Home / Suncorp Group / Determination 12-00-1033909

Determination 12-00-1033909

Roof damage claim declined; ceiling repairs and excess dispute

FirmSuncorp Group
Decided2024-09-17
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The insurer accepted internal ceiling damage but declined roof damage as maintenance issues and an inherent defect. AFCA upheld the roof decline, but ordered the insurer to complete the ceiling repairs and treat the 2021 and 2023 damage as one claim with a single excess.

The roof underpitch and sealant issues are excluded maintenance or defect matters, but the insurer's failure to advise all roof works meant the internal damage should be one claim.

Issues

Subjects and remedies

home or building damagereassess claimrepair or rectify

Related

All Suncorp Group determinations · Find similar determinations

Text of the determination

Determination | Case number | 12-00-1033909 | Financial firm | AAI Limited Case number: 12-00-1033909 15 August 2024 Determination overview Complaint The complainant held a home building insurance policy with the financial firm (insurer). On 18 October 2023, she lodged a claim for internal damage to the living room ceiling and external damage to the roof arising from ongoing water ingress. The insurer accepted the claim for the resultant internal damage. However, it declined cover for the roof damage. It says there is no damage to the roof from an insured event. Further or alternatively, it also says the roof damage is expressly excluded under the policy. It also says that previous repairs to the living room ceiling following a storm event in 2021 were properly completed in 2022. The complainant disagrees with the insurer’s decision. She seeks that it covers the roof damage and says the internal damage is due to the previous faulty repairs. Issues and key findings Has the insurer correctly assessed the claim? Yes. The insurer has correctly assessed the claim. I am not satisfied the complainant has established a claimable loss for the roof. There is also no evidence the insurer’s repairs or inspection caused any damage or water ingress. Why is the outcome fair? It is fair that the insurer is not liable for any damage to the roof as these are maintenance issues or defects. The insurer also has not caused any damage or failed to property complete repairs. However, it is fair that the insurer completes the living room ceiling repairs and that the resultant damage from 2021 and 2023 is considered as one claim with a single excess. Determination This determination is substantially in favour of the insurer. If the complainant accepts the determination, within 14 days of being notified of the acceptance, the insurer is required to: engage any contractors to complete any outstanding repairs to the living room ceiling; confirm that it will assess the 2021 and 2023 resultant damage as a single claim and apply a single excess. Reasons for determination Has the insurer correctly assessed the claim? Yes. The insurer has correctly assessed the claim. I am not satisfied the complainant has established a claimable loss for the roof. There is also no evidence the insurer’s repairs or inspection caused any damage or water ingress. Onus on complainant to establish a claimable loss The complainant is required to show, on the balance of probabilities (that it is more likely than not), that there is a claimable loss under the policy. This means the complainant must prove the loss or damage was caused by a risk that is covered under the policy. Once the complainant proves there is a claimable loss, the insurer is liable for the loss unless it shows an exclusion or limiting condition applies. The insurer has the onus of proving, on the balance of probabilities, that the exclusion or condition applies. Policy covers accidental loss or damage subject to conditions and exclusions The insurer’s policy consists of the policy schedule and product disclosure statement (PDS). It is not in dispute the insurer provided the policy documents to the complainant. The complainant’s policy covers the complainant for accidental loss or damage. The PDS defines accidental loss or damage as ‘loss or damage that you did not intend or expect to happen’. However, the insurer relies on conditions in the policy which require the complainant to: • keep the building structurally sound, watertight, secure and well maintained (e.g. remove mould, fix any holes in floors, walls, ceilings, fix loose, missing or rusted steps, gutters, flooring); • …fix any inherent defect, faulty design, structural defect, structural fault and/or faulty/poor workmanship at the building as soon as possible after you identify it or are told about it… • ensure that the building is kept in good condition (e.g. there are no blocked gutters, the roof is not rusted, the building is not infested with vermin and there is no termite damage)… The insurer also refers to the Defects, faults, workmanship exclusion which excludes: • loss or damage caused by, connected with or arising from, or liability caused by, connected with or arising from inherent defects, faulty design, structural defects, structural fault or faulty/poor workmanship…if you knew or should have reasonably known about it (e.g. because the defect or fault was able to be observed by you or because it was identified in a pre-purchase building