Text of the determination
Determination
|
Case number
|
12-00-1035958
|
Financial firm
|
The Hollard Insurance Company Pty Ltd
Case number: 12-00-1035958 25 September 2024
Determination overview
Complaint
The complainant holds a home insurance policy with the financial firm (the insurer). In March 2022, she lodged a claim for storm damage.
The home has been stripped out, but repairs have not started. The complainant’s building consultant estimates repairs will take 10 months. The complainant says she will not start repairs until the claim is settled.
In April 2024, the complainant’s building consultant estimated the cost of repairs at $424,760.92. The insurer said this was accurate, but some of the damage was caused by the complainant’s delay in starting repairs. It has offered to pay $295,781.83 for repairs.
The insurer paid the policy limit for accommodation, which covered accommodation to March 2024. The complainant wants the insurer to pay for accommodation until her home is repaired.
Issues and key findings
Should the insurer pay more for building damage?
Yes. Some of the claimed damage was caused by the delay in starting repairs. However, the insurer was responsible for the delay from March 2022 to October 2023. The insurer has not shown any damage occurred after October 2023.
The insurer made an interim payment of $100,000. The insurer should pay an additional $385,441.04, plus interest from 11 June 2024. Details of how this was calculated are set out in section 2.1 of this determination.
Should the insurer pay more for accommodation?
Yes. The insurer paid the policy limit for accommodation. However, the complainant incurred additional accommodation costs because the insurer mishandled the claim. The insurer should pay the complainant:
the reasonable cost of accommodation from March 2024 to 24 September 2024
the estimated reasonable cost of accommodation from 24 September 2024 to 24 July 2025.
Is the complainant entitled to other compensation?
Yes. The insurer must pay:
$5,000 (the most AFCA can award) for professional costs (partial reimbursement of the fee charged by the complainant’s building consultant)
$5,400 (the most AFCA can award) for non-financial loss (stress, inconvenience, and delay).
Why is the outcome fair?
Fairness requires the insurer to pay for any storm damage to the insured property, and any loss the complainant suffered because of the insurer’s errors.
The panel is satisfied that this determination provides the fairest possible outcome, based on the information provided by the parties.
Determination
This determination is in favour of the complainant.
The insurer must pay the complainant:
$385,441.04, plus interest at the rate determined under section 57 of the Insurance Contracts Act 1984 (Cth) from 11 June 2024 to the date of payment, in settlement of the claim for building damage
the reasonable cost of accommodation from March 2024 to 24 September 2024, and the estimated reasonable cost of accommodation from 24 September 2024 to 24 July 2025 (after the complainant provides information about her accommodation costs)
$5,000 for professional costs
$5,400 compensation for non-financial loss.
Reasons for determination
Should the insurer pay more for building damage?
Yes. Some of the claimed damage was caused by the delay in starting repairs. However, the insurer was responsible for the delay from March 2022 to October 2023. The insurer has not shown any damage occurred after October 2023.
The insurer made an interim payment of $100,000. The insurer should pay an additional $385,441.04, plus interest from 11 June 2024. Details of how this was calculated are set out in section 2.1 of this determination.
Insurer offers $295,781.83 for repairs
The complainant says tree branches fell on her roof during a storm on 12 February 2022. Water leaked through the roof during subsequent storms. The complainant put tarpaulins on the roof, but this did not stop the leaks.
The complainant appointed a builder (GP), who inspected the home on 10 March 2022. GP said there was ‘severe water damage and mould to [the] majority of ceilings and multiple walls’.
On 16 March 2022, the complainant lodged a claim for storm damage. The insurer said its builders were too busy to inspect or repair the damage (many insurance claims had been lodged after widespread storms and floods in late February 2022). The insurer advised the complainant to appoint her own builder to prepare a scope of works.
The complainant appointed another builder (IC), who inspected the home on 29 August 2022. IC prepared a scope of works totalling $283,321.50. The insurer did not accept this.
The insurer appointed a builder (AJG), who first inspected the home on 13 September 2022. AJG prepared scopes of work with the following totals:
$117,450.37 (13 September 2022)
$206,842.75 (20 July 2023)
$268,892.58 (undated, circa November 2023).
