section.
The bank engaged the quantity surveyor for its own purpose
The complainants say builder A made fraudulent progress claims against their loan by submitting invoices that did not correctly represent the progress of the build. After terminating their contract with builder A, the complainants say they discovered that deposits builder A had advised were paid to suppliers for certain materials, had not been paid to those suppliers. They say due to this, some materials were not provided by the suppliers.
In their submissions, the complainants referred to the quantity surveyor’s reports which the bank relied upon to support its decision to pay the progress claims. They say there were multiple flaws in the bank’s processes when it assessed the progress claim requests from builder A. These are outlined below:
a progress payment schedule was appended to the building contract upon the bank’s request. However, given the cost plus nature of the building contract, this schedule was irrelevant and did not represent the work completed for either of the progress claims submitted by builder A
the bank did not provide a copy of the building contract to the quantity surveyor or advise them of the cost plus nature of the contract
the bank and the quantity surveyor did not request builder A’s payment summary outlining the expenses associated with the progress claims. However, this information was requested by the bank for builder B’s progress claims. Had the bank requested this information from builder A, it would have discovered builder A had overstated his payments to suppliers.
For the reasons above, the complainants say the bank is responsible for their financial losses associated with the progress payments made to builder A.
The complainants say they understood the bank required a quantity surveyor to be appointed as part of its loan approval to protect both themselves and the bank. They understood the quantity surveyor’s responsibility was to ensure builder A did not overclaim for each of the progress claims. They say this was important given the cost plus nature of the building contract, and given the quantity surveyor had a greater understanding of the costings involved than both the bank and themselves.
While I acknowledge the bank appointed the quantity surveyor, it did so for its own purposes. The complainants’ understanding that the quantity surveyor’s role was to assist or protect them is misconceived. This is because:
the bank is not a builder, and it appointed the quantity surveyor to:
> satisfy itself on the progress of the construction project
> prevent cost overruns overall in order to protect its security position.
while the quantity surveyor reports were exchanged with the complainant as part of the AFCA process, they were prepared by the quantity surveyor for the bank’s use only, and not for the benefit of the complainants. It was ultimately a credit decision by the bank as to what information it exchanged with the quantity surveyor and what action it took upon receiving the quantity surveyor’s reports
neither the bank or the quantity surveyor, were responsible for conducting an audit of work conducted by builder A, builder A’s payments to suppliers or the delivery of materials to the building site. The bank’s responsibility was only to investigate costings for its own purpose to ensure it was covered against any cost overruns
the complainants entered into the building contract with builder A. It was therefore their responsibility to ensure the building progress and standard of completion was satisfactory before authorising the release of funds from the loan. In respect of this, the loan terms and conditions state the following:
‘When we inspect or value a property […] [we] make no representation to you about the condition of the land, the construction of any building […].’
The complainants confirmed their acceptance of builder A’s work upon signing the invoices and providing them to the bank for payment
the bank’s role was not to provide financial or building advice to the complainants. The loan terms and conditions contained a recommendation by the bank that the complainants obtain their own independent advice. Its construction loan brochure (which it advised is provided to all construction loan customers) also states:
‘We’ll conduct inspections and property valuations at various stages of your construction to check that everything’s on track […]. Keep in mind: these inspections and valuations don’t endorse the quality of work performed by your builder. If you would like this to occur you should contact an independent building inspector.’
It was open to the complainants to obtain advice before proceeding with the loan and throughout the course of the building construction. No information has been provided to show the complainants did obtain their own independent advice.
I have reviewed the costing reports prepared by the quantity surveyor, and I am satisfied they contain appropriate information on the estimated costings for the bank to reasonably rely upon. In any event, the costing reports were obtained for the bank’s purpose and not for the complainants’ benefit. The bank was not responsible for any decision by the complainants to purchase the property or enter into an agreement with builder A, and the complainants were responsible for ensuring the standard of the build was of a satisfactory standard. For these reasons, it is my view the bank was not responsible for the complainants’ financial loss.
The bank was entitled to decline a progress payment claim
In their submissions, the complainants said the bank has been inconsistent generally in its decision to approve or reject progress claims. They described the following examples:
the bank declined a progress claim for the deposit on an elevator which was being manufactured overseas. The request was declined as the materials were not on-site
the bank approved a progress claim for the deposit on cabinetry and joinery for materials ordered but not on-site (as the materials were on the tradesman’s premises at that time).
The complainants clarified that they did not incur financial losses related to these examples, but they say it illustrates the inconsistencies in the bank’s processes.
The loan terms and conditions contain the following provision for when the bank may refuse a progress payment claim:
‘We reserve the right not to pay any construction loan drawing if you have not provided us with the documentation for the building works we told you in writing we needed or if the building works (if any) are not to our reasonable satisfaction […].’
Supporting documentation has not been provided for either of these progress claims; but in the absence of this, I will make the following comments:
while I acknowledge the elevator was being manufactured overseas, considering no materials were on-site at the time of the progress claim for the deposit, under the loan terms and conditions, the bank was entitled to refuse this progress claim or request further information from the complainants
as mentioned earlier, the quantity surveyor was not required to conduct an audit of all materials delivered to the site. It is unclear from the information provided whether there were any other cabinetry or joinery materials on-site at the time of this claim to satisfy the bank. But in any event, assuming the complainants signed builder B’s invoices and submitted these to the bank for payment, the bank has acted in line with the loan terms and conditions and its internal credit policies.
The bank is not responsible for builder A’s actions
As mentioned earlier, the complainants say builder A’s invoices were fraudulent because:
the invoices included claims for payments builder A said he had made to multiple suppliers; and
it was later discovered some of these payments had not been made, and materials were withheld by the suppliers accordingly.
