Determination 12-00-1032962
Alternative accommodation costs after policy benefit exhausted, and claim delays
Summary
The complainant's home was unliveable after a burst pipe and the insurer's policy alternative accommodation cap of 52 weeks was exhausted before repairs finished. AFCA ordered the insurer to reimburse $20,900 of further accommodation costs, rejecting the rest of her claim, including non-financial loss.
The insurer's handling contributed to repair delays, so it is fair to cover accommodation costs for the estimated remaining repair period outside the policy terms.
Issues
- Claim denial primary · upheld“It is fair that the insurer pays additional AA costs outside of its policy terms when it has contributed to the delays in repairs.”
- Claim amount dispute secondary · not upheld“Based on the available information, I am satisfied that the insurer's cash settlement for the remaining repairs is adequate.”
- Delay secondary · upheld“The insurer's claims handling has contributed to unreasonable delays.”
Subjects and remedies
pay claim
Related
Text of the determination
Determination
|
Case number
|
12-00-1032962
|
Financial firm
|
Hollard Insurance Partners Limited
Case number: 12-00-1032962 13 November 2024
Determination overview
Complaint
The complainant holds a home and contents policy with the financial firm (the insurer). On 3 February 2022, she lodged a claim with the insurer for damages to her home following a burst flexi pipe in her kitchen on 3 February 2022. There was water ingress throughout the townhouse, with water damage in the upstairs kitchen and open plan living room.
The insurer accepted the claim and the prepared a scope of works (SOW) for the repairs to the property. The complainant disputed the adequacy of the SOW. This led to protracted delays in commencing repairs. The insurer has now cash settled the complainant for the remaining repairs.
The complainant is seeking further alternative accommodation costs (AA) outside of the policy terms. She says that the insurer’s delays in commencing repairs were unreasonable and she has incurred further AA costs which she says the insurer should compensate her for. She says the insurer should continue to pay her AA costs until the repairs are completed, together with interest. The complainant also seeks compensation for the claim delays.
The insurer says that they have paid the complainant 52 weeks AA costs with a further 21 weeks on an ex-gratia basis. It denies that it is required to pay any more.
The complainant is represented by her father. For convenience, unless indicated otherwise, reference to ‘the complainant’ will include both.
Issues and key findings
Is the complainant entitled to further AA?
Yes. The insured property remained unliveable with repairs not completed. The insurer’s claims handling has contributed to unreasonable delays, and it is fair that the insurer be required to cover the AA costs equal to the estimated time it will take to complete the repairs accepted under the policy. However, the complainant is not entitled to reimbursement of AA for the period where she contributed to delays by refusing to sign a SOW.
Is the complainant entitled to non-financial loss compensation?
No. The complainant has not provided information in support that she suffered an unusual degree of stress or inconvenience due to the insurer’s management of the claim.
Why is the outcome fair?
It is fair that the insurer pays additional AA costs outside of its policy terms when it has contributed to the delays in repairs to the property following the insured event.
Determination
This determination is in favour of the complainant.
Should the complainant accept the determination, she is to provide evidence to the insurer that she has paid AA costs of $700 per week and within 14 days of receipt, the insurer is to reimburse the complainant the sum of $20,900.
Reasons for determination
Is the complainant entitled to further AA?
Yes. The insured property remained unliveable with repairs not completed. The insurer’s claims handling has contributed to unreasonable delays, and it is fair that the insurer be required to cover the AA costs equal to the estimated time it will take to complete the repairs accepted under the policy. However, the complainant is not entitled to reimbursement of AA for the period where she contributed to delays by refusing to sign a SOW.
Onus on complainant to establish a claimable loss
The complainant is required to show, on the balance of probabilities (that is more likely than not), that she suffered a claimable loss under the policy. This means that she must show the loss was caused by a risk for which she is insured.
Once the complainant, on balance, establishes a claimable loss, the insurer is liable for the loss unless it shows an exclusion or limiting condition applies. The insurer has the onus of proving, on balance, the application of the exclusion or condition.
The terms of the policy include the Certificate of Insurance (COI) and the Product Disclosure Statement (PDS). The policy covers damage caused by one of the listed events. It does not provide cover for all damage. Amongst these events is cover for sudden escape of liquid.
