Home / NAB / Determination 12-00-1021759

Determination 12-00-1021759

Progress payments from a construction loan made on allegedly forged authority forms and invoices submitted by a broker

FirmNAB
Decided2025-05-15
ProductCredit · Home loan
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss$4,000
Amount claimed$206,500
SourceAFCA PDF

Summary

The complainant said her broker forged her signature on progress payment documents so the bank paid $206,500 to a builder who did not complete the home. AFCA found the bank liable for the $88,500 Lock up payment, the complainant liable for the Frame payment and for the Fixing payment (interest free), and ordered $4,000 non-financial loss and $5,000 legal costs.

A bank needs a valid mandate to debit an account and red flags should have prompted inquiries at Lock up stage, but the complainant failed to mitigate her loss by not disputing the Lock up payment before the Fixing payment.

Issues

Subjects and remedies

broker or intermediarydigital banking or apphome or building damagelanguage or cultural barriermental healthscamcorrect recordsloan or hardship variationpay compensationpay non financial lossrefund fees or charges

Related

All NAB determinations · Find similar determinations

Text of the determination

Determination | Case number | 12-00-1021759 | Financial firm | National Australia Bank Limited Case number: 12-00-1021759 15 April 2025 Determination overview Complaint On 21 September 2021, the complainant entered a fixed price building contract to construct a new home. On 22 November 2021, the complainant entered an interest-only construction loan contract (loan) with the financial firm (bank). The loan was arranged by a mortgage broker. The complainant also opened a linked transaction account with the bank from which loan repayments were debited (transaction account). The bank drew down the loan and made the following progress payments to the builder (disputed payments) based on signed Progress Payment Authority forms (authority forms) and builder’s invoices submitted by the broker for each of the following stages of construction:  on 28 June 2022, $59,000 paid for Frame Stage (Frame payment)  on 8 July 2022, $88,500 paid for Lock up Stage (Lock up payment), and  on 15 March 2023, $59,000 paid for Fixing Stage (Fixing payment). In fact, the construction did not proceed beyond Frame Stage. The complainant says the bank made the disputed payments without following proper process. She says the broker forged her signature on the authority forms and invoices and emailed these to the bank without her knowledge or consent. The complainant says she should not be held liable for the disputed payments. The complainant also requested non-financial loss compensation of $10,000 and legal costs of $9,807 to be paid by the bank. On 8 October 2024, AFCA’s Senior Dispute Resolution Specialist made a preliminary assessment of the above issues. The preliminary assessment was substantially in favour of the complainant. Both parties rejected the preliminary assessment and made further submissions that have been considered in this determination. AFCA convened a panel consisting of an ombudsman acting as chair, together with a member with experience in the banking industry and a member with experience in consumer claims to consider and determine this complaint. This determination is made by the panel. Issues and key findings Did the bank follow proper process when making the disputed payments? Based on the available information, the panel was satisfied the process followed by the bank when making the disputed payments was consistent with the terms and conditions of the loan. Were the disputed payments authorised by the complainant? The panel was satisfied that, on the balance of probabilities, the complainant authorised the Frame payment, but not the Lock up and Fixing payments. The panel considered there were red flags in the documents submitted at Lock up Stage which should have led the bank to make further inquiries before making the Lock up payment. Did the complainant take reasonable steps to mitigate her loss? Based on the available information the panel was satisfied that the complainant had ample opportunity to dispute the Lock up payment before the Fixing payment was made. The panel considered that by failing to do so, the complainant failed to take reasonable steps to mitigate (or avoid) further loss. What is a fair outcome in this complaint? In the circumstances, the panel considered it fair for:  the complainant to bear liability for the Frame payment in accordance with the terms of the loan  the bank to bear liability for the Lock up payment  the complainant to bear liability for the Fixing payment because this loss could have been avoided if the complainant had taken reasonable steps to mitigate her loss. However, the bank should not charge interest on the Fixing payment  the bank to pay the complainant $4,000 in non-financial loss compensation, and  the bank to pay $5,000 to cover the complainant’s legal costs in bringing this complaint. Why is the outcome fair? The panel accepts the complainant has suffered financial loss and significant distress because most of her building loan funds were paid to the builder but her home has not been built. While the panel empathises with the complainant’s situation, in the circumstances, it would not be fair to hold the bank responsible for all the loss suffered by the complainant. It is fair for the bank to be accountable for the Lock up payment because, in the absence of a valid mandate from the complainant, the bank was not entitled to debit the complainant’s account and there were red flags in the documentation submitted to the bank that should have