Home / Hollard / Determination 12-00-1018655

Determination 12-00-1018655

Denial of flood damage claim to retaining wall

FirmHollard
Decided2024-11-08
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss—
Amount claimed$231,944
SourceAFCA PDF

Summary

The insurer declined a flood damage claim for a retaining wall on the basis of an exclusion for structural defect or faulty design. AFCA found the flood caused the damage and the exclusion not established, and ordered the insurer to appoint an assessor and settle the claim under its policy terms.

The insurer did not prove on the balance of probabilities that an inherent defect or faulty design was the proximate cause of the loss, rather than the flood.

Issues

Subjects and remedies

reassess claim

Related

All Hollard determinations · Find similar determinations

Text of the determination

Determination | Case number | 12-00-1018655 | Financial firm | The Hollard Insurance Company Pty Ltd 12-00-1018655 31 October 2024 1 Determination overview Complaint The complainant held a comprehensive home building insurance policy with the financial firm (insurer) from 19 June 2020 to 19 June 2021. The complainant lodged a claim for flood damage to his property from a flood event in March 2021. The insurer partially accepted the claim but excluded the jetty and retaining wall from the settlement. The insurer later reviewed the issue of the jetty and made an offer of settlement. AFCA wrote to both parties on 15 October 2024 confirming the settlement offer and noting a Determination would proceed on the retaining wall alone. The parties were invited to contact AFCA by a particular date if this was incorrect. The insurer contacted the AFCA stating it was “…happy to overturn the liability decision regarding the pontoon/jetty” but it had not received quantum documents for settlement. Given this, the determination will address the retaining wall alone. The insurer has declined the claim for the retaining wall on the basis there was no identifiable flood damage, and the retaining wall was not compliant with applicable building codes at the time of construction. The complainant disagrees with the insurer’s decision and seeks settlement of $231,944 plus GST, covering both the jetty and retaining wall’s reconstruction. Issues and key findings Has the complainant established a claim under the policy cover? Yes. Based on the exchange information, the complainant has established that it is more likely than not that a flood event damaged the retaining wall. Has the insurer established that the retaining wall claim is excluded? No. The insurer has not established that the excluded event caused the damage to the retaining wall rather than the flood event. Why is the outcome fair? The outcome is fair as it considers relevant law, policy terms and expert opinions regarding the cause of the damage. The complainant has established a claim covered by the policy and the insurer has not established that a policy exclusion applies to refuse the claim. Determination Within 30 days of the insurer receiving notification of the complainant’s acceptance of this determination, the insurer is required to appoint an assessor for an assessment of the costs required to repair or replace the retaining wall. The insurer is to then settle the claim for the retaining wall in line with its policy terms and conditions. Reasons for determination Has the complainant established a claim under the policy cover? Yes. Based on the exchange information, the complainant has established that it is more likely than not that a flood event damaged the retaining wall. Complainant has the onus to establish a valid claim The complainant has the onus of establishing he suffered a loss from an event covered by the policy. If the complainant can establish that he suffered a claimable loss, the onus shifts to the insurer to show, on balance: it is entitled to rely on an exclusion under the policy, or it is otherwise entitled to decline the claim. For both the complainant and the insurer, the onus of proof is on the balance of probabilities (that is, it is more likely than not). The policy provides accidental damage cover which includes flood events The policy consists of the product disclosure statement (PDS) and the certificate of insurance. The policy covers sudden and unexpected accidental loss or damage subject to any exclusions or limitations to cover. The cover further specifies that retaining walls are covered under the definition of buildings. The policy definitions for accidental damage cover is set out below: WHAT YOU ARE INSURED FOR Accidental damage cover When you insure your building and/or your contents under this policy you will be covered for sudden and unexpected accidental loss or damage that occurs during the period of insurance and at the location up to the amount shown on your Insurance Certificate. There are exclusions that apply to certain events or losses and these are detailed under ‘When we will not pay a claim for loss or damage under the policy’. These limitations and exclusions may restrict the amount payable in the event of a claim or alternatively they may prevent a claim from being paid at all. The complainant has established a valid claim There is no dispute between the parties that a flood occurred on 28 March 2021, which severely affected the Hawksbury River area where the complainant’s property is situated. There are aerial photographs showing the flood inundation at the insured location. The complainant has provided a quotation form EV dated 29 May 2021 which states that: On inspection of the river bank stone walls it is noted that these have been moved with the flood waters and caused erosion in, around and behind the walls. This was evident when the sand dumped on the ground areas from the flood, was removed to expose the grass and rock face. .. There has been movement and de stabilization of the rock wall either side of the boat ramp. The complainant has further provided an expert engineering report from ‘CS’ which provides the following: The downstream impact of the Warragamba Dam Overspill and tributary catchment flows after the 21st of March 2021, had devastating damage and destruction to properties aligning the Hawkesbury River and the subject property was severely impacted by this flooding event, amounting to the loss of the jetty, severe