There is no dispute that the complainant’s home was inundated with water following the burst flexi pipe. However, a dispute has arisen as to the insurer’s obligation for settlement of the AA when the AA benefit under the terms of the policy has been exhausted.
Policy provides for AA
Page 39 of the PDS provides that AA are an additional benefit. The policy provides:
Alternative accommodation costs
If we pay your claim as a result of an insured Event and the damage at your insured address is so extensive that you can no longer live there, we will pay your reasonable accommodation costs:
- If you own your insured address and have Building Cover; or
- If you own the insured address, and it is a strata title property, and your contents are insured by this policy.
If we pay these costs, we will do so from the time your insured address becomes unliveable until it is liveable again, for up to a maximum of 52 weeks.
Complainant says that insurer has caused delays
The complainant says that since the date of the insured event, she has resided in the neighbouring property which is owned by her father and is paying him rent. She says that she pays her father $700 per week. The complainant advised that she initially paid her father $550 per week but as the insurer had delayed repairs to the property which meant that she required further AA, this had increased to $700 per week. She said that there had also been a typographical error when she initially submitted the claim where she recorded that she paid her father $450 per week.
The complainant seeks payment of AA from 5 May 2023 until the repairs are completed. The complainant also seeks to be reimbursed $150 per week for the period where the insurer paid $550 per week. That is from 3 February 2022 until 3 February 2023 in the amount of $7,800.
The complainant refers to a previous AFCA determination 834998 and says that this supports her claim that AA should be paid until repairs are completed notwithstanding that it was outside of policy terms. She says that the delays have been caused by the insurer and therefore it should be required to continue to pay AA until the repairs are completed.
Insurer says reasonable AA has been provided
The insurer says:
it has paid the policy limit of 52 weeks and an additional 21 weeks of AA on an ex-gratia basis
it has paid AA at the rate of $700 per week, despite the complainant providing signed receipts acknowledging payment of $450 per week, and then claimed to be $550 per week
the complainant has provided little evidence to substantiate their claim for AA, by way of a residential tenancy agreement or bank statements evidencing payments
the rental appraisal provided by the complainant does not verify the rent paid by the complainant
the complainant has contributed to the repair delay, for example by failing to sign a SOW and attending to maintenance on the balcony as requested to enable repairs to commence.
The insurer denies that it should pay any additional AA as the complainant has failed to provide proof of loss as requested.
Complainant has contributed to claim delays
The insurer had accepted the claim and authorised the repairs to commence on 6 April 2022. However, the complainant disputed the extent of the SOW and claimed additional damages were omitted. These included concerns about the extent of painting to include undamaged walls to colour match the repairs, and the upstairs bedroom. The insurer has provided the SOW’s prepared by UB which outline the variations. In August 2022 remediation works were continuing.
Further amendments to the SOW were included in March 2023, with post mould remediation being completed in early February 2023.
An amended SOW was sent to the complainant on 19 April 2023. The complainant disputed the lack of inclusion of repairs to the balcony. While the complainant alleged that the damage was from the insured event, she did not provide any evidence by way of an expert report to refute the findings of the insurer’s builder UB. UB found that the damage was caused by a lack of grout and sealing and was a maintenance issue.
The complainant later alleged in July 2023 that the insurer’s contractors had caused damage to the balcony when undertaking leak detection tests and/or by placing equipment on the balcony. However, the complainant did not provide any evidence to support the allegations.
PF, a plumber, undertook a flood test on the balcony on 8 March 2022 on behalf of the insurer. The report provides colour photographs of the balcony, including gaps evident between the wall lining and tiles and a lack of grout. A further leak detection test was undertaken by NL, plumber, on 7 July 2022. NL used buckets of water and found that the balcony’s tile grout failed due to tiles dislodging off the balcony wall.
UB responded to the complainant’s allegations in an email dated 24 July 2023, and said that the leak detection test would not cause damage to the membrane but tracks where the existing fault is. UB noted that the leak was identified almost immediately and therefore the drain was blocked only for a minimal period of time.