Descriptions, allowances, and room measurements varied between AJG’s scopes. The reasons for the changes are not clear. The complainant says she asked about the changes, but the insurer could not explain them.
On 16 November 2023, the insurer offered to pay $295,781.83 for building repairs (AJG’s quote of $268,892.58, plus a 10% contingency). The complainant did not accept the offer. The insurer has maintained the offer.
Experts agreed on cost of repairs of $424,760.92
The complainant appointed a building consultant (SG), who inspected the home on 8 April 2024. SG prepared a report on the damage to the home, and a scope of works for repairing the damage. The scope of works totalled $424,760.92.
AJG reviewed SG’s report and scope of works and reinspected the home on 11 May 2024. AJG said SG’s scope of work included all work required to repair the home. AJG recommended that the insurer settle the claim based on SG’s report and scope of works.
No damage attributable to complainant’s delay
The insurer admits SG’s scope of works is ‘fair’ and ‘accurate’. However, it says some of the damage was caused by the complainant delaying repairs.
In October 2023, the insurer made an interim payment of $100,000 to allow the complainant to start repairs. The insurer says the complainant’s failure start repairs in October 2023 allowed the house to deteriorate. It says it is not liable for this deterioration.
The panel does not accept the insurer’s argument, because:
the first expert to inspect the home (on 10 March 2022) reported ‘severe water damage and mould to [the] majority of ceilings and multiple walls’. This indicates the initial damage was severe and widespread
restoration work arranged by the insurer (including asbestos removal) was not finished until October 2023. The complainant could not have started repairs before October 2023
the complainant says (and the insurer does not dispute) large amounts of water entered the home on several occasions between February 2022 and October 2023 (despite attempts to prevent this by tarping the roof). Significant deterioration is likely to have occurred between February 2022 and October 2023
the insurer did not specify what damage occurred after October 2023 and did not ask AJG to comment on this.
The panel is satisfied that the damage identified by SG should be covered under the claim. The panel is not satisfied that any of the damage was caused by the complainant delaying repairs.
Home not a total loss
The complainant says the home is a total loss (meaning it would be more economical to demolish and rebuild than it would be to repair). She wants the insurer to pay the building sum insured of $1,049,700.
The complainant says AJG said the home was a total loss when they inspected it on 11 May 2024. However, this is not consistent with their report.
GP (who first inspected the home on 10 March 2022) reinspected the home on 28 February 2024. GP said the home had deteriorated since 2022, and now needed more extensive repairs. GP said the cost of these repairs would be considerably higher than demolishing and rebuilding the home.
The panel is not satisfied that the home is a total loss, because:
GP’s report is brief and lacks detail. It says the cost of repairs would be higher than the cost of demolishing and rebuilding, but does not say what either of these costs are
SG’s report is much more detailed than GP’s report. SG described all the work required to repair the home, and provided an estimate of the cost of this work ($424,760.92, less than half the building sum insured)
AJG said SG’s scope of works included ‘all the required repairs to ensure the property is brought back to pre-loss condition’.
The available information does not show the cost of repairs would exceed the building sum insured. The insurer is not required to settle the claim by paying the building sum insured.
Replacement of roof tiles not shown to increase costs
SG’s scope of works allows for the installation of a new steel roof. The insurer notes the home currently has a tile roof.
SG’s scope of works allows $49,226 (excluding builder’s margin, contingency, and GST) for roof repairs, including replacing existing tiles with steel sheets.
AJG’s latest scope of works allows $77,370 (excluding builder’s margin, contingency, and GST) for roof repairs, including replacing existing tiles with the nearest existing matching tiles.
The available information does not show the replacement of the tile roof with a steel roof will increase the cost of repairs.
Insurer not required to pay for roof and wall frames
SG’s scope of works was for ‘resultant damage’. This included damage caused by the initial storm and by water subsequently leaking into the property. It did not include the cost of rectifying the roof and wall frames because SG believed these were defective when originally constructed.
The complainant appointed an engineer (ZH), who inspected the home on 9 May 2024. ZH said some beams had insufficient support and connections. This is because of the construction of the building, not because of storm damage.