put it on inquiry. However, the panel considers that it is fair the complainant remain liable for the Fixing payment as the bank would not have made this payment if the complainant had notified the bank in a timely manner that the Lock up payment was unauthorised. It would be unfair, however, for the bank to benefit from having made the Fixing payment without the complainant’s authority by charging interest on this payment. It is also fair in the circumstances for the bank to pay $4,000 to compensate the complainant for non-financial loss and to contribute $5,000 to the legal costs incurred by the complainant in bringing this complaint. Determination This determination is partly in favour of the complainant and partly in favour of the bank. If the complainant accepts this determination, the bank must, within 14 days of acceptance:  reconstruct the loan account to return it to the position it would have been in had the bank not made the Lock up and Fixing payments. The bank should apply all loan repayments made by the complainant to the amount advanced by the bank prior to 8 July 2022  create a new interest free loan account or a sub-account of the loan for the $59,000 paid at Fixing Stage, so that the complainant may repay this amount within the remainder of the term of the existing loan without paying interest, and  pay $9,000 into an account nominated by the complainant, being $4,000 non-financial loss compensation and $5,000 of legal costs paid by the complainant. The complainant remains liable for the balance of the loan following the above reconstruction and for the repayment of the interest free loan or sub-account. If the complainant is in financial difficulty, she should complete a statement of financial position and contact the bank to discuss a repayment arrangement. The parties should work together in good faith to try and come to agreement on a repayment arrangement. If the complainant does not accept the determination, the bank is not required to take any of the steps above and it may continue to exercise the rights it has under the terms of the existing loan. Reasons for determination Did the bank follow proper process when making the disputed payments? Based on the available information, the panel was satisfied the process followed by the bank when making the disputed payments was consistent with the terms and conditions of the loan. The bank did not breach its terms and conditions The complainant’s representative says the bank failed to follow proper process because:  it made the disputed payments based on documents emailed by the broker without contacting the complainant  it did not perform an inspection to confirm each stage of construction before making the disputed payments  the bank paid the Frame Stage progress claim even though the framing did not comply with building regulations, and  it accepted a builder’s invoice which was not marked as a tax invoice, contrary to the “Your Guide to Building and Renovating” (Guide) published by the bank. The bank says it acted prudently and diligently in making the disputed payments and was entitled to rely on the documents emailed by the broker. The bank has submitted the following information to AFCA:  a Personal Consent Form dated 18 October 2021 signed by the complainant at the time of loan application. By signing this form the complainant agreed the broker was her agent and authorised the bank to exchange information with the broker in relation to the loan  the terms and conditions which applied to the loan. The following clauses are relevant to building loans. These are copied in full in section 3.3 of this determination but in summary provide: > clause 5.1 states the bank is not responsible for the supervision of the building work even though it may inspect the building > clause 5.2 states the bank need not lend any part of the building loan until it has received any document or certificate that it requires in a form satisfactory to the bank, and until it is satisfied with any inspection that it may require.  the Guide, which provides more detail about the building loan process to the bank’s customers. Relevantly the Guide states that: > for building undertaken by registered builders, the bank will conduct an inspection when the first progress payment is requested and when the final progress payment is requested > inspection of the construction is for the bank’s own internal purposes > to make funds available, the bank requires a completed and signed progress claim and copies of relevant invoices or receipts > the invoices should be on the builder’s letterhead and include the builder’s ABN, a description of any change to payment amounts previously agreed, the builder’s preferred payment method, the GST payable and be clearly marked as a tax invoice  a record showing the bank received an inspection report dated 27 June 2022 which confirmed framing was completed before the Frame payment was made, and  signed authority forms and builder’s invoices for each of the three disputed payments. Based on the available information, the bank:  was entitled to act on instructions received from the broker who was the complainant’s agent, except where any red flags were present that indicated that further inquiries should be made to confirm the authenticity of those instructions  was not required to inspect the building before making the Lock up and Fixing payments  was not responsible for identifying defects in the frame when it performed an inspection before making the Frame payment, and  was entitled under the Terms and Conditions to make a progress payment if it received such documents as it required and considered satisfactory. The purpose of the Guide was to inform borrowers of the