Home / Allianz Australia / Determination 12-00-1028115

Determination 12-00-1028115

Claim for corroded steel stumps denied as gradual deterioration and corrosion excluded

FirmAllianz Australia
Decided2024-06-27
ProductGeneral Insurance · Home building and contents
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The complainant claimed for corroded steel stumps under his home building policy after attributing the damage to storm rainfall. AFCA found the damage was gradual corrosion from defective original installation and excluded under the policy, so the insurer was entitled to deny the claim without further investigation.

The proximate cause of the corrosion was the lack of adequate stump corrosion protection rather than rainfall, and the policy excludes gradual deterioration, structural defects and corrosion unless a direct result of an insured event.

Issues

Subjects and remedies

home or building damageno remedy

Related

All Allianz Australia determinations · Find similar determinations

Text of the determination

Determination | Case number | 12-00-1028115 | Financial firm | Allianz Australia Insurance Limited Case number: 12-00-1028115 27 June 2024 Determination overview Complaint Since 2018, the complainant has held home building insurance with the financial firm (insurer). On 18 October 2022, he lodged a claim after it was identified the home’s steel stumps were corroded. He attributed the corrosion to recent storm activity. The insurer denied the claim. It says the damage predates the policy’s commencement and is not due to a single storm. Rather, the damage was caused by gradual deterioration, wear and tear, and structural defects. Damage from those causes is excluded under the policy terms. The complainant says the insurer did not adequately investigate the claim. He submits that it is probable some stumps only began to deteriorate after the policy commenced, and that already corroded stumps might have been further damaged by subsequent rainfall. The complainant wants further investigations to be undertaken, and for the insurer to indemnify him for any damage to the stumps that occurred after the policy commenced. Issues and key findings Is the insurer entitled to deny the claim? Yes. The exchanged information sufficiently establishes that the complainant has not shown a claimable loss under the policy terms. Instead, it is more likely than not the damage is the result of excluded causes. Why is the outcome fair? It would not be fair to require the insurer to further investigate or accept the claim when the exchanged information confirms that the policy does not respond. Determination This determination is in favour of the insurer. The insurer is entitled to deny the claim. It is not required to take any other action. Reasons for determination Is the insurer entitled to deny the claim? Yes. The exchanged information sufficiently establishes that the complainant has not shown a claimable loss under the policy terms. Instead, it is more likely than not the damage is the result of excluded causes. ​Complainant must show a claimable loss under the policy ​The complainant is required to show on the balance of probabilities (that it is more likely than not), that he suffered a claimable loss under the policy. This means he must show the loss was caused by a risk for which he is insured. ​Subject to the terms and conditions set out in the product disclosure statement (PDS), the complainant’s policy covers damage to his home caused during the period of insurance by a listed insured event. Those events include ‘Storm cyclone, rainwater or run-off’ (Storm insured event). ​On 18 October 2022, the complainant notified the insurer his home’s steel stumps were corroded. The complainant said the damage had been happening for years, but he only noticed the problem on 18 August 2022. ‘Stumps have rusted, this is a two storey house, this has occurred with the rain water we have had’. ​Once the complainant proves the existence of a claimable loss, the insurer is liable for the loss unless it shows an exclusion or limiting condition applies. The insurer has the onus of proving on the balance of probabilities the application of the exclusion or condition. Proximate cause of damage must be determined In a claim under a general insurance policy, the term ‘proximate cause’ is used to describe whether an event is the cause of the loss or damage. The proximate cause of a loss is the dominant, effective or operative cause. It does not have to be the first, the last or the only cause. It is a question of fact that depends on the circumstances of each case. It requires a common-sense evaluation of the evidence. If there are several causes, each should be examined to determine whether it is a dominant, effective or operative cause of the loss. For example, if one cause would have caused the loss on its own, and the other cause would not have caused the loss without the first, then the first is the proximate cause. Insurer denied the claim The insurer engaged engineer CR to report on causation. CR inspected the home on 7 December 2022, and reported that:  the home is about 70 years old, was extensively renovated in 1999, and was purchased by the complainant in 2015  a stump to footing connection diagram stamped as an ‘approved plan’ by a building certifier in 1999 shows the concrete pad surrounding a post extending above ground level and sloping away from the post. Presumably, the intention was that surface water would shed away from the post (stump)  trades installing a retaining wall in August 2022 noticed significant corrosion at the base of several steel stumps. Many corrosion-affected stumps were subsequently identified  due to wall cladding and pavement build up, observations of the steel stumps/posts were generally very limited  most of the steel stumps that were viewed showed varying extents of corrosion to their bases, indicating a global issue rather than a localised problem  the concrete surrounds for several stumps did not reach ground level. Other stumps had the concrete pad footing extend above ground level but were still corroded  the proximate cause of the corrosion was the failure by the builder who attended to the 1999 renovation to provide adequate corrosion protection of the stumps  the builder had therefore not complied with the minimum requirements for steel stumps set out in