Determination 12-00-1018543
Storm damage claim: cash settlement and partial denial of kitchen wall damage
Summary
The insured's storm claim was partly cash settled and partly declined, with the insurer relying on exclusions for unrepaired and maintenance-related damage. AFCA found the kitchen wall damage covered, ordered assessment and extra settlement amounts, and upheld the $2,000 non-financial loss offer.
The insurer did not establish that the exclusions for gradual deterioration and failure to maintain applied to the storm-caused kitchen wall damage.
Issues
- Claim denial primary · upheld“The complainant has established, on balance, the damage to the kitchen walls was caused by the storm. The insurer has not established an exclusion applies”
- Claim amount dispute secondary · upheld“the cash settlement of the mould remediation must include a 10% uplift; the repairs must include the damage to the kitchen walls”
- Delay secondary · not upheld“I am persuaded the insurer has handled the claim generally appropriately and within a reasonable timeframe”
Subjects and remedies
home or building damagenatural disasterpay claimpay compensationpay non financial lossreassess claim
Related
Text of the determination
Determination
|
Case number
|
12-00-1018543
|
Financial firm
|
Insurance Australia Limited
Case number: 12-00-1018543 5 December 2024
Determination overview
Complaint
The complainant holds a Home Plus Buildings and Contents policy underwritten by the financial firm (insurer). On 28 February 2022, the complainant lodged a claim for damage to her property following a storm on 27 February 2022. The insurer:
accepted the claim for internal water damage to the kitchen, lounge, dining, and entry ceiling, and
cash settled the accepted damage.
The insurer also arranged for the complainant and her family to stay in temporary accommodation from 30 December 2022 until 20 October 2023, and cash settled a further six months of temporary accommodation costs.
The complainant says:
the insurer’s cash settlement is insufficient to repair the damage or cover temporary accommodation costs
she is entitled to the contents safety net amount, and
she wants the insurer to cover the cost of electricity, water, internet at the property while in temporary accommodation, as well as the cost to install a security camera and clean her car.
Issues and key findings
Is the insurer entitled to deny the claim for all the claimed damage?
No. The complainant has established, on balance, the damage to the kitchen walls was caused by the storm. The insurer has not established an exclusion applies to deny the claim for this damage. It is also fair for the insurer to assess the insulation in the kitchen ceiling and kitchen walls.
Is the insurer’s cash settlement fair and reasonable?
The insurer’s cash settlement of the contents claim is fair and reasonable. However, the cash settlement of:
the mould remediation must include a 10% uplift
the repairs must include the damage to the kitchen walls (and, if found to be damaged, the insulation in the kitchen walls and ceiling), and
temporary accommodation costs must increase to cover an additional two months of temporary accommodation in a furnished property.
Why is the outcome fair?
The outcome is fair because the complainant has established a claim for damage to the kitchen walls. It is therefore fair to require the insurer to:
cover this damage, and
assess the damage to the insulation in the kitchen walls and kitchen ceiling, and
cover additional temporary accommodation.
The complainant has also established some of the insurer’s cash settlements were not fair and reasonable. It is therefore fair for the insurer to increase those cash settlements.
The insurer’s offer of $2,000 non-financial loss compensation is also fair and reasonable.
Determination
This determination is partially in favour of the complainant. If the complainant accepts this determination, within 21 days of receiving the complainant’s acceptance, the insurer must:
if it has not already done so, pay the complainant $7,104 to cover the accepted pet accommodation costs and $100 for the accepted skip bin costs
pay the complainant $2,000 non-financial loss compensation
pay the complainant $1,650 for the uplift on the mould remediation cash settlement
obtain an actionable quote for two months of temporary accommodation in a fully furnished property
arrange for the assessment of the insulation in the kitchen walls and kitchen ceiling, and
obtain a scope of works and actionable quote for the water damage to the kitchen walls (and insulation, if damaged).
Within 14 days of receiving the actionable quote for:
the repairs, the insurer is required to cash settle the complainant with a 10% uplift for contingencies and the loss of a lifetime guarantee on repairs, and
the temporary accommodation, the insurer is required to cash settle the complainant in line with this quote.
Reasons for determination
Is the insurer entitled to deny the claim for all the claimed damage?