documents the bank would require before making a progress payment. However, the bank was entitled to accept an invoice that did not meet all the requirements stipulated in the Guide, including an invoice that did not clearly state that it was a tax invoice, if that was satisfactory to the bank. The panel did not consider the bank acted unreasonably in accepting an invoice that did not clearly state that it was a tax invoice. The panel was satisfied the bank acted in line with the terms and conditions of the loan and substantially followed the process it set out in the Guide. This does not however mean the bank had received and acted on valid instructions from the complainant or that the disputed payments had been authorised by the complainant. Were the disputed payments authorised by the complainant? The panel was satisfied that, on the balance of probabilities, the complainant authorised the Frame payment, but not the Lock up and Fixing payments. The panel considered there were red flags in the documents submitted at Lock up Stage which should have led the bank to make further inquiries before making the Lock up payment. The complainant says she did not authorise the disputed payments The complainant denies signing the authority forms and builder’s invoices for the disputed payments. She says that the broker, conspiring with the builder, forged her signature on those documents then sent them to the bank without her knowledge or consent. The complainant says she would not have authorised the disputed payments because:  on 25 July 2022, she arranged an independent building inspection which led to a ‘Written Direction To Fix Building Work’ (direction) being issued against the builder  the builder has not complied with the direction, the dispute with the builder has not been resolved and the construction has not progressed beyond framing  on 26 June 2023, after the building contract’s stipulated 265-day building period had passed, the complainant through her solicitors: > gave the builder a written ‘Notice of Intention to Terminate the Contract’ > terminated the building contract, and > lodged a complaint with the Domestic Building Dispute Resolution Victoria. The complainant says the broker introduced the builder to the complainant and neither the builder nor the broker can be contacted. The complainant believes they have left the country. The building firm that previously employed the builder has denied knowing about the building contract with the complainant and does not accept liability for any work undertaken by the builder. In August 2023, the complainant lodged a written complaint with Victoria Police, naming the broker and the builder as co-conspirators in a joint enterprise to defraud her. The bank must have a valid mandate to debit a customer’s account The bank says that it was entitled to rely on the payment instructions provided by the broker given the process that applied to the authorisation of progress payments from building loans. The bank says the documents received from the broker passed verification as the signatures on them were consistent with the complainant’s specimen signature on its file. It is a fundamental principle of banking law that a bank should act on a valid mandate from their customer when debiting the customer’s account. This applies irrespective of how convincing a forged mandate may be, or if the bank’s processes could not have identified the forgery. It is a matter for the bank to introduce systems and processes that are sufficient to verify that any payment instructions it receives are valid. If the process adopted by the bank for the authorisation of payments under its building loans is susceptible to fraud, this is a risk borne by the bank not by its customers. In this case, the bank made large payments to the builder based on its assessment of the validity of the complainant’s signature in the authority forms and invoices emailed by the broker. The panel noted that, in circumstances where customers have access to mobile banking, it was open to the bank to establish a more secure process for the authentication of payments. The bank’s decision to rely on signatures for its building loans process was a matter for the bank. It is not possible to determine whether the signatures are genuine Where there is a serious question about the authenticity of signatures, AFCA seeks analysis from an independent forensic handwriting expert. The investigating AFCA case workers sent originals of the complainant’s signature plus the emailed documents received from the broker to three independent handwriting experts for examination. Due to the style and type of signature and the fact the documents were emailed to the bank, each examination was inconclusive. Each of the three experts told AFCA that they could not determine the authenticity or otherwise of the signatures on the copy documents. To determine whether the signatures were forged, the experts needed to carry out a full forensic analysis of the original documents signed by the complainant. The bank’s process did not require the broker to submit original signed documents and these are not available for examination. In the absence of a full forensic analysis of the original signed documents, the panel weighed up the remaining information to determine on the balance of probabilities whether the complainant authorised each of the disputed payments. The bank’s supporting arguments were contested by the complainant In rejecting AFCA’s preliminary assessment of the complaint, the bank made further submissions in support of its position. The bank says that:  it notified the complainant by SMS immediately after processing each disputed payment. The bank provided records