Text of the determination
Determination
|
Case number
|
12-00-1029174
|
Financial firm
|
AAI Limited
Case number: 12-00-1029174 03 December 2024
Determination overview
Complaint
The complainants first made a claim in 2016 and repairs to a bridge were completed at the direction of the insurer.
The complainants made a further claim 18 March 2020 for erosion of the creek bank around a bridge footing.
That further claim was resolved as the insurer accepted liability for the erosion of the creek bank and agreed to pay $5,000 non-financial loss compensation.
The current complaint was raised on 20 October 2023. The complainants say after the previous complaint was resolved in May 2021, the bridge has still not been constructed.
They also say the insurer caused further, extensive and unreasonable claim delays, and the service quality and claim handling provided by the insurer was poor. They are seeking for:
the bridge construction to be completed
the insurer to pay further non-financial loss compensation for significant claim delays and poor service quality.
Issues and key findings
Is non-financial loss compensation payable?
Yes. The insurer is required to pay further compensation.
Why is the outcome fair?
The outcome is fair as it is consistent with the exchanged information, the insurer’s obligations under the policy and AFCA’s Rules.
Determination
This determination is in favour of the complainants.
If the complainants provide written notice that they accept this determination (notice), the insurer is required to:
within 14 days of receiving the notice, pay each complainant $5,400 (total $10,800) compensation $5,400,
within 14 days of receiving the notice, pay each complainant $2,700 (total $5,400).
Reasons for determination
Is non-financial loss compensation payable?
Yes. The insurer caused unreasonable and extensive delays and communicated poorly. The insurer also handled the claim poorly and provided overall poor service. The delays and poor claim handling each caused the complainants major stress, inconvenience and significant physical and emotional hardship.
Background
The complainants made a claim in 2015 for damage to a bridge on the property, which was accepted, and the insurer directed the repair of the bridge footings, which was completed in February 2016.
The complainants made a further claim on 18 March 2020 for erosion of the creek bank around the bridge footing. They said it had been incorrectly designed and constructed and was the cause of continuing erosion and damage to the creek bank.
The claim was initially declined on 16 November 2020. However, the complainants initiated the insurer’s internal dispute process, and the decline was rescinded. The insurer determined it needed more information and engaged a hydrologist.
The complainants then lodged the previous AFCA complaint, 780942. Under that complaint, the complainants had also raised issues with the quality of service provided by the insurer.
After negotiation facilitated by AFCA, the insurer accepted liability for the erosion of the creek bank and the complaint was resolved on 7 May 2021. The insurer also agreed to pay the complainants $5,000 non-financial loss compensation for the poor service quality it had provided up to that date.
The current complaint was raised on 20 October 2023. The complainants are seeking:
the bridge construction to be completed
further non-financial loss compensation for significant and extensive claim delays and poor service quality
The bridge construction is complete
The complainants informed AFCA the insurer’s trades commenced construction of the bridge on 7 September 2024 and completed it on 25 October 2024. Given construction is now complete, AFCA considers this issue has been resolved and will not address it any further in this determination.
AFCA can award compensation for delays and poor claim handling
Under paragraph D.3 of the AFCA Rules, we may award compensation for non-financial loss (capped at $5,400 per claim) where the insurer’s actions have caused an unusual amount of:
physical inconvenience
time taken to resolve the situation
interference with the complainants expectation of enjoyment or peace of mind.
AFCA takes the view that a ‘claim’ refers to the set of facts that, put together, gives the complainant the right to ask for a remedy. The $5,400 compensation cap for non-financial loss claims applies to each claim, so AFCA can award a complainant, or complainants more than $5,400 in total in a complaint if they have several claims.
AFCA can award separate non-financial loss compensation for each insured listed on a policy, if they are also complainants included in the AFCA complaint.
When considering an award for non-financial loss, AFCA considers the severity and impact of the insurer’s conduct on each particular complainant.
Insurer caused unreasonable and significant delays, stress and inconvenience
The information shows the complainants were first advised in September 2021 that the bridge was expected to be completed before Christmas 2021. However, construction only construction in September 2024 and was completed on 25 October 2024.
The complainants say the insurer’s actions and those of its agents caused the claim, construction and repair of the bridge to be unreasonably delayed. They say this has caused them severe, unreasonable and significant stress, inconvenience, together with physical and emotional hardship.
The exchanged information is voluminous and will not be repeat here. However, I will summarise key aspects.
The insurer was aware from the start that:
the property is in a rural location
the bridge is the only route over the creek to access the complainants’ property
the weight restriction of the bridge in its damaged state was only 2 tonne, which meant ambulance, fire and other emergency services vehicles could not access the property.