No. The complainant has established, on balance, the damage to the kitchen walls was caused by the storm. The insurer has not established an exclusion applies to deny the claim for this damage. It is also fair for the insurer to assess the insulation in the kitchen ceiling and kitchen walls.
Complainant must establish a claimable loss
It is established insurance law that the complainant carries the initial onus to show a loss of a type covered by their policy. The complainant must show this on the balance of probabilities (i.e. that it is more likely than not).
If a claimable loss is shown, the onus shifts to the insurer to show the loss is not covered, either by way of one of the policy exclusions or on some other basis.
The terms of the policy include the Certificate of Insurance (COI) and the Product Disclosure Statement (PDS). Cover under the policy is subject to the conditions, limitations and exclusions specified in the PDS.
There is no dispute the insurer provided the policy documents to the complainant. Therefore, I am satisfied the insurer is entitled to rely on the policy provisions to assess its liability under the claim.
The complainant holds a listed events policy which covers loss or damage to the complainant’s home and/or contents as a result of the incidents listed in the PDS.
In this case, the relevant listed event is ‘storm’, which is set out below in section 3.2 of this determination.
It is not in dispute the complainant has established some of the claimed damage was caused by a storm. The parties dispute the extent of the damage and the quantum of the cash settlement to cover the damage and temporary accommodation.
Circumstances surrounding the loss
The complainant lodged the claim for storm damage following a storm on 27 February 2022.
The complainant also lodged a separate claim for damage to the property on 4 March 2022 following a flood (flood claim). I have not considered the flood claim in this determination.
The flood claim decision letter shows the insurer’s assessor found:
on 1 March 2022, flood and rainwater run-off entered the property internally at approximately 1.9 metres and externally at 3.9 metres
the flood and rainwater run-off took approximately two days to recede, and
the flood and rainwater run-off was directly responsible for damaging the bedrooms, bathroom, linen press, converted garage, tool shed and contents.
The insurer accepted the damage to the bathroom ceiling. However, it declined most of the claimed damage because the complainant did not have flood cover.
In its flood claim decision letter, the insurer requested the complainant:
arrange for the damage to be repaired, and
provide it with written evidence of the completed repairs.
There is no information to show the complainant repaired the declined flood damage.
In relation to the storm claim, the insurer accepted the claim for internal water damage to the internal ceiling of the kitchen, lounge room, dining room and kitchen. The reasons the insurer declined some of the claimed damage are set out below.
Between 30 December 2022 and 20 October 2023, the insurer arranged for the complainant and her family to stay in temporary accommodation, as the insurer initially made the decision to arrange for the repairs to be completed. For the reasons discussed below, the insurer eventually decided to cash settle the claim.
Complainant disputes the insurer’s cash settlement for repairs
The insurer has cash settled:
the repairs for the damage it accepted
the complainant’s further temporary accommodation costs for six months
the mould remediation costs it accepted, and
the complainant’s contents claim.
The complainant disputes the insurer’s repair and mould remediation quotes and the cash settlement amounts. The complainant says:
due to the spread of the mould, the kitchen needs to be stripped out, and
after moisture and mould was left in the house for a year, the damage became beyond repair.
The complainant provided a mould assessment report dated 3 October 2023 and a repair quote for the repairs she says the insurer is liable for.
The complainant’s mould assessment report says, among other things:
significant mould growth and water staining was observed on the ceilings located in kitchen area, with mould growth also being observed on the walls, windows, window frames, gloss paint to the trim, doors and furnishings
there is mould growth located on the ceilings and walls in the bathroom, WC (water closet), study, lounge, dining room, bedroom one, bedroom two and bedroom three. Water damage did not appear evident in these areas, however access into the roof cavity was not possible due to the construction of the roof
the plasterboard ceiling in the kitchen that has been inundated with water will need to be replaced, particularly if the upper ceiling surface has been in contact with saturated insulation
water may have pooled for a considerable time which in turn can compromise the fixings
the plasterboard walls will need to be replaced in the kitchen as water damage has also occurred to the upper walls and likely have migrated down the walls, and
the timber framing to the ceilings and walls within the kitchen area will also require mould remediation.
The complainant’s repair quote includes, among other things:
mould spray on all mouldy surfaces
a roof inspection, and a provisional sum of $2,500 to allow for roof repairs
ceiling and wall gyprock and insulation
installation of new kitchen cabinetry
installation of a splashback in the kitchen, and
fit off of plumbing in the kitchen.