damage to the reinforced concrete wall base, timber log and dry stacked rock retaining wall, which had been built many years ago to protect the riverbank from normal “speed boat wash” and not built to sustain the impact forces caused by this flooding event. I am therefore satisfied that the complainant has established that damage occurred to his retaining wall arising out of a flood event which is covered under the accidental damage cover of the policy. The insurer does not deny that a flood occurred but denies that it was the cause of loss to the retaining wall. Has the insurer established that the retaining wall claim is excluded? No. The insurer has not established that the excluded event caused the damage to the retaining wall rather than the flood event. The insurer relies on an exclusion relating to structural defect or faulty design The insurer relies on its engineering expert SW who states that the retaining wall has not been built to the requirements of the applicable Australian Standards, such as AS4678:2002. The insurer’s position is that the following exclusion applies: You are not covered for any loss or damage caused by or resulting from, or the costs incurred from or of: .. - Inherent defects, structural faults, faulty workmanship or faulty design; .. Accordingly, if the insurer can establish that the damage was caused by or resulting from inherent defects, structural faults, faulty workmanship or faulty design rather than flood then the insurer would not be liable to make payment for damage which arose from the excluded cause of damage. The retaining wall is comprised of different sections The insurer’s engineering expert, SW, suggests that based on their inspection they did not observe excessive movement or rotation within the retaining wall to be considered resultant damage from the flood event. However, SW did note scouring and soil erosion about the front of the sandstone block seawalls (retaining wall) on either side of the boat ramp. In contrast, the complainant’s expert engineer CS describes the damage as: ….severe damage to the reinforced concrete wall base, timber log and dry stacked rock retaining wall, which had been built many years ago to protect the riverbank from normal “speed boat wash” and not built to sustain the impact forces caused by this flooding event CS also refers to the retaining wall and dry stacked rock wall separately. CS further notes that the concrete base is beyond repair. The difference in opinions may be explained by SW who states: From our inspection, we reaffirm that the retaining wall in question is a dry stacked retaining wall constructed over a concrete base and the timber retaining wall referenced by [CS] has been removed in most part with a section remained (sic) along the boat ramp which in our opinion is a redundant system considering the stone retaining wall has extended behind the timber retaining wall section. Based on the information provided, the overall retaining wall structure appears to be composed of a concrete base, dry stacked rock and some timber components. The original timber retaining wall was replaced with the dry stacked rock wall, but timber is visible in photographs of the damage and noted by CS. SW has focused on the rock portion of the wall on the basis that the rock or stone wall extends beyond the timber retaining wall section and the timber section is redundant. SW is of the opinion that the dry stacked rock is functioning as the retaining system and was constructed in 2013. SW’s latest report does acknowledge that in January 2010 Nearmaps showed the seawall construction prior to the increase in height through the dry stack stone wall. The original seawall, based on image results obtained by SW, was constructed between 2005 and 2010 and would be required to comply with AS4678-2002 earth retaining structures and the local council’s development control plan 2002 (DCP). There appears to be general agreement between SW and CS that the relevant retaining wall(s) has been subject to a series of improvements or alterations over time. The proximate cause of the damage must be determined In a claim under a general insurance policy, the term ‘proximate cause’ is used to describe whether an event is the cause of the loss or damage Damage can have more than one cause. When deciding whether the policy responds, I need to identify what the proximate cause of the damage was. This is a question of fact depending on the circumstances. The proximate cause is not necessarily the first or last or the sole cause of the loss. It is the effective, dominant or operative cause of the loss. The proximate cause(s) must be identified and determined in assessing whether the exclusion applies. The exclusion has not been established The insurer relies on their expert engineer, SW, who provided the following information: …. considering the effects of flood and scouring should have been included within the design and construction of the seawall to which in our professional opinion the current dry stacked retaining wall is inadequate and therefore non-compliant with AS 4678 which has been in effect at the time of construction. SW provided the following observations to conclude that the wall was not constructed to the required Australian Standards: there was evidence of scouring in front of the retaining walls due to erosion of backfill from behind the walls, which was evidence of the omission of geofabric which is installed between the wall and backfill interface as an erosion preventative measure in accordance with AS 4678:2002 the sandstone blocks were poorly stacked on top of each other with limited surface bondage between the adjacent blocks to resist long term sliding resultant from lateral earth pressure the seawall walls are a “gravity” based system retaining wall whereby the capacity to resist retaining pressures and overturning is relative to the self-weight of the wall (sandstone blocks), height and width of the base from review of the retaining wall design and construction, the retaining walls have insufficient structural capacity to withstand the imposed long-term loading from soil and flood water in accordance with AS 4678:2002. As noted above, both EV and CS believe the stone wall had been moved with the flood waters and that flood waters had caused erosion in, around, and behind the walls. CS also specifically