The insurer is not required to pay the cost of rectifying the roof and wall frames
Insurer must pay allowance for transfer of risk
The policy says the insurer can settle a claim for building damage by repairing the building or paying the cost of repairs. The insurer chose to settle the complainant’s claim by paying the cost of repairs. The complainant has not disputed this decision.
SG’s scope of works is the best available estimate of the cost of repairing claim-related damage. Therefore, the claim settlement should be based on SG’s scope of works.
When an insurer settles a claim by repairing damage, it guarantees the quality of the repairs. If the repairs are unsuccessful, or cause additional damage, the insurer is responsible for the cost of rectification. When the insurer settles a claim by paying the cost of repairs, it transfers this risk to the customer. Furthermore, the customer may find it more difficult and expensive to arrange repairs, because they do not have the insurer’s industry knowledge and bargaining power.
AFCA considers that if an insurer cash-settles a claim, it should consider paying an allowance for the transfer of risk. Generally, AFCA considers that a reasonable allowance is likely to be between 5% and 25% of the quoted cost of repairs.
The work needed to repair the complainant’s home is extensive. It includes mould remediation, the installation of new ceilings, walls, and flooring throughout the home, and a complete roof replacement. The risk of complications arising is high.
SG’s scope of works includes a 5% contingency. However, the panel considers a 20% contingency is required to account for the transfer of risk.
Increasing the contingency from 5% to 20% increases the cost of SG’s scope of works to $485,441.04.
Insurer must pay $485,441.04 for repairs
The insurer should settle the claim by paying $385,441.04 ($485,441.04, less $100,000 already paid).
Section 57 of the Insurance Contracts Act 1984 (Cth) says an insurer must pay interest on a claim settlement payment from the time it was unreasonable to have withheld payment. In the circumstances, the panel considers this to be 11 June 2024, one month after AJG’s report saying the claim should be settled based on SG’s scope of works.
The insurer should settle the claim for building damage by paying $385,441.04, plus interest from 11 June 2024.
Should the insurer pay more for accommodation?
Yes. The insurer paid the policy limit for accommodation. However, the complainant incurred additional accommodation costs because the insurer mishandled the claim. The insurer should pay the complainant:
the reasonable cost of accommodation from March 2024 to 24 September 2024
the estimated reasonable cost of accommodation from 24 September 2024 to 24 July 2025.
Insurer has paid policy limit for accommodation
The policy covers ‘reasonable temporary accommodation costs… for the time it will take to repair or rebuild the building to a liveable condition.’ This cover is limited to the lesser of 12 months’ rent or 10% of the building sum insured ($104,970).
The insurer paid the complainant $104,970 for accommodation costs. The complainant says this covered the cost of accommodation to March 2024. She wants the insurer to cover her accommodation costs from March 2024 until the home is repaired.
The insurer has paid the policy limit for accommodation. The policy does not entitle the complainant to any further payment for accommodation. However, if the complainant incurred additional accommodation costs because the insurer mishandled the claim, the insurer should compensate her for this loss, regardless of the policy terms.
Insurer should pay more for accommodation
The insurer arranged restoration work which was not completed until October 2023. The complainant could not have started repairs before October 2023.
The complainant was not able to start repairs in October 2023 because there was no accurate scope of works for repairs. The complainant had to appoint a building consultant to prepare a scope of works. This was done in April 2024.
The complainant said she received legal advice not to start repairs until the claim was settled, in case further inspections were required. She notes the insurer arranged an inspection by AJG in May 2024.
The panel considers the complainant should have started repairs in May 2024. However, the insurer did not respond to the complainant’s statement that she was delaying repairs in case further inspections were required. The insurer did not tell the complainant it would not require further inspections before repairs started.
In the circumstances, the panel considers it fair for the insurer to pay the complainant’s reasonable accommodation costs from March 2024 to now, and for the estimated time it will take for the home to be repaired.
SG estimated the repairs would take 10 months. The insurer has not provided information to refute this.