The available information shows the following issues contributed to unreasonable delays in finalisation of the claim:
the complainants had approximately 14 claim managers and 6 project managers
on several occasions the insurer’s contractors made appointments with the complainant which they then, without notice, failed to attend
there were periods where the insurer and its agents did not maintain contact with the complainants at least every 21 days
the complainants were given confusing and contradictory information about whether they would be able to remain in the property during bridge installation
the complainants were not provided updated versions of construction plans, reports and other expert information in a timely manner, which caused them to waste time and effort querying outdated information
the builder and project manager (AB) did not have access to historical correspondence between the parties and this resulted in them needing to request copies of correspondence from the engineer (KM) to respond to the complainants’ questions regarding bridge design elements
the information given to the complainants regarding progress on fabrication of the bridge, readiness to commence construction, and the inclusion/exclusion of crucial design elements by the insurer, AB, and KM, was frequently inconsistent, confusing and contradictory
on multiple occasions the complainants were told an expected completion date (despite the bridge manufacture not having commenced) which was then repeatedly changed
despite asking multiple times, the complainants were not provided with any repair schedule or specific timeline until September 2024
the changes in claim handlers at the insurer resulted in previously included and crucial elements of the scope of works (such as gabion baskets) being erroneously left out in subsequent revisions, or previously confirmed variations being re-reviewed
the complainants were told construction of the bridge had been approved and ordered in September 2022, but in December 2022 the insurer elected to re-investigate the claim citing ‘discrepancies’ in the initial reports
in January 2023, the insurer told the complainants that all previous bridge design variations submitted by AB were invalid (an eighth variation was approved in late January 2023)
until July 2023 the bridge manufacturer was unaware gabion baskets were required as part of the design, and this added additional time.
The complainants say their lives in general, ability to conduct maintenance, complete crucial property repairs, and address health and safety-related property issues was severely impacted by the ongoing delays in bridge repair. In particular the weight restriction of the bridge in its damaged state was an issue. They say:
they had to change their gas supplier to one that was able to deliver gas bottles for heating, hot water and cooking on a light utility
their energy supplier (EX) was not able to access the property to resolve a power-outage in May 2024
they were unable to complete preventative bushland maintenance to the area that was closed off by the make-safe fencing installed by the insurer, over three bushfire seasons
they were unable to have demolition and earthmoving machinery access the property to remove fallen trees or demolish a building damaged by trees which fell in a January 2023 tornado event
they were unable to preventatively remove large gum trees adjacent to the property after the January 2023 tornado
they were unable to resurface the gravel driveway after multiple significant storm events washed away parts of it between 2021 and 2024
they were unable to have the contractor access the property to clean the water tanks that provide their drinking water
they were unable to maintain their non-potable water pumps as the supplier has a 5-tonne truck.
The insurer says there were delays caused by COVID lockdowns and the wet seasons in Queensland. The insurer has apologised and acknowledged several times that the claim has taken an unreasonable amount of time to resolve.
The insurer has not provided any explanation or apology for its poor claim handling.
I am satisfied the available information shows, aside from COVID lockdowns, or wet season periods where construction could not take place, the insurer and its agents caused extensive and unreasonable delays to the claim.
The extensive delays also significantly reduced the overall safety of the complainants’ property, given certain emergency vehicles could not access it. I acknowledge and accept this would have contributed significantly to and compounded the complainants’ stress and concerns for their safety at home.
I am satisfied the extensive delays caused by the insurer caused the complainants unreasonable and significant stress, inconvenience, physical and emotional hardship, and greatly reduced their overall enjoyment of their property, for the life of the claim.
I am satisfied the actions of the insurer and its agents also resulted in poor service quality, and a poor overall claim experience. The poor claim experience, separately from delays, caused the complainants separate and significant stress, inconvenience, physical and emotional hardship.
The insurer’s unreasonable and extensive delays amount to the first stand-alone ‘claim’ giving the complainants a right to request non-financial loss compensation.
The insurer’s poor claim handling is a second stand-alone ‘claim’ giving the complainants a right to request non-financial loss compensation.
I am satisfied the complainants have a right to non-financial loss compensation for each of the above ‘claims’. The insurer is to pay each of the complainants, the following individual amounts, totalling $16,200:
$5,400 for stress, inconvenience, physical and emotional hardship caused by delays
$2,700 for stress, inconvenience, physical and emotional hardship caused by poor claim handling.
Why is the outcome fair?
The outcome is fair
It is fair in all the circumstances that the insurer pays the complainants individual non-financial loss compensation amounts because:
it caused unreasonable and significant and extensive claim delays and;
the quality of service it provided and overall claim handling was poor.
Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all the information the parties have provided.
While the parties have raised several issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.