the version of the Building Code of Australia applicable at the time of the renovation  ‘The observed corrosion is long-term multiple-year, progressive chemical degradation of the metal, which is unrelated to any one-off definable event’  ‘The corrosion was likely in existence prior to the Ownership of the property by the Insured, slowly continuing to degrade due to its current condition’. Based on CR’s report, the insurer has denied the claim. It says:  the damage has been occurring since before the policy commenced in 2018  multiple rainfall events since the 1999 renovation have contributed to the damage  the policy only covers damage from a single identifiable insured event  in any event, the proximate cause of damage was the builder’s failure in 1999 to provide adequate corrosion protection of the stumps. In addition, the insurer submits that policy exclusions apply to preclude cover for the claim. It refers to pages 55 and 56 of the PDS, pursuant to which the policy does not cover damage:  as a result of, caused by or arising from: > gradual deterioration, wear and tear > faulty design, structural defects or poor workmanship  caused directly or indirectly by rust or corrosion, unless it is a direct result of an insured event. Complainant disputes the claim denial The complainant says the trades he engaged in August 2022 to replace a timber retaining wall discovered several stumps had not been installed correctly. Those stumps had not been raised to the proper height with concrete and lacked appropriate rust protection. Further investigation showed many stumps were affected, resulting in him lodging the claim. He has provided a diagram of how the stumps were installed and how they should have been installed. The former shows a stump with concrete at its base, well below ground level. The latter aligns with the building certifier’s 1999 approved plan diagram. The complainant relies on a report dated 6 March 2023 by engineer BC. After inspecting the home on 14 February 2023, BC reported that:  only a limited number of stumps could be reviewed, with the majority not visible due to timber cladding, metal capping and ground surface  ‘The presence of rainwater and run-off in combination with concrete or ground against the steel stump is expected to exacerbate corrosion to the steel stump’  ‘In our professional opinion, the proximate cause of the observed corrosion to the steel stumps was the presence of rainwater and run-off in the ground’  the significant corrosion damage would have increased over an extended period of years due to each rainfall event providing rainwater and runoff. In relation to proximate cause, the complainant submits that: The rust started under the soil surface and travelled upward. The only reason the stumps rusted is because of rainfall. If there had been no rainfall, the stumps would not have rusted even though they were incorrectly installed. Thus, as stated by [BC], the proximate cause of the rust is rainfall. The complainant says BC’s report should be preferred over the report by CR because CR:  conducted an investigation that was neither proper nor credible  ‘claimed that the cause of the rust was moisture in the air, which is not credible’  is the insurer’s panel engineer, whereas BC is truly independent. He lists his concerns as:  the insurer did not investigate the timing of each stump’s rust deterioration  it is probable that some stumps began deteriorating after the policy commenced  stumps that began deteriorating before the policy commenced might have experienced further damage due to subsequent exposure to rain. The complainant wants the insurer to:  obtain a comprehensive rust assessment from an independent engineer appointed by AFCA, addressing his concerns  indemnify him for the repair costs related to stumps the engineer determines: > began deteriorating after the policy commenced > were deteriorated before then, but after the policy commenced suffered additional damage due to subsequent rainfall. Insurer is entitled to deny the claim Based on the exchanged information, the insurer is entitled to deny the claim without having to undertake further investigations. I am satisfied the complainant has not shown a claimable loss under the policy terms. Instead, it is more likely than not the damage is due to excluded causes. This is because:  CR concluded that: > the proximate cause of the corrosion was the failure by the builder who undertook the 1999 extension to provide adequate stump corrosion protection > the corrosion has been occurring gradually over many years, likely from well prior to the policy’s commencement > the damage is not the result of a single storm  CR’s report contains more detailed analysis on causation than BC’s report. Overall, I find CR’s report more persuasive  applying a common-sense evaluation of the evidence, I agree with CR that the proximate cause of damage was the lack of adequate stump corrosion protection, not rainfall. If the stumps were adequately protected, the rainfall/runoff would not have had an impact  I do not agree with the complainant’s criticisms of CR. The contention CR failed to properly investigate is without evidentiary support and I am satisfied CR is an independent expert. I also note CR did not conclude that the corrosion was from moisture in the air  CR, BC and the complainant agree the damage has been occurring gradually over years  the complainant acknowledges that the stumps were installed defectively. I acknowledge that only a relatively small proportion of the stumps have been inspected, and that the precise timing of when each stump commenced corroding is not known. However, I am not satisfied this means the insurer should be required to continue to investigate the claim. The exchanged information enables a decision on coverage to be made. Why is the outcome fair? It would not be fair to require the insurer to further investigate or accept the claim when the exchanged information confirms that the policy does not respond. Supporting information The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. I have reviewed and considered all the information the parties have provided. While the parties have raised several issues in their submissions, I have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we may find that a claim cannot be established.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.