Home / IAG / Determination 12-00-1016276
Determination 12-00-1016276
Declined storm claim for damage to retaining wall
Summary
The complainants claimed storm damage to a retaining wall that was declined as earth movement and gradual deterioration. AFCA found the wall was defective and cracked before the storm, so the policy did not respond and no expert cost contribution was ordered.
Under the proximate cause test the dominant cause of the damage was pre-existing wall failure and ground movement, which the policy excludes, so the storm was not the operative cause.
Issues
- Claim denial primary · not upheld“The insurer has established it is more likely than not the proximate cause of the retaining wall damage was excluded earth movement and gradual deterioration.”
Subjects and remedies
home or building damagenatural disasterno remedy
Related
Text of the determination
Determination
|
Case number
|
12-00-1016276
|
Financial firm
|
Insurance Australia Limited
Case number: 12-00-1016276 12 December 2024
Determination overview
Complaint
The complainants hold a home and contents policy with the financial firm (the insurer). On 3 June 2022, they lodged a claim for damage following heavy rainfall that occurred on 8 and 9 March 2022.
The insurer has denied the claim for damage to the property’s retaining walls on the western side of the property. It says the proximate cause of damage was earth movement and gradual deterioration. Damage from those causes is excluded under the policy terms.
The complainants say that the retaining wall cracked due to the extraordinary volume of rain that fell during the storm event. The complainants want the insurer to repair the retaining wall.
Issues and key findings
Is the insurer entitled to decline the retaining wall damage?
Yes. Based on the exchanged information, the insurer has established it is more likely than not the proximate cause of the damage to the retaining walls are excluded factors.
Is the insurer required to reimburse expert costs?
No. The complainant’s engineering report from TC has not supported their claim.
Why is the outcome fair?
The exchanged material does not persuasively show the storm event caused the damage to the retaining wall. It would not be fair to require the insurer to cover the damage to the retaining wall when the policy does not respond.
Determination
This determination is in favour of the insurer.
The insurer is entitled to decline the claim and is not required to take any further action in relation to the claim or this complaint.
Reasons for determination
Is the insurer entitled to decline the retaining wall damage?
Yes. Based on the exchanged information, the insurer has established it is more likely than not the proximate cause of the damage to the retaining walls are excluded factors.
Complainant must establish a claimable loss
The complainants are required to show, on the balance of probabilities (that is more likely than not), that they suffered a claimable loss under the policy. This means that they must show the loss was caused by a risk for which they are insured.
Once the complainants, on balance, establishes a claimable loss, the insurer is liable for the loss unless it shows an exclusion or limiting condition applies. The insurer has the onus of proving, on balance, the application of the exclusion or condition.
The insurer provided the complainants with the relevant policy documentation including the Product Disclosure Statement (PDS) and Certificate of Insurance (COI). I accept the insurer is entitled to rely on the policy provisions to assess its liability under the claim.
The policy covers the insured property against accidental loss or damage. Cover under the policy is subject to the conditions, limitations and exclusions specified in the PDS. The policy defines accidental damage as:
Damage to, loss or destruction of the buildings that make up your home, or your contents and valuable items, when it is caused by an unintentional act, or an unforeseen and uncontrollable incident.
The complainants say their neighbour advised them of cracks in the retaining wall in or around June 2022. The complainants say that the damage occurred following the severe storms in March 2022 which resulted in 315mm of rain falling within the two days.
Insurer obtained expert reports
The insurer appointed a builder, RC to attend the property and prepare a report. RC attended the property on 17 June 2022 and inspected the retaining wall and noted:
the masonry retaining wall had extensive cracking in various places
there was organic material growing over the wall
there was a deteriorated timber fence on top of the retaining wall
there was a large crack to the corner of the wall.
RCC recommended that the insurer appoint an engineer to assess the retaining wall.
The insurer appointed an engineer, M, to inspect and provide a report. M’s report is dated 15 August 2022. M noted that the insured property is located on a battle-axe block. The wall overlooks onto neighbouring property to the front (No 86) and another property (No 84) to the western side. M found:
the retaining wall has reached the end of its service life
it is unable to adequately drain groundwater flow
the wall has begun to fail due to the water pressure building up behind the wall
the heavy rain during February/March 2022 has likely inundated the retaining wall’s drainage system (likely a series of weepholes)
the rainfall saturated the retained soil and exerted active hydrostatic pressure on the wall.
M concluded that:
…it is our opinion that the damage observed to the wall have been the result of a combination of heavy rain for an extended period, and lack of, or inadequate retaining wall drainage allowing build-up of hydrostatic pressure behind the wall.
The retaining wall is considered to be of major structural consequence, at risk of imminent collapse, and should be demolished and reconstructed as soon as possible.
The insurer also appointed a geotechnical engineer, JK to inspect the property. JK attended the property on 27 March 2023. JK observed:
a brick wall extends along the northern end of the western boundary of the main site
along the western end of the northern boundary of the main body of the site retains the front yard up to 3m above the neighbouring property to the west (No 84) and north (No 86) respectively
approximately 3m south of the north-western corner, the western leg of the wall steps out to the west approximately 1m and then returns south
there was a vegetated timber fence along the crest of the retaining wall
the northern section of the wall (adjoining No 84) has been built with relatively large gaps in the brickwork, presumably to provide drainage
the wall had three main cracks
the southern crack is located between the carport and the retaining wall step out- it is retaining 1.2m of the insured property above No 84
an intermediate crack is located over the west facing section of the brick wall immediately to the north of the step out where it is retaining 2.3m of the insured property above No 84
the northern most crack is the most severe and located at the north-west corner of the retaining wall where it is retaining 3m of No 88 above the insured property and No 84.