inspection report); • any loss or damage to the part of the building with an inherent defect, faulty design, structural defect or faulty/poor workmanship, whether or not you knew or should reasonably have known about it. Parties disagree about cause and extent of current damage to the property The complainant contacted the insurer on 17 May 2023 to advise that water was coming through the ceiling in the same spot as reported on the previous claim. The insurer has obtained a report from HR regarding the previous 2022 repairs and to assess the current damage. It also obtained a leak detection report from a plumber, MW. The MW report dated 14 July 2023 confirms that there was no leak from the bathroom above the living room and that all leak detection tests were passed. However, MW says, in relation to the roof, that: it is non-compliant as it is underpitched at only 0.2 degrees; the air conditioner flashing/cables have not been sealed correctly; spray testing to the air conditioner flashing failed. Water ingress was found to the living room ceiling below; and it recommends that the air conditioner flashing be sealed in accordance with Australian Standards. However, as the roof is underpitched, water tightness cannot be guaranteed. HR’s report states: when it attended the property on 30 May 2023, the complainant reported a water stain had reappeared on the living room ceiling which was previously repaired by HR. HR observed a small area of the ceiling where the plasterboard required replacement; when it attended on 13 July 2023, it noted water staining, popped fixings and a deflection to approximately 3 sqm of the lounge room plaster ceiling directly under the first-floor perimeter wall and the flat metal roof intersection; the plumber’s inspection of the roof found no storm damage present. Rather, the plumber identified a number of maintenance issues and that the roof was underpitched; in its opinion, the internal damage is consistent with a single new insured event. The damage is not due to inadequate repairs by HR’s trades in 2022; and extensive maintenance works are required to be completed by the customer to re-pitch the metal roof and replace apron flashings in order to prevent any future water ingress. On 12 October 2023, the insurer sent a maintenance letter to the complainant setting out the works required. It put the complainant on notice that any delay in carrying out these works may cause further damage to the property which may not be covered under the policy. The complainant has not obtained any expert reports. However, she says the damage is due to HR not completing the repairs properly on the previous claim. She also says the insurer’s contractors caused damage when inspecting the roof, including moving the air conditioner, which worsened the leak. On balance, no claimable loss in relation to the roof On balance, I do not consider the complainant has established a claimable loss in relation to the roof. The available reports have identified issues with the sealing of the roof and, more importantly, that it is underpitched. I accept MW’s evidence that even if the roof were resealed, this would not guarantee that the property would be watertight due to the under pitching of the roof. HR also says significant maintenance works including resealing and re-pitching the roof are required to avoid further damage. Outside of these issues, the experts say there is no evidence of any damage to the roof, accidental or otherwise, or as a result of a storm or other insured event. I consider both MW and HR are suitably qualified to comment on the roof. In the absence of any expert evidence to the contrary, I am not satisfied that there is in fact any damage to the roof other than the issues identified. Rather, I accept the inadequate sealant is a maintenance issue and the under pitching is an inherent defect. Therefore, there is no cover for these items as the policy expressly states that such items are not covered. Accordingly, the insurer is entitled to decline cover for any issues arising in relation to the roof. On balance, no issue with repairs or evidence insurer’s trades caused damage The complainant made a previous claim on the policy on or about 12 July 2021 when she noticed watermarks in the corner of the bathroom (above the living room) and the plaster bubbling. When she went downstairs, she also noticed yellow marks on the ceiling in the living room under the bathroom. The insurer obtained various reports in relation to the water ingress and concluded that the damage was the result of a storm related overflow from the single-storey flat metal roof sheets. The builder identified two main issues: water ingress to the first-floor bathroom has been caused by the lead flashing around the vent pipe not being weathered along the end (which has been folded down instead of up); the roof tile has not been cut around the flashing, instead the tile has been pushed up to sit behind the decktite; and water ingress to the living room ceiling is caused by flashing around the decktite over the first-floor roof but also silicone being applied to the downturns of the metal sheet cover flashings. Cracks in the silicone have allowed rainwater to pool under the capping and spill over the back of the roof sheet into the living room ceiling cavity. The builder also noted the roof was under pitched