of three SMS messages sent to the complainant’s mobile phone number, each of which was in the following form: Your construction claim for [variously “Frame”, “Lock up”, “Fixing”] has now been paid. Funds may take 1-2 business days to appear in the nominated account. Kind regards, [bank] Broker Construction Team  the complainant accessed her loan account using her internet banking facility multiple times during the relevant period. The bank provided internet banking logs of online access to the complainant’s accounts. The bank says this information demonstrates the complainant must have been aware of the disputed payments soon after they were made but did not raise any concerns with the bank. This, the bank says, shows that she authorised the disputed payments. In turn, the complainant strenuously denies becoming aware of the disputed payments before 14 July 2023. She says she promptly contacted the bank as soon as she became aware of the disputed payments. The complainant initially denied receiving any of the SMS messages notifying her of the disputed payments but subsequently identified one of the messages on her device. The complainant has admitted to receiving the last of the messages, notifying her that the claim for Fixing had been paid on 15 March 2023. The complainant maintains that she did not receive the two previous SMS messages. The complainant says she rarely accessed internet banking, let alone the number of times alleged by the bank, but instead regularly obtained updates at her local branch. When asked to explain the access recorded in the bank’s internet banking logs, the complainant said the broker had been working with the builder to defraud her and it was likely the broker accessed her account. The complainant also said she suspected that one of the bank’s branch staff may have been involved in the fraud. AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider available documents, the recollections of the parties, and all relevant circumstances. We give more weight to contemporaneous documentary information. If there are no relevant documents, we will decide what is most likely to have occurred based on the information provided to us. If there are conflicting recollections and these are evenly weighted, we may find that a claim (or a defence to a claim) cannot be established. The complainant most likely received SMS messages from the bank Having weighed up all the available information, the panel was satisfied that, more likely than not, the complainant received the bank’s SMS messages following each of the disputed payments. This is because:  the bank’s contemporaneous records show the bank sent all three messages in the same format to the same phone number, which is the complainant’s number  the complainant has confirmed she received the last of these messages on 15 March 2023  the complainant did not act on the last message for about a month and initially said she had not received it  it is more likely than not the complainant received previous similar messages but did not review/act on them and these have since been deleted. While the panel accepted that SMS messages were most likely received by the complainant after each of the disputed payments were made, the panel did not regard this as proof the complainant authorised all the disputed payments. The panel considered the complainant may not have understood the importance of the SMS messages she received or deleted them without reading them first. The panel considered the following in coming to this view:  the SMS messages were sent after the disputed payments were made  they did not require any response or action by the complainant  the messages were sent from a mobile phone number that was not branded and which was therefore not recognisable as the bank’s number. The complainant may not have realised they were important messages from the bank  the complainant’s legal representative says the complainant had some difficulties with the English language. The panel noted the broker and builder spoke the same language as the complainant  neither the terms and conditions nor the Guide mentioned the complainant would receive SMS messages when progress payments were made so the complainant would not have been looking out for them. The SMS messages were considered by the panel in determining whether the complainant took reasonable steps to mitigate her loss in section 2.2 below. The complainant most likely accessed her account online Having weighed up all the available information, the panel was satisfied that, more likely than not, the complainant used her internet banking facility to view her loan account during the relevant period. This is because:  when entering the loan, the complainant opted to view her account statements online instead of receiving paper statements  the bank’s contemporaneous records show the loan account was accessed online multiple times during the relevant period  the only action taken online in relation to the loan was to view account information and extract transaction data  the complainant has not explained how the broker knew her online password needed to access her online banking facility  the online banking logs show that at least some of the access required additional one-time passcodes to be entered and these would have been sent to the complainant’s phone number  there was no need for the broker to access the complainant’s account to perpetrate the fraud as payment instructions were given by email and the bank made the disputed payments directly to the broker  the loan account information accessed would have been known to the broker without logging into the complainant’s online banking facility given he managed the loan application