As mentioned earlier, the bank engaged the quantity surveyor for its own purposes – to satisfy itself on the progress of the construction project, and to prevent cost overruns for the overall project to protect its security position.
The bank was not responsible for, nor did it have visibility of, builder A’s non-payment to certain suppliers. The building contract was an agreement between the complainants and builder A. As such, any dispute raised by the complainants about the actions of builder A, is a civil matter between them. The complainants appear to have been aware of this, as they instigated Court proceedings against builder A. In January 2023, they obtained a judgment from the Court against builder A, for the amount of $210,415 plus costs.
In February 2024, the complainants’ solicitor conducted an enquiry on their behalf into builder A’s financial position. The results showed any recovery of their losses from builder A was unlikely.
As of 9 May 2024, the complainants advised they had accrued legal and Court costs of $33,869 in their attempts to recover their financial losses. While I understand and sympathise with the difficult situation the complainants are in, the bank is not responsible for builder A’s actions. For this reason (and the reasons outlined earlier), the bank is not responsible for any legal costs incurred by the complainants in pursuing builder A for their losses.
Why is the outcome fair?
The outcome is fair in all the circumstances
The outcome is fair in all the circumstances because the bank met its obligations and did not make any error when it paid the progress claims to builder A. This is because:
the complainants signed the building contract with builder A. The bank was not a party to this agreement
the complainants authorised the bank to pay the progress claims to builder A by providing the signed invoices requesting payment
the complainants signed the loan contract provided by the bank, and the bank complied with the loan terms and conditions when it paid the progress claim payments to builder A
while the bank appointed a quantity surveyor, it did so for its own purpose, not for the complainants’ benefit. The complainants remained responsible for ensuring the build was completed to a satisfactory standard
the bank was entitled to decline a progress claim request in accordance with the loan terms and conditions if the works were not completed to its reasonable satisfaction.
The bank was not responsible for, nor was it on notice of, builder A’s decision to not pay suppliers – this is a civil matter between the complainants and builder A. The bank’s actions did not cause the complainants’ financial losses. For these reasons, it would not be fair to require the bank to pay financial loss compensation to the complainants.
Supporting information
Timeline of events
|
Date
|
Key points
|
22 Sep 2021
|
The bank obtained an independent valuation with an ‘as if complete’ value of $3.2 million.
|
1 Oct 2021
|
The quantity surveyor provided an initial costings report (report 1).
|
15 Oct 2021
|
The complainants signed the cost plus building contract with builder A and the loan contract for $2.375 million with the bank.
|
26 Nov 2021
|
Builder A issued an invoice for $134,928.30 for the ‘undercroft slab instal’ stage of the build (payment due date 7 December 2021).
|
10 Jan 2022
|
Builder A provided a statement of works to the complainants.
|
8 Feb 2022
|
First progress payment of $134,928.30 paid to builder A from the loan for ‘undercroft slab instal’ stage. This includes a aluminium window deposit of $14,718 of which the complainants say builder A did not pay to the supplier.
|
14 Feb 2022
|
Quantity surveyor report 2 (plus costing progress appendix).
|
21 Mar 2022
|
Builder A invoice for $134,928.30 for ‘undercroft plate height’ (payment due date 28 March 2022).
|
3 Apr 2022
|
Builder A’s supply/work log.
|
12 Apr 2022
|
The bank says it received the second progress payment claim request for builder A for ‘undercroft plate height’ stage for $134,928.30.
|
18 Apr 2022
|
The bank changed its procedure for progress payment claims. From this date it required customers to state: ‘I/we authorise payment of this invoice’ in addition to signing the builder’s invoice.
|
19 Apr 2022
|
Quantity surveyor report 3 (plus costing progress appendix).
|
20 Apr 2022
|
The bank says the second progress payment of $134,928.30 was processed/paid to builder A on this date.
|
9 Jul 2022
|
Builder A’s building registration expired. The complainants say builder A continued working unlicensed after this date while in contract with them.
|
25 Aug 2022
|
Email from the complainants to builder A requesting removal of scaffolding, delivery of outstanding pre-purchased bricks and list of expense receipts.
|
30 Aug 2022
|
Email from supplier to complainants advising builder A did not pay the deposit for materials or sign relevant documents to proceed with quote.
|
2 Sep 2022
|
Email from complainants to builder A terminating building contract and requesting copies of receipts for goods/services provided to date and a refund of the balance paid.
|
8 Sep 2022
|
Statutory declaration signed by the complainants regarding the termination of their building contract with builder A.
|
12 Sep 2022
|
Email from the engineer to the complainants advising builder A did not pay their invoices for site inspections completed.
|
15 Sep 2022
|
Complainants signed new cost plus building contract with builder B. Letter from builder B to the complainants with quotation and payment schedule.
|
13 Dec 2022
|
Schedule of payments with builder B.
Tax invoice and progress claim for builder B for $24,588.34.
|
10 Jan 2023
|
Complainants obtained default judgment from the Court against builder A for $210,415.82 plus costs.
|
8 Jan 2024
|
Quantity surveyor report 4.
|
15-19 Feb 2024
|
Complainants obtained ‘means enquiry’ information for builder A showing limited opportunity for them to recover their losses from him.
|
28 Feb 2024
|
The complainants say the bank approved progress payment of $78,780.72 to builder B. However, they say $20,000 worth of joinery work included as part of this claim had not been completed and no cabinetry materials were on site.
|
9 May 2024
|
The complainants advised they had accrued legal costs of $33,869.17 to date.
The AFCA process
AFCA’s approach is based on fairness
AFCA has assessed this complaint based on what is fair in all the circumstances, having regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided.
While the parties have raised a number of issues in their submissions, we have restricted this recommendation to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.