at 0.6 degrees. It says due to the amount of work required to adjust the pitch, tray deck flashings would be a better solution to be installed over the sheets. A second report from a roofer identified the maintenance repairs required as ‘Remove all silicone from the cover flashing that downturn above the living room and re-seal’. However, due to fading light at the time of the inspection, the roofer was unable to perform a full roof inspection. Following receipt of the expert reports, the insurer accepted the claim for the resultant internal damage however it said the complainant needed ‘to conduct some roof maintenance first before [the insurer could] proceed with internal repairs’. The maintenance works are not specified in the email. However, the insurer’s claim notes for the previous claim state that it ‘adv[ised the complainant] that only maintenance that [the insurer has] been adv[ised] of is Remove all silicone from the cover flashing that downturn above the living room and re-seal’. The insurer also told the complainant that ‘the trades that she engages to do maintenance on roof, will still need to do a full roof report to make sure that they address all issues’. It did not, however, issue a maintenance letter to the complainant or outline fully the issues identified by the builder. In response, the complainant provided an invoice confirming she had all her gutters cleaned. She has also provided a contemporaneous text message exchange with a contractor who confirms the entire roof has been resealed. I note the complainant says she does not have an invoice for the resealing work. The claim notes also confirm that once the complainant advised that the maintenance works were completed on or about 7 September 2021, the insurer arranged for its builder to complete the internal repairs. Due to Covid-19 lockdown delays, the repairs were not finalised until February 2022. The complainant says the previous repairs were not properly completed by the insurer’s contractors. She also says the plastic tarp placed beneath the air conditioner and the movement of the unit in order to carry out the roof inspection have caused damage to the seals. The complainant has also raised concerns about the repairs completed to the internal ceilings following the water ingress. She says the ceiling is no longer stable and is concerned that the first floor may cave in. The onus is on the complainant to establish that any previous repairs/make safe has not properly been completed. I am not satisfied that the complainant has established this. Further, there is no evidence, expert or otherwise, provided which suggest any faulty repairs. Rather, MW says the air conditioner flashing/cables have not been sealed correctly. I would also expect that if there were any issues with the repairs, it is unlikely to have taken over a year for this to manifest. Noting that the current leak occurred 15 months after the previous claim was made, on balance, I consider the previous internal repairs were properly completed by the insurer’s contractors. I otherwise do not consider there is any evidence of the insurer’s contractors having caused damage to the seals on the roof. Therefore, I am satisfied the insurer properly completed the repairs in relation to the previous claim. I also do not consider the insurer’s contractors have caused any damage to the sealant on the roof so as to cause or contribute to the water ingress. All internal damage should constitute one claim with a single excess It is not in dispute that the insurer has accepted the internal damage to the property in both 2021 and 2023. However, the only maintenance work that the insurer notified the complainant of in 2021 was the resealing of the roof. The insurer failed to fully advise the complainant of all the roof issues, including the under pitching and vent pipe, or any specific repairs required. Based on the evidence available, I accept that the general resealing work was carried out by the complainant’s contractor prior to the insurer completing the internal repairs. Arguably, if the complainant was advised of all the repairs required to the roof, the 2023 water ingress could have been avoided. The complainant was not given the opportunity to carry out these repairs as she was not informed of the extent of the maintenance work required. The insurer’s the failure to inform the complainant of all the repairs required to the roof does not mean the insurer is liable for these works. However, I do consider that due to this, the 2021 and 2023 internal resultant damage ought to constitute one claim and a single excess should apply. Why is the outcome fair? It is fair that the insurer is not liable for any damage to the roof as these are maintenance issues or defects. The insurer also has not caused any damage or failed to property complete repairs. However, it is fair that the insurer completes the living room ceiling repairs and that the resultant damage from 2021 and 2023 is considered as one claim with a single excess. Supporting information The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to: the legal principles applicable industry codes or guidance good industry practice previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider: available documents the recollections of the parties all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.