I am satisfied that UB’s explanation is reasonable and note that leak detection tests are a common testing method used to assess leaks. Further, the initial report by UB dated 4 March 2022 showed gaps evident between the wall lining and tile. A cracked tile was also evident.
UB said that it was not possible to complete the repairs to the garage until the maintenance work which included re sealing the balcony had been completed.
The complainant signed the SOW on 19 October 2023 after the insurer agreed to include the maintenance repairs to the balcony to enable the repairs to continue on an ex gratia basis. Repairs commenced on 21 October 2023.
On 22 November 2023, repairs were halted when further damage was found in the joists in the balcony. The insurer appointed an engineer, IE who inspected the property and prepared a SOW for repairs which included the replacement of timber joists and blocking timber.
The parties were also in dispute in relation to the flooring, with the complainant saying that the flooring supplied by the insurer was not the same colour.
The insurer elected to offer the complainant a cash settlement for the remaining repairs on 22 February 2024 based on a SOW prepared by IE and quote from UB for the remaining repairs, including the garage.
I am satisfied that the complainant caused delays with her:
challenges to the SOW for relatively minor inclusions to the SOW such as painting to ensure matching
refusal to undertake maintenance repairs to the balcony
refusal to sign a SOW until the maintenance repairs of the balcony were included
delayed acceptance of cash settlement offers to complete repairs.
Insurer should provide further AA
There is no dispute the policy includes an additional AA benefit. However, this cover is not unlimited and is subject to conditions and limitations as noted above. The AA benefit is triggered when, the damage is so extensive that the insured is unable to live there.
The insurer says that it has paid the complainant 52 weeks of AA. It has paid for a further period from 6 February 2023 until 2 May 2023 on an ex-gratia basis in the amount of $15,361.28.
The complainant has provided inconsistent evidence in support of her claim for AA. Inconsistencies have been shown in the records of the amount being paid, which was initially receipted and signed by the complainant’s father as being $450 per week. This was then amended to $550 per week, with the complainant saying that it was a typographical error.
Later, the complainant claimed it should be $700 per week based on a recent market rent appraisal from an agent. There has also been confusion as to how the complainant was paying rent, as notwithstanding that the complainant had provided a signed agreement/letter saying that she had paid her father cash for rental payments, the insurer was directed to pay rent into the complainant’s father’s account.
These inconsistencies have caused concern to the insurer in establishing whether the rental payments are reasonable. However, they have accepted them and paid them, including reimbursing the complainant for the revised rent of $700 per week for a period of 52 weeks, paid on 3 May 2023.
The complainant also claims that a further $7,800 is outstanding in AA.
The insurer has provided evidence of payment of $7,800 for accommodation for the period 5 February 2022 until 5 February 2023 which was paid on 3 May 2023.
I am satisfied based on the available information that the insurer has compensated the complainant for the period 5 February 2022 until 5 February 2023 and no payment is required.
The complainant seeks AA from 2 May 2023 until the repairs are completed based on a rent of $700 per week.
I am satisfied that the complainant’s conduct did contribute to the delays and prevented repairs from commencing in a timely manner. The insurer should not be required to pay for AA when the complainant has not established that the delay was warranted.
The complainant did not provide any evidence to substantiate her claim that the damage to the balcony was from the insured event. The insurer accepted the repairs to the balcony, although not required to under the policy, in an effort to allow the repairs to commence. It would not be fair to require the insurer to pay AA on an ex-gratia basis for this intervening period of 5 months.
However, I accept that little repairs were undertaken in the first twelve months which exhausted the AA under the policy. The insurer could have taken further steps to improve the claim delays, including accepting the damage to the garage earlier based on the available information.
On 27 February 2024, the insurer offered to settle the complainant an additional $20,900 towards AA based on:
the period from 21 October 2023 until 28 February 2024
an additional 11 weeks calculated from 1 March 2024 to 17 May 2024
The insurer relied on the estimate provided by UB in the SOW for the remaining repairs. However, the insurer later withdrew the offer as the complainant had not provided evidence to substantiate her claim for AA.
In the circumstances, it is fair that the insurer compensates the complainant for further AA based on a rent of $700 per week. The insurer had previously accepted this and had not sought to challenge the complainant earlier. It would not be fair to now require the complainant to provide evidence in support of this arrangement which is clearly an informal arrangement between family members.