I have considered the complainant’s mould assessment and quote further below.
Insurer has established the property has unrelated damage
The insurer has obtained various expert reports which discuss the damage and the condition of the property.
The insurer’s building report dated 13 March 2022 says:
based on the initial site inspection of the property, the builder was able to confirm that water has leaked into the kitchen ceiling and the plasterboard has been affected
the damage is a visual surface inspection only of what is present and able to be inspected
any damage sustained to the wall framing or structural elements not listed will be subject to inspection during the repair process and may impose a variation to be compiled.
The building report dated 13 March 2022 also contains commentary from the roof report the builder arranged, as follows:
the roof of the property was in poor condition and had multiple cracked and chipped roof tiles
the pointing on the ridge and hip capping was cracked and, in some parts, missing
the guttering has been overflowing causing water to escape onto the eaves
the guttering does not have enough downpipes which is causing an overload of the existing downpipes and causing the guttering to overflow
homeowner roof maintenance identified at the time of the roof inspection/report must be completed for the internal repairs to be completed
all broken, cracked and chipped roof tiles need to be replaced
all the pointing on the ridge and the hip needs to be re-done.
The insurer provided a builder’s report dated 15 January 2023 following the builder’s re-attendance at the property. The re-attendance report says:
an inspection of the kitchen benchtop found there to be some sort of mould mites present on the benchtop and cabinetry
an inspection of the remaining bedrooms found there to be mould to the majority of ceilings and bathroom
there is strong mould growth present to the top level of the property which appears to have been getting worse since the downstairs area of the property flooded in February 2022
the downstairs area which had 500mm of water flow through it has not been stripped
an inspection inside a wall cavity to the downstairs area of the property found there to be mould present on the framework. The downstairs area should have been stripped and cleaned after the flooding
there is an almost certain chance that mould has spread around the property since the event, and
the builders are unable to warrant any repair works at the property due to this reason.
It is not in dispute the complainant did not undertake remediation repairs to the house following the February 2022 flood.
The insurer also provided a roof report dated 10 May 2023 which says:
water is entering in the kitchen area, causing internal damage to the plasterboard ceiling. This is above the valley. The debris and the loose valley tiles look to have been cleared and repaired
the pointing along the ridge and hip capping has been re-done and are now watertight, which has occurred since the last inspection.
The roof report identifies the following maintenance issues/prior damage:
there are a number of broken and cracked roof tiles, which is a point of water entry
there is dirt and debris in the grooves of the roof tiles, which restricts the flow of water, causing the water to backup and overflow internally at the point of the tile clips, which is a point of water entry
there is debris in the guttering and valleys, which restricts the flow of water and causes it to back up and overflow internally. This is a point of water entry, and
the metal downpipe has come away from the dropper and the astragals have also come away from the brickwork.
Considering the insurer’s expert reports, I am persuaded, on balance:
there were existing issues with the roof at the time of the storm
the property suffered flood damage shortly after the storm, which was not repaired and is unrelated to the storm.
Complainant has not established her quote sets out storm damage
The complainant’s repair quote does not provide any commentary on the cause of the damage listed for repair. It also does not sufficiently itemise the cost of each material item needed to complete the repairs. I am therefore not satisfied:
the insurer is liable for all the damage listed in the quote
the quote persuasively sets out the likely costs of the repairs listed, or
the insurer is required to cash settle the repairs based on the complainant’s quote.
As outlined below, there were pre-existing issues with the roof, which does not appear to be in dispute. The complainant has not provided any supporting information to establish the roof was damaged by the storm. I am not persuaded the complainant has established a claim for the roof inspection and roof repairs.
The mould assessment report does not state the kitchen cabinetry or splashback need replacing as part of the mould remediation. It also does not provide any commentary on the damage to the kitchen cabinetry or the splashback (including the cause). I am not persuaded the complainant has established:
any physical damage to the kitchen cabinetry or the splashback was caused by the storm, or
replacement of the kitchen cabinetry or the splashback is required to treat any mould growth.
The quote provides no commentary on why plumbing work is required. If it is linked to the installation of the kitchen cabinetry, as I am not persuaded the complainant has established a claim for damage to the kitchen cabinetry, the insurer is not liable for the plumbing work.
I acknowledge the complainant says the insurer’s lengthy handling of the claim has caused moisture and mould spread to the point that the upstairs needs to be stripped out in order to be repaired.