references damage to the base of the wall, stating photographs: …clearly show the base of the wall has collapsed, due to the overloading by many tonnes of washed-up sand/debris during the first impact of the flood event. Further, CS states the method of construction for the dry stacked sandstone boulder component was to allow for tidal rise and fall, and to protect the sand embankment behind from collapse by allowing the water from passing speed boats (wave wash) to enter and exit from these open pores. It was not to be mortar filled, as assumed by SW in concluding it was a non-compliant wall. CS does agree that any reconstruction ‘like for like’ would not be to a level as imposed by AS4678-2002 unless the insured is prepared to pay additional monies. On 4 February 2024, EV gave an updated quotation that stated It is now noted that the rock wall has gone all together in this time since the previous quote There is no commentary on whether the rock wall collapsed or was removed. The complainant further relies on The Hawkesbury-Nepean River 2021 Flood Review – Final Report dated December 2021 to demonstrate the flood event had unusual factors (Flood Report). The Flood Report shows that there was prior flooding to the Hawkesbury River in 2020 but not to the same flood depth as March 2021. The 2021 flood was unique in that it had a double peak in upstream areas, and this translated to a long duration flood in downstream areas. The long duration is considered a likely causative factor in the extensive erosion of riverbanks. Further, the report records photographs between Windsor Bridge and Cattai Creek (which is in the locale of the insured premises) to demonstrate the erosion of the riverbank. The report notes: The images and inspection indicate that erosion was extensive, damaging bank protection works, farm pumps, and caravan parks. Rotational (or circular) slumps were observed to be a common mode of bank failure. This type of gravitational failure is conceptualised in Figure 21. One likely cause of this erosion was the long duration of this flood in the Richmond/Windsor floodplain and the lower Hawkesbury (Figure 18). This meant that soils were saturated for long periods and collapsed under the weight The photographs show substantial riverbank collapse as well as road and bridge collapse. I particularly note that the flood managed to cause damage to bank protection works. The complainant has further criticised SW for not addressing the flood impacts and for not specifically stating the cause of the loss viewed to the retaining wall. The complainant has highlighted that SW only states that the flood event is not the proximate cause of the damage to the subject seawall but never says what the proximate cause is. I accept that the dry stacked rock portion of the wall did not contain construction elements that it should have to be fully compliant with the Australian Standards, such as geofabric. However, there is no explanation as to why, without any the impact from the flood water, the rocks may have experienced rotation and erosion. An explanation regarding this aspect was important, particularly in light of the Flood Report, in demonstrating the damage arose from an excluded cause of loss. Further, whilst there is some assertion that the concrete base of the wall needed to comply with the same standard as the dry stacked rock portion of the wall, there is no explanation as to why this portion does not comply. I have difficulty accepting SW’s assertion that only the rocks are acting as a retaining wall from a functional perspective given SW also describes the concrete base as the original seawall. SW’s most recent report states: …landscape works completed at the subject property involved the modification and increase of the seawall height through construction of a new dry stack stone wall above original concrete seawall… There is insufficient explanation as to why the damage viewed to the concrete base (original seawall) and the dry stack rock wall (seawall or retaining wall) experienced damage due to the lack of compliance rather than the flood. Given this, I do not find that construction defects have been established as the proximate cause of the loss. I find it more probable than not that the cause of the loss was the flood with a double peak which increased the duration of the flood. This in turn had an impact on the riverbanks and structures along the riverbank by creating serious issues with erosion and washing of large amounts of sand/soil and debris onto the riverbanks. This issue of washing of additional sand/soil onto the riverbank in the location of the damage is demonstrated by a photograph provided in the CS expert report. It follows that I do not find the exclusion has been proven by the insurer. Settlement of the damage claimed to the retaining wall The complainant has offered a quotation which should not be relied on due to age. I further note that the policy does contain some limitations in relation to settlement of claims for building, under which the retaining wall falls. The insurer is only liable to pay to repair or rebuild the building ‘as new’. The policy does not suggest that the insurer would cover any additional expenses to replace undamaged parts of the building. There is insufficient information about the damaged concrete base in ‘as new’ condition, however the dry stack rock wall ‘as new’ was not built in a manner compliant with the Australian Standards. The insurer is entitled to arrange for an assessment of the building work required to repair or rebuild the retaining wall base and dry stack rock wall together with any timber components as new. The insurer is to settle the claim in accordance with its policy terms. Why is the outcome fair? The outcome is fair as it considers relevant law, policy terms and expert opinions regarding the cause of the damage. The complainant has established a claim covered by the policy and the insurer has not established that a policy exclusion applies to refuse the claim. Supporting information The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to: the legal principles applicable industry codes or guidance good industry practice previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider: available documents the recollections of the parties all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.