There is no dispute that the insured property remained unliveable for this period and that the complainant resided in the neighbouring property which her father owned and arguably would have otherwise tenanted.
The insurer’s offer is fair in all the circumstances, noting that the complainant’s builder’s AN estimate for the remaining repairs was 3 weeks.
While the complainant refers to a previous AFCA determination of 834998 which determined that the insurer was required to pay AA outside of policy terms, the factual circumstances distinguish this matter. In that determination, the insurer had initially accepted the claim and commenced repairs and then subsequently denied the claim almost a year later. The determination found that the insurer was not able to deny the claim as the complainant has established a claimable loss and was required to pay AA until the repairs were completed.
The complainant is to provide evidence to the insurer that she has paid AA costs of $700 per week and within 14 days of receipt, the insurer is to reimburse the complainant the sum of $20,900 for the period as noted above.
Cash settlement appropriate
The insurer has cash settled the remaining repairs based on a SOW from UB in the amount of $23,873.47 which also included an uplift of 20% for contingencies and the loss of the lifetime guarantee.
The complainant also provided an informal quote from a builder AN contained within an email dated 27 May 2024 that estimated repairs in the sum of $22,000 on a cash basis.
The complainant accepted the insurer’s offer for a cash settlement on 31 May 2024 in the amount of $23,873.47 with an additional payment of $1,300 for electricity costs. The insurer paid these costs to the complainant on 16 October 2024.
The complainant says that the cash settlement may not be accurate if there are structural problems as advised by a representative from UB. The complainant says that the insurer cash settled them in respect of the repairs to the garage as it could not warrant the repairs to the damaged beams, wood and ceiling of the garage due to structural concerns about the two properties that adjoin each other.
The insurer has provided an email from UB dated 27 June 2024 which confirms that structural joists in the garage have been included in the SOW. UB noted that the balcony next door was poorly maintained and believed that there could be water ingress from the balcony which may have had or will continue to impact on the joists which are to be replaced.
The complainant’s builder did not identify any issues and was prepared to undertake the works for less than what was quoted by UB. The complainant has not provided any information to support her claim that the cash settlement is inadequate.
Based on the available information, I am satisfied that the insurer’s cash settlement for the remaining repairs is adequate. I accept that the insurer’s builder may not be able to warrant repairs if there are issues with a neighbouring property which does not relate to the insured event.
Is the complainant entitled to non-financial loss compensation?
No. The complainant has not provided information in support that she suffered an unusual degree of stress or inconvenience.
AFCA can award compensation for non-financial loss
Under our Rules, AFCA can award up to $5,400 compensation for non-financial loss. This must relate to poor claims handling or other actions of the insurer which cause an unusual degree of stress, delay, or inconvenience.
No compensation in the circumstances of the claim
The complainant’s representative, her father, has included a submission advising that he seeks compensation for the stress and anxiety the claims delays have caused him. The complainant’s representative has managed the claim for its entirety. However, the complainant’s representative is not the policy holder or a member of the complainant’s household.
The complainant has not provided any information that supports that she has suffered any stress and anxiety because of the claim delays. The AFCA Rules do not allow for an award of non-financial loss compensation to the complainant’s father.
Rule D.3.3(b) provides that compensation may be warranted in relation to the time taken to resolve the situation. While I acknowledge that the claim has been ongoing for more than two and a half years, the delays are not solely caused by the insurer.
In all of the circumstances, I am not satisfied that an award of compensation to the complainant is warranted.
Why is the outcome fair?
It is fair that the insurer pays additional AA outside of its policy terms when it has contributed to the delays in repairs to the property following the insured event.
Supporting information
The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. I have reviewed and considered all of the information the parties have provided.
While the parties have raised a number of issues in their submissions, I have restricted this determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.
Damage to kitchen sink and benchtop not considered
The complainant forwarded an email dated 11 November 2023 claiming additional damage to a kitchen sink and the omission of the kitchen benchtop from the SOW. These items were not considered as the determination had been finalised and have not been previously raised as part of this determination.