However, this does not mean the complainant has established the cause of the mould and moisture was the storm. It is not in dispute there was flood related damage at the property shortly after the storm, which is unrelated to the storm.
Considering the exchanged reports, I am persuaded, on balance:
there is unrelated flood damage to internal parts of the house, and
the state of the downstairs areas has caused or contributed to further internal damage to the property.
The complainant was aware the insurer had declined the claim for flood damage, and that she needed to undertake repairs to the property to address the flood related damage.
I am persuaded by the insurer’s expert reports that the flood related damage (which was not repaired) has caused and contributed to the spread of mould throughout the house.
This is because the builder’s report dated 15 January 2023 identifies significant mould in the downstairs walls. This is unrelated to the upstairs storm damage to the internal ceiling.
I am not satisfied the complainant has established, on balance, the full extent of the mould spread was caused by the storm. Therefore, the insurer is not liable for the mould remediation, other than what it has accepted for the upstairs and cash settled.
Complainant has established claim for kitchen wall damage
The insurer says:
the exchanged information confirms the property's roof has maintenance issues. The water ingress has not resulted from storm damage to the property's roof, but due to a combination of deterioration and unrelated maintenance relate issues
all the damage caused by the unrepaired damage, such as the mould damage caused by the maintenance related roof issues, is excluded from cover
the resultant internal damage caused by the storm event, and covered by the policy, include the water damage to the kitchen, lounge, dining, and entry ceiling.
It is unclear on what basis the insurer has differentiated between the damage caused by:
water ingress due to the roof maintenance issues, and
the storm.
However, the insurer does not dispute there is internal storm damage.
I acknowledge the insurer says there is unrepaired damage downstairs which was caused by flood. This makes it difficult to determine which parts of the damage are likely attributable to the storm.
The complainant’s mould assessment report identifies water damage to the upper section of the kitchen walls. As it is not in dispute the internal damage to the kitchen was caused by a storm, I am persuaded, on balance, the water damage to the walls was likely also caused by the storm.
This is because the assessment report identifies the water damage is located on the upper part of the walls. This is consistent with having been caused by water ingress from a storm (which the insurer does not dispute occurred).
The complainant’s mould assessment report also mentions saturated insulation. However, the report does not state the insulation was saturated or damaged.
The complainant’s quote lists the replacement of insulation in the kitchen walls and the kitchen ceiling. I note the mould assessment report confirms due to the construction of the roof, the assessor was unable to access the roof cavity.
The insurer’s building report also shows the inspection was visual only.
Considering it is not in dispute storm water entered the roof and caused the internal damage to the kitchen ceiling, it is plausible that the insulation in the kitchen ceiling is water damaged.
Further, as I am persuaded the damage to the kitchen walls was, on balance, caused by the storm, it is also plausible that the insulation in the kitchen walls is water damaged.
As there is no persuasive information to show the insulation was assessed, or the extent of the damage to the insulation, I consider it fair for the insurer to:
assess the insulation in the kitchen ceiling and walls, and,
if the insulation is damaged, obtain a scope of works and actionable quote for the damage.
Insurer has not established an exclusion applies to deny claim for kitchen walls
I accept the insurer has shown there was unrepaired damage to the downstairs area that is unrelated to the storm.
The insurer has sought to rely on exclusions for gradual deterioration, and failure to maintain the home, in making its claim decision.
The exchanged information shows, on balance, the damage to the kitchen walls was likely caused by the storm. The insurer accepted the water damage to the kitchen ceiling was caused by the storm. This also supports a finding that the water damage to the kitchen walls was caused by the storm.
The insurer has not explained how the water damage to the upstairs kitchen walls could have been caused by:
flood related damage, or
the maintenance issues with the roof.
Therefore, I am not persuaded the insurer has established it is entitled to rely on either exclusion to deny the claim for this damage.
Is the insurer’s cash settlement offer fair and reasonable?
The insurer’s cash settlement of the contents claim is fair and reasonable. However, the cash settlement of:
the mould remediation must include a 10% uplift
the repairs must include the damage to the kitchen walls (and, if found to be damaged, the insulation in the kitchen walls and ceiling), and
temporary accommodation costs must increase to cover an additional two months of temporary accommodation.