and progress payments on her behalf  online access would have afforded the broker an opportunity to move funds from the complainant’s transaction account. The complainant has not raised any concerns about unauthorised transactions from that account  there is insufficient information to support a finding that branch staff colluded with the broker or builder to assist them to perpetuate the fraud. Based on the available information, the panel was satisfied on the balance of probabilities that the complainant learned about the unauthorised payments some time before she reported these to the bank on 14 July 2023. However, this does not necessarily mean the complainant authorised the disputed payments. The panel considered the impact of the complainant’s access to her online banking in relation to each disputed payment below. The complainant most likely authorised the Frame payment Having weighed up all the available information, the panel was satisfied that more likely than not, the complainant authorised the payment of $59,000 on 28 June 2022 in relation to the Frame Stage. The reasons for the panel’s view are discussed below. Based on the available information, on 26 June 2022, the bank received from the broker an authority form dated 21 June 2022 and a builder’s invoice dated 13 June 2022 in relation to the Frame Stage progress claim. Both appear to have been signed by the complainant. The bank sent a SMS message to the complainant advising it had received the claim and would order an inspection to confirm the status of construction. The bank completed its inspection on 27 June 2022 and made the progress payment on 28 June 2022. The bank confirmed the payment was made by SMS message that day. It was not until 25 July 2022, about a month after the Frame payment was made, that an independent building inspection identified flaws in the construction of the frame and issued a Written Direction to Fix Building Work to the builder. There is insufficient information to show the complainant was aware of a problem with the construction of the frame when the progress claim documents were submitted to the bank. In these circumstances, the panel was not satisfied that the complainant did not sign the documents submitted in relation to the Frame payment or that she did not authorise for these documents to be submitted to the bank. The panel noted the complainant did not raise any concerns with the bank about the Frame payment until a year later. While this does not necessarily mean the complainant had signed the documents submitted by the broker or authorised the payment, the complainant’s conduct was consistent with the panel’s conclusion that the Frame payment had most likely been authorised by the complainant. The complainant most likely did not authorise the Lock up payment On 4 July 2022, the bank received the signed authority form and signed builder’s invoice for the Lock Up Stage payment. Both documents are dated 30 June 2022, which is 4 days after the signed authority form for the Frame payment. There is a substantial amount of work between Frame and Lock up Stages, as reflected by the larger amount payable for Lock up than for any other construction stage. It is very unlikely that this work could have been completed in four days. The bank’s online banking log shows the complainant accessed online banking on six days between 20 July and 10 November 2022 but did not perform any transactions online. The log does not, however, show that the complainant accessed her loan account rather than her transaction account on these days. It is not until 2 December 2022, almost six months after the Lock up payment, that the online banking logs show online access to the complainant’s loan account. The relevant entry reads “Account details extraction successful” followed by the loan account number. The bank says that the balance of the loan account would have been visible to the complainant when she first logged onto online banking to access her transaction account with the bank. The bank also says the complainant would have seen higher interest repayments from her transaction account when the outstanding balance of the loan increased. The complainant had no obligation to look at her loan account and it is possible that she did not notice the increased balance or the increased repayments if she was using her online facility for an unrelated purpose. The panel was not satisfied based on the information submitted, that the complainant was aware that the Lock up payment had been made before 2 December 2022. While the available information is not conclusive, on the balance of probabilities, the panel considers the complainant most likely would not have authorised the payment of $88,500 to the builder in relation to the Lock up Stage. Given the complainant had only authorised the Frame payment a few days earlier, she would have been aware that construction could not have progressed significantly beyond framing. There is insufficient information to confirm the complainant became aware of the Lock up payment shortly after it was made. There were red flags present to put the bank on inquiry It is possible the complainant had signed blank forms if she had been requested to do so by the broker to avoid the need for further meetings, and the broker subsequently dated the documents and submitted them to the bank without her knowledge and consent. The date on both the authority form and the invoice submitted for the Lock up Stage appears to have been handwritten by the same person. This differs from the Frame Stage documents, where dates were entered electronically in different typefaces, consistent with each of the documents. There is no information to substantiate that this