Reasonable for complainant to move out of caravan
In 2022, the insurer paid the complainant $104,970 for accommodation costs. The insurer says the complainant planned to use most of this money to buy a caravan to live in while her home was repaired. It says, if the complainant bought the caravan in 2022, she would not need to pay for accommodation now.
The complainant says she lived in a rented caravan for four weeks as a ‘trial’. However, with a family of six people and many large pets, she found it was not feasible to live in a caravan long-term. The panel considers this reasonable.
Complainant must provide information about accommodation costs
The insurer said it would consider paying further accommodation costs if the complainant provided receipts showing her current accommodation costs. The complainant has not provided this information.
The complainant must provide information showing the cost of her accommodation from March 2024. Upon receipt of this information, the insurer must pay the complainant:
the reasonable cost of accommodation from March 2024 to now
the estimated reasonable cost of accommodation for the next 10 months.
Is the complainant entitled to other compensation?
Yes. The insurer must pay:
$5,000 (the most AFCA can award) for professional costs (partial reimbursement of the fee charged by the complainant’s building consultant)
$5,400 (the most AFCA can award) for non-financial loss (stress, inconvenience, and delay).
Insurer must contribute $5,000 to complainant’s professional costs
Under the AFCA Rules, we can require an insurer to contribute to legal costs, other professional costs, or travel costs a complainant incurred in making a complaint.
AFCA cannot award professional costs of more than $5,000 unless there are special circumstances. The panel does not consider there are special circumstances in this case.
In deciding whether to award compensation, we consider whether the costs were reasonably incurred, and whether they helped resolve the complaint.
The complainant has provided an invoice showing SG charged her $10,762.40 for its inspections and reports. SG’s reports were comprehensive and accurate (as the insurer admitted). The panel found SG’s reports helpful in preparing this determination.
The insurer must contribute $5,000 to the complainant’s professional costs.
Insurer must pay $5,400 compensation for non-financial loss
Under the AFCA Rules, we can award up to $5,400 compensation for non-financial loss if a complainant suffered an unusual degree of stress, inconvenience, or delay because an insurer mishandled a claim.
The insurer mishandled the claim, because:
it did not complete restoration work until October 2023, more than 18 months after the claim was lodged. Many insurance claims were lodged after widespread storms and floods in late February 2022, making it more difficult for insurers to arrange timely attendances by contractors. However, even in these circumstances, the time taken to complete the restoration work was unreasonable
it did not prepare an accurate scope of works, which meant the complainant had to appoint a building consultant to prepare a scope of works
it refused to settle the claim based on the building consultant’s scope of works, even though its own builder recommended this
it said some of the claimed damage was deterioration caused by the complainant’s failure to arrange repairs. It did not identify which damage was caused by the complainant’s failure to arrange repairs. It ignored the delay from March 2022 to October 2023, which was outside the complainant’s control, and undoubtedly contributed to the deterioration
it said the complainant should have bought a caravan in 2022, which she would have had to live in (with her family of six people and many large pets) for several years. This was an unreasonable suggestion. The insurer said this justified its refusal to pay for accommodation after March 2024.
The damage to the complainant’s home would have caused her stress and inconvenience, even if the insurer handled the claim perfectly. However, the insurer’s handling of the claim has caused additional stress and inconvenience. The complainant has had to spend time and effort communicating with the insurer and AFCA and arranging for experts to inspect her home. The delay in repairing the home has extended the time for which the complainant is unable to live there.
The complainant contributed to the delay in repairing her home by deciding not to start repairs until the claim was settled. However, the most significant delay, from March 2022 to October 2023, was outside her control.
The insurer’s mishandling of the claim caused the complainant severe stress over a long period of time. The panel believes this warrants compensation of $5,400.
Why is the outcome fair?
Fairness requires the insurer to pay for any storm damage to the insured property, and any loss the complainant suffered because of the insurer’s errors.
The panel is satisfied that this determination provides the fairest possible outcome, based on the information provided by the parties.
Supporting information
The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided.
While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome.
A panel determined this matter
Due to the nature of this complaint, we referred it to a panel for determination. The panel includes:
an ombudsman
a member with extensive experience in consumer and small business advocacy
a member with extensive experience in insurance.