Condition of the property delayed decision to cash settle
The complainant says the insurer could have repaired the property, however, the restoration team refused to do the work.
The builder’s email to the insurer on 26 July 2023 says the property was deemed to be a biohazard and recommended:
the claim be cash settled, or
the contents be removed and the contents claim be cash settled, and the builder be engaged to complete the structural repairs only.
The repairer’s make safe attendance notes dated 27 July 2023 outline the specific safety hazards the property posed to the repairer. These were not related to the damage, but rather, the cleanliness of the home and contents.
The insurer has also provided photographs of some of the repairer’s concerns in support of the repairer’s decision not to continue with the work.
The repairer is entitled to take reasonable steps to protect its staff and provide a safe working environment to its staff. Having reviewed the supporting information, I accept the repairer’s decision not to continue with the works due to the safety concerns was fair and reasonable.
I am not satisfied the repairer’s conduct amounts to an error on the insurer’s part.
Insurer entitled to cash settle the damage
The insurer says:
the policy excludes cover for damage caused by gradual deterioration, depreciation or wear or tear, previous damage that has not been repaired and not maintaining your site in good repair and condition
due to the pre-existing issues with the roof, the insurer’s builder advised they are unable to warrant the repairs and recommended the complainant be cash settled for the claimed damage
the builder also deemed the property to be a biohazard and ceased working at the property, and
it is entitled to cash settle the claim under the policy.
The PDS sets out how the insurer may settle a building and/or contents claim. This includes paying:
the reasonable cost to repair or rebuild the home
the sum insured that applies to the loss or damage to the contents.
The policy provides some examples of when the insurer may choose to cash settle a building claim. This includes situations where:
not all damage to the building is covered by the policy, and
the building may have some damage that existed proper to the event being claimed for.
Considering the exchanged reports identify existing building damage that is not covered, and the policy allows the insurer to cash settle the building claim, I am satisfied the insurer’s decision to cash settle the claim is fair and reasonable.
Reasonable for the insurer to cash settle the temporary accommodation
The insurer says it was previously arranging the complainant’s temporary accommodation. However, it decided to cash settle costs because the complainant and her family were asked to leave one of the temporary accommodation locations due to their behaviour.
This is supported by an email the insurer received from its agent on 3 October 2023 confirming the complainant’s eviction from the hotel she and her family were staying at temporarily.
The insurer says it is not obligated to arrange the complainant’s temporary accommodation under the policy. Rather, the policy obliges it to pay temporary accommodation costs for the reasonable time it agrees it should take to repair or rebuild the complainant’s home. An extract of the relevant section is set out below.
Considering the above and the wording of the policy, I am persuaded the insurer’s decision to cash settle the temporary accommodation costs is:
fair and reasonable, and
in line with the terms of the policy.
Insurer must take steps to assess additional kitchen damage
The insurer cash settled the accepted damage for $5,111.64 (which includes a 10% uplift). The complainant has not established this is insufficient to cover the accepted damage. Therefore, the insurer is not required to increase the cash settlement offer for the accepted damage.
However, for the reasons discussed above, I am satisfied:
the insurer is liable for the damage to the kitchen walls, and
it is fair for the insurer to assess any damage to the insulation in the kitchen ceiling and walls.
Therefore, the insurer must:
arrange for the assessment of the insulation
obtain a scope of works and actionable quote for the damage to the kitchen walls and insulation (if it is damaged), and
cash settle this damage in line with the actionable quote, plus a 10% uplift.
Insurer should include an uplift for the mould remediation
The insurer’s cash settlement of the mould remediation is $16,500 based on a quote it obtained dated 15 May 2023. The quote is for structural cleaning of the upstairs of the property.
The complainant’s repair quote includes work to remediate the mould. However, the costs listed for ‘mould spray’ in the complainant’s quote are less than the insurer’s mould remediation quote. Therefore, I am not satisfied the complainant has shown the insurer’s cash settlement is not fair and reasonable. However, I consider it fair for the insurer to add a 10% uplift to cover for contingencies and the loss of the lifetime guarantee on repairs.
Therefore, the insurer’s cash settlement of the mould remediation should be $18,150. The insurer must pay the complainant an additional $1,650.
Complainant has not yet shown it is reasonable for insurer to pay safety net
The insurer has agreed to cover the contents claim for the sum insured (being $95,661). The complainant does not dispute this. The exchanged information shows the insurer agreed to this partly because its conduct caused further damage to the contents.