is what happened, and the complainant strenuously denies having signed the documents submitted by the broker. Even if the complainant’s signatures on the authority form and builder’s invoice dated 30 June 2022 were genuine signatures of the complainant (and the panel is unable to make that finding), the panel considers the unrealistically short period of construction indicated by the documents should have been a red flag for the bank to undertake additional inquiries. The bank has submitted that its inspection report of 27 July 2022 confirmed the frame had been erected and included a photograph of the frame. This report would have shown the construction to have only reached Frame Stage as at 27 June 2022. The broker submitted documents to the bank confirming completion of construction to Lock up Stage which were dated only 3 days after the bank’s inspection of the building. In circumstances where red flags were present in information submitted by the complainant’s agent, the bank should have made further inquiries to ascertain that the agent was acting on proper authority from the complainant and the complainant had in fact authorised the Lock up payment. The panel considered the bank’s failure to query the documents submitted to it before making the Lock up payment has contributed to the fraud perpetrated on the complainant. The complainant most likely did not authorise the Fixing payment On 10 February 2023, the bank emailed the broker requesting information about the status of the construction as the loan file had been dormant for over 11 months. On 22 February 2023, the bank received an email from the broker stating “After speaking with the client, the builder is finalising the fixing stage. [Bank] should receive fixing stage invoice from the builder soon”. On 13 March 2023, the bank received a signed authority form and signed builder’s invoice for the Fixing Stage, both dated 13 March 2023. The dates were added to the documents in the same handwriting as in the Lock up Stage documents. On 15 March 2023, the bank paid $59,000 to the builder’s account for the Fixing Stage and sent a SMS message to advise the complainant that Fixing had been paid. The bank notified the broker that as the next stage would be a final payment, the bank would require an occupancy permit and home insurance certificate of currency and would conduct a property inspection. The bank’s notes show that on 6 June 2023, the complainant called the bank to request a copy of the building contract. The online log shows that after the Fixing payment, the complainant first accessed the loan account online on 20 June 2023. Documents submitted by the complainant show that on 26 June 2023, a lawyer acting for the complainant, gave the builder a Notice of Direction to Terminate Contract. The complainant subsequently accessed the loan account online on 28 June, 1 July and 3 July, each time extracting details from the loan account, before notifying the bank that funds were missing from her account on 14 July 2023. Based on the available information, the panel was satisfied on the balance of probabilities, that given the complainant’s dispute with the builder and the fact the construction had not progressed beyond Frame Stage, the complainant would not have authorised the payment of $59,000 to the builder for completion of the Fixing Stage on 15 March 2023. Based on the available information, the panel considered it more likely than not, that the complainant became aware that the Fixing payment was made on 20 June 2023, the date the online logs first record “Account details extracted: [loan account number]” after the Fixing payment was made. Although the complainant did not advise the bank that this payment was unauthorised until 14 July 2023, the panel did not consider this necessarily meant the complainant authorised the Fixing payment. It is clear that during this period, the complainant consulted a lawyer and took steps against the builder after she became aware of the Fixing payment. The panel took the complainant’s delay in notifying the bank of the disputed payments into consideration when determining whether the complainant took sufficient steps to mitigate her loss, as discussed in section 2.2 below. Did the complainant take reasonable steps to mitigate her loss? Based on the available information the panel was satisfied that the complainant had ample opportunity to dispute the Lock up payment before the Fixing payment was made. The panel considered that by failing to do so, the complainant failed to take reasonable steps to mitigate (or avoid) further loss. The complainant had the opportunity to mitigate her loss Where a financial firm makes an error which may cause loss, if a customer is aware of the error, they are expected to take reasonable steps to try to avoid or mitigate the resulting loss. Where the complainant’s inaction has led to avoidable loss, it is appropriate to adjust compensation based on the assumption that reasonable mitigative measures were taken. Generally, bank customers are expected to contact the bank as soon as they become aware of an unauthorised transaction on their account. The bank says that it could have avoided or reduced the loss if the complainant:  alerted the bank to the disputed payments when she received the SMS messages, because the bank would have had the opportunity to recall the funds, and/or  alerted the bank to the first disputed payment in a timely manner, because the bank would not have made any further progress payments based on instructions received from the broker. The panel accepted that the complainant had the opportunity to mitigate some of her loss but did not take reasonable steps to do so. The reasons for the panel’s view are set out in more detail below. The complainant may not have been able to avoid loss at Lock up Stage Having weighed up all the available information, the panel was of the view that the complainant had little opportunity to mitigate the loss of the disputed payment made at Lock up Stage. This is because:  the panel found that the Frame payment was authorised by the complainant, and she had no reason to suspect the broker would make an unauthorised progress payment request several days later  even though the panel was satisfied the complainant likely received a SMS message confirming the Lock up payment was made, the panel was of the view the complainant could have easily missed this message or failed to appreciate its importance for the reasons set out in section 2.1 above  based on the bank’s log, the complainant did not access the loan account after the Lock up payment was made until 2 December 2022. While it may have been possible for the complainant to see the higher loan account balance when she logged onto online banking to access her transaction account, as discussed in section 2.1 above, she may not have noticed this information or noticed that higher repayments were being drawn from her transaction account  however, the panel was satisfied the complainant either did identify, or should reasonably have identified, that a $88,500 payment had been made without her authority when she viewed the loan account online on 2 December 2022  even if the complainant had disputed the Lock up payment with the bank on 2 December 2022, however, there is insufficient information to show the bank could have successfully recalled these funds five months after the disputed payment was made. The complainant did not take reasonable steps to avoid loss at Fixing Stage Having weighed up all the available information, the panel was satisfied the complainant had failed to take reasonable steps to mitigate her loss at Fixing Stage. This is because:  the bank’s logs show the complainant logged onto online banking and extracted account details from her loan account on 2 December 2022  the panel was satisfied that, even if the complainant had missed the SMS sent to her following the Lock up payment and not paid attention to information about the loan visible when she logged into online banking to view her transaction account, the complainant should reasonably have been aware from 2 December 2022 that $88,500 was paid to the builder without her authority on 8 July 2022. The complainant did not advise the bank of the unauthorised payment until July 2023, a month after the next Fixing payment was made  the panel was satisfied that had the complainant advised the bank that the Lock up payment was unauthorised prior to 15 March 2023, or told the bank that she was in dispute with the builder and construction had stalled at Frame Stage, the bank would not have paid $59,000 to the builder based on documents submitted by the broker for Fixing Stage. In the circumstances, the panel considered the complainant’s failure to promptly inform the bank of unauthorised payments from her loan account resulted in a loss of $59,000 which could have been avoided. What is a fair outcome for this complaint? In the circumstances, the panel considered it fair for:  the complainant to bear liability for the Frame payment in accordance with the terms of the loan  the bank to bear liability for the Lock up payment  the complainant to bear liability for the Fixing payment because this loss could have been avoided if the complainant had taken reasonable steps to mitigate her loss. However, the bank should not charge interest on the Fixing payment  the bank to pay the complainant $4,000 in non-financial loss compensation, and  the bank to pay $5,000 to cover the complainant’s legal costs in bringing this complaint. It is fair for the financial loss to be apportioned between the parties As discussed above, the panel was satisfied that on the balance of probabilities, the Lock up payment was most likely not authorised by the complainant. In addition, the panel considered the documents emailed by the builder should have led the bank to make further inquiries before making the Lock up payment. While the panel also considered that on the balance of probabilities, the Fixing payment was also not authorised by the complainant, the panel found that had the complainant contacted the bank in a timely manner to advise that the Lock up payment had not been authorised or that she was in dispute with the builder and did not wish to make any further payments under the building contract, the loss of $59,000 at Fixing Stage would likely have been avoided. In these circumstances the panel considered that it was fair to apportion the loss between the parties so that the bank bear liability for the $88,500 Lock up payment and the complainant remain liable for the $59,000 Fixing payment. The panel considered that it would not, however, be fair for the bank to benefit by charging interest on the Fixing payment. The panel considered that it would be fair for the bank to:  reconstruct the loan account to return it to the position it would have been in had the bank not made the Lock up and Fixing payments and apply all loan repayments made by the complainant to the amount advanced by the bank prior to 8 July 2022  create a new interest free loan account or a sub-account of the loan for the $59,000 paid at Fixing Stage, so that the complainant may repay this amount within the remainder of the term of the existing loan without paying interest. The bank is not liable for loss associated with the building activity The complainant’s home has remained at the framing stage for several years and she says all the