However, the complainant says she is also entitled to an additional 25% for the contents under the ‘safety net’ benefit.
The safety net benefit says:
We pay more than your Buildings or General Contents sum insured if a listed event causes loss or damage to your home or contents and the cost to rebuild, repair or replace them is higher than your sum insured.
[…]
Covered under Contents Insurance
up to 25% of your General Contents sum insured to cover reasonable extra costs to repair or replace your General Contents.
We pay this benefit on top of your General Contents sum insured.
It is not in dispute a listed event caused damage to the complainant’s contents. However, the complainant has not shown the general contents sum insured is insufficient to replace the damaged contents.
I acknowledge the complainant has returned to live in the substantially unrepaired property. However, it is not in dispute the property has not been repaired. It is also unclear if the complainant has replaced the contents of the home.
Once the complainant has replaced the contents of her home (if she has not already done so), and if the costs are greater than the general contents sum insured, it is fair for:
the complainant to provide supporting information to the insurer to show the costs incurred, and
for the insurer to assess whether the complainant is entitled to any additional cover under the safety net benefit.
However, the complainant is not entitled to any additional cover under the safety net benefit as an outcome to this complaint.
Insurer should allow for additional temporary accommodation costs
In addition to previously arranging temporary accommodation, the insurer has cash settled the complainant’s temporary accommodation for six months in the amount of for $19,760.
The insurer’s letter dated 28 September 2023 shows the insurer’s offer contemplated the complainant purchasing furniture for the rental property using funds from the contents cash settlement it made to her.
The insurer made this payment on 3 October 2023. Therefore, the complainant was covered for temporary accommodation until 3 April 2024.
The complainant says this was insufficient to rent a five bedroom, fully furnished, property. The complainant is seeking $120,000 for six months of temporary accommodation.
The complainant previously requested temporary accommodation in a furnished Air BnB property which cost $4,500 per week to rent. The insurer declined the complainant’s request as it did not consider it reasonable.
The PDS says the insurer will cover:
costs for temporary accommodation that we agree are reasonable and appropriate for you, your family and your pets that you normally keep at your site
any additional living expenses that we agree are appropriate
costs to remove and store your contents and then return them to your home.
We pay these costs for the reasonable time we agree it should take to repair or rebuild your home. If you have a:
Home policy, for up to 12 months from when the listed event took place.
Home Plus policy, for up to 24 months from when the listed event took place.
The insurer says:
its settlement was based on the median rental price for houses in the complainant’s suburb
the repairer estimated the repairs for the accepted damage would take up to four weeks, and
its cash settlement offer was in excess of the reasonable time it should take to repair the property.
The insurer has provided information to show the current median rental property price is $700 per week. I acknowledge the complainant is seeking $120,000 to cover the temporary accommodation for her family for six months.
The complainant has provided messages between her and an Air BnB host showing they were willing to rent her a property for $4,500 per week. However, this, in itself, does not persuasively establish the temporary accommodation costs the complainant is seeking are fair and reasonable, or necessary for the reasonable time it would have taken to repair the property.
It was estimated the accepted damage would take up to four weeks to repair. This is not in dispute. Even if I accept the complainant’s Air BnB costs as fair and reasonable, the insurer’s cash settlement for the accepted damage would cover the complainant’s costs for the expected repair timeframe.
However, for the reasons discussed above, I am satisfied the complainant has established a claim for some further damage the insurer has not accepted. This means it will likely take more time than the repairer has estimated to repair the property (particularly as a scope of works and quote are required).
The complainant is entitled to up to temporary accommodation cover for 24 months from when the event took place (being 27 February 2024). As it has been more than 24 months since the event, the complainant has exhausted her temporary accommodation cover under the policy.
However, considering the complainant has established a claim for additional damage the insurer has previously declined, I am not satisfied the insurer’s cash settlement for the accepted repairs is sufficient to cover all the repairs the insurer is liable for.
The complainant’s repair quote provides estimates of the time it will take the repairer to complete the work she says the insurer is liable for. The estimated time is approximately 208 hours.
While I am not satisfied the insurer is liable for all the repairs listed in the quote, I consider it fair for the insurer to cover an additional two months of temporary accommodation costs to cover the time it will reasonably take for the additional repairs to be completed.