framing will now need to be pulled down and rebuilt. She also says the cost of completing the build has substantially increased since the complainant entered the fixed price building contract with the builder in 2021. The complainant’s representative says AFCA should take these matters into consideration when awarding compensation to the complainant. The panel was of the view that the bank did not contribute to any loss suffered by the complainant in connection with the Frame Stage. Any loss suffered by the complainant due to faulty construction, failure to complete the building or the increased cost of building is a civil matter between the complainant and the builder and not the bank’s responsibility. The complainant’s representative also says the complainant has suffered financial hardship as she was paying rent and making loan repayments at the same time throughout the relevant period. The complainant has four children and pays school fees for all of them. If following the adjustment of the loan in line with this determination the complainant still has difficulty making loan repayments, she should complete a statement of financial position and discuss with the bank whether a repayment arrangement is possible until the complainant’s financial difficulty is resolved. The bank should pay non-financial loss compensation and legal costs Under AFCA’s Rule D.4, in this case AFCA can award up to a maximum of $5,400 non-financial loss compensation. AFCA takes a conservative approach to awarding compensation for non-financial loss caused by an error of the financial firm. We do not award non-financial loss compensation merely because the complainant has suffered some inconvenience and anxiety. We expect complainants to be moderately robust and to bear the normal degree of inconvenience experienced when a problem occurs and to take reasonable steps to manage the situation. The panel acknowledged that the complainant suffered from mental health problems as a result of the unauthorised payments. In the circumstances, the panel considered it fair the bank pay non-financial loss compensation of $4,000 to the complainant for the stress and inconvenience suffered. This amount balances the relative contributions of the bank and the complainant to the complainant’s situation. Under AFCA’s Rule D.5, AFCA can require a financial firm to contribute up to $5,000 to the legal or other professional costs incurred by the complainant in the course of the complaint. The panel was satisfied that this complaint raised complex issues and it was reasonable for the complainant to obtain assistance from a legal representative in order to adequately present her claim. In the circumstances, the panel considered it fair for the bank to contribute $5,000 to the complainant’s legal costs. The complainant’s legal representative has submitted invoices and receipts that show the complainant paid legal costs in excess of this amount in relation to her complaint with AFCA. These documents have been shared with the bank. Why is the outcome fair? The panel accepts the complainant has suffered financial loss and significant distress because most of her building loan funds were paid to the builder but her home has not been built. While the panel empathises with the complainant’s situation, in the circumstances, it would not be fair to hold the bank responsible for all the loss suffered by the complainant. It is fair for the bank to be accountable for the Lock up payment because, in the absence of a valid mandate from the complainant, the bank was not entitled to debit the complainant’s account and there were red flags in the documentation submitted to the bank that should have put it on inquiry. However, the panel considers it is fair the complainant remain liable for the Fixing payment as the bank would not have made this payment if the complainant had notified the bank in a timely manner that the Lock up payment was unauthorised. It would be unfair, however, for the bank to benefit from having made the Fixing payment without the complainant’s authority by charging interest on this payment. It is also fair in the circumstances for the bank to pay $4,000 to compensate the complainant for non-financial loss and to contribute $5,000 to the legal costs incurred by the complainant in bringing this complaint. Supporting information The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established. Building contract stage progress payment schedule | Stage | Percent | Amount | Date Paid | Base Stage | 15% | $44,250 | 2 May 2022 | *Frame Stage | 20% | $59,000 | 28 June 2022 | *Lock-up Stage | 30% | $88,500 | 8 July 2022 | *Fixing Stage | 20% | $59,000 | 15 March 2023 | Completion | 10% | $29,500 | Never paid | *Total disputed payments | $206,500 | Credit Contract General Terms 5.1 g) We are not responsible for the supervision of the building or any aspect of the building work, even though we may approve an alteration to or inspect the building. 5.2 … we need not lend any part of the home loan where building loan conditions apply until: (a) you have contributed any money towards the cost of building that you have agreed to contribute and which is stated in your application or as otherwise agreed; (b) we have received any document or certificate that we require and it is satisfactory to us (including council approved plans and permits, a request from you for the drawing and a certificate from your architect or builder showing the cost of works covered by the certificate); (c) we are satisfied with any inspection that we may carry out or require; and (d) for the final advance, we have received a certificate of occupancy (or equivalent).

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.