Considering the insurer’s previous cash settlement for temporary accommodation costs was based on the complainant entering into a six-month rental agreement, and covered her until 3 April 2024, I do not consider $760 per week to adequately cover the complainant and her family while the additional repairs are being completed.
As per the terms of the policy, the costs for temporary accommodation must be reasonable and appropriate for the complainant, her family and her pets. An unfurnished property would not be appropriate in the circumstances.
Therefore, I consider it fair for the insurer to:
obtain quotes/estimates for the reasonable cost for the complainant and her family (including pets) to stay in furnished temporary accommodation for two months, and
cash settle the temporary accommodation costs in line with quotes/estimates.
Complainant has not established a claim for additional costs
In addition to the damage, the complainant wants the insurer to cover:
the costs incurred to place her dog in boarding
electricity, water and internet costs incurred for the property while she has been in temporary accommodation, and
installation of a security camera at the property
the cost of a skip bin.
The insurer confirmed it previously covered the complainant’s pet accommodation costs from 3 March 2023 and 31 May 2024 (being $3,424, which included a deduction of the $1,000 excess). The complainant does not dispute this payment.
After providing an additional invoice, the insurer agreed to pay the complainant $7,104, which covers the whole invoice.
The insurer has agreed to cash settle the $100 cost for the skip bin.
In relation to the other expenses the complainant seeks reimbursement for, the complainant has not done so. Even if I were to accept the insurer is liable for these costs, either under the policy or on some other basis, as the complainant has not substantiated she has incurred such costs, the insurer is not required to reimburse them as an outcome to this complaint.
It remains open to the complainant to give the insurer a copy of the invoices for the above expenses so it can decide whether to cover them.
The complainant is also seeking cover for the cost she incurred to clean her car, which has become dirty because she has had to move between multiple temporary accommodation locations.
The insurer says the complainant is not entitled to compensation for the cleaning of her car because:
the mess in the car was not caused by a listed event, and
the policy excludes consequential financial loss.
I acknowledge moving between temporary accommodation locations may mean it is difficult for the complainant to keep her car clean. However, this does not mean the financial burden of doing so shifts to the insurer. The responsibility has always rested with the complainant.
I am not satisfied the insurer is liable for the complainant’s car cleaning costs under the policy or otherwise.
Insurer’s offer of non-financial loss compensation is fair and reasonable
The complainant has raised various issues about the insurer’s handling of the claim. Of note, the complainant says the insurer has caused delay.
Under paragraph D.3 of the AFCA Rules, we may award compensation for non-financial loss (capped at $5,400) where the insurer’s actions have caused an unusual amount of:
physical inconvenience
time taken to resolve the situation, or
interference with the complainant’s expectation of enjoyment or peace of mind.
We take a conservative approach to compensation and expect a complainant to bear a normal degree of inconvenience during a claim.
The insurer offered the complainant $2,000 non-financial loss compensation for its handling of the claim. I acknowledge the claim has been ongoing for some time. Notwithstanding the additional damage the insurer is liable for, I am persuaded the insurer has handled the claim generally appropriately and within a reasonable timeframe.
I consider the insurer’s offer of non-financial loss compensation to be fair and reasonable in the circumstances.
Why is the outcome fair?
Outcome is fair in the circumstances
The outcome is fair because the complainant has established a claim for damage to the kitchen walls. It is therefore fair to require the insurer to:
cover this damage, and
assess the damage to the insulation in the kitchen walls and kitchen ceiling, and
cover additional temporary accommodation.
The complainant has also established some of the insurer’s cash settlements were not fair and reasonable. It is therefore fair for the insurer to increase those cash settlements.
The insurer’s offer of $2,000 non-financial loss compensation is also fair and reasonable.
Supporting information
The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided.
While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.
Relevant section of the PDS
Covered
storm
landslide or subsidence that happens immediately as a direct result of a storm.
For example, hail damages your roof.
Not covered
loss or damage to:
retaining walls
gates, fences or free standing walls if the damage occurred because they are not structurally sound or well maintained
pontoons, jetties or bridges
gravel driveways, or
swimming pool/spa covers that are more than 5 years old
loss or damage caused by:
erosion, deterioration, collapse, shrinkage or any other earth movement
water which enters your home through any tarpaulins or fixings set up while you’re renovating or altering your home.