JK reviewed the rainfall data that recorded 515.4mm of rain between 1 March 2022 and 9 March 2022. 315mm of rain was recorded on 8 and 9 March 2022. JK found that the rainfall intensity for this period was considered severe.
JK found that the wall was non-compliant as it was of inadequate design. JK says for a 3m high vertical compliant retaining wall, it would require a base width of at least 1.8m, without ignoring the effects of the vegetated fence. Further, the wall would need to increase progressively with depth given the limited tensile (or bending) capacity) of brickwork.
JK found that given the non-compliance and the brittle nature of brickwork, it is likely that the wall was cracked prior to the storm event.
JK found:
the southern most crack is a long term crack which is likely from an abrupt increase in the retained height of the wall (caused by a drop in founding level)
the intermediate crack is a long term crack resulting from differential lateral movements associated with the stiffness provided by the step out, with the cracking occurring along a weaker section of the wall (i.e. section with gaps) adjacent to the step out
the northern crack appears to be the result of behind wall pressures pushing each of the north facing leg and west facing leg outwards, with the result that the corner of the wall splits. The behind wall pressure include lateral earth pressures, vehicle surcharge loads and horizontal ‘jacking’ due to roots. This crack existed pre-event.
JK disagreed with M’s conclusion in relation to the lack of adequate drainage, noting that there had been some provision for drainage. Further, the northern most crack was unlikely to have been caused by hydrostatic pressures, as such pressure would have dissipated relatively rapidly following initial cracking.
JK acknowledged that the cracks were likely exacerbated by the rainfall but all the cracks pre-existed. JK believes that if the wall was compliant, it would not have suffered cracking to the extent that it did.
JK provided a supplementary response dated 14 April 2023 confirming that its analysis of the cause of the cracks was also consistent with the crack patterns observed. JK says that the crack pattern on the southern and intermediate cracks are not consistent with additional lateral pressure having been applied to the wall as a result of the storm event.
JK acknowledged that the pre-existing northern crack has most likely been exacerbated by the event, meaning that the crack or damage has worsened. However, says that remediation of the wall pre-event and post-event would require the same solution, that is demolition and reconstruction.
Insurer says that based on the expert reports the damage is excluded
The insurer says that the complainants have not established a claimable loss. The insurer relies on the evidence from JK that establishes that the claimed damage was not caused by the storm event but was the result of long-term earth movement and gradual deterioration. Further, the storm event did not result in any increase to the repairs required before the storm. As such, no cover is available under the policy for repairs to the retaining wall.
The insurer also relies on its policy which provides that cover for landslide or subsidence is only available if the loss or damage occurs within 72 hours of a storm (page 10 of the PDS). It also relies on its general exclusions for loss or damage caused by:
- settling, shrinkage or any movement of earth
- erosion, rust, corrosion, gradual deterioration, depreciation, wear or tear
…
- roots from trees, plants, shrubs or grass.
Complainants say claim should be accepted
The complainants have provided a copy of a geotechnical engineer report dated 2006 which was obtained following the completion of the construction of units on the eastern side of the property. The complainants say that they had rock breakers disturbing them for years and they were worried about potential damage.
The complainants disagree with the reports from M and JK and say that they are based on guesswork, with no soil samples being taken and the boundaries for the retaining wall are incorrect.
The complainants rely on a report from an engineer, TC dated 20 August 2024. TC says that during the weather event, approximately 25% of the annual mean rainfall total fell across two days. TC says that during this event, large volumes of overland stormwater flows were able to overwhelm the capacity of the walls’ drainage system, resulting in additional lateral pressures and subsequently the ability of the wall to resist these pressures was overcome, causing the cracking and damage now evident.
TC says that JK did not provide evidence to support its conclusion that the wall was cracked pre-event.
TC says that he believes, on balance, the most likely cause of the damage was due to the severe weather event which occurred on 8 and 9 March 2022 and the reported damage can reasonably be attributed to a single weather event.
Cause of damage, on balance, is earth movement and gradual deterioration
Damage can have more than one cause. When deciding whether the policy responds, the proximate cause of the damage needs to be identified. This is a question of fact depending on the circumstances. The proximate cause is not necessarily the first or last or the sole cause of the loss. It is the effective, dominant or operative cause of the loss. It is a question of fact that depends on the circumstances of each case.
The report from TC has provided little analysis of the cracking to the retaining wall. TC concludes that the damage was due to the storm event and severe rainfall but does not provide any commentary in relation to the adequacy of the construction of the wall or why the cracks had formed in parts of the wall.
Further, while TC reports that the complainants advised that it was in a good condition prior to the storm event, the history provided is that the complainants did not observe the damage to the wall until contacted by their neighbour some months after the storm. The cracks were observed on the neighbours’ side of the retaining wall, as the complainants’ property is elevated. The retaining wall was also reported as having extensive organic matter covering it. I am therefore not satisfied that it can be established that the wall was undamaged prior to the storm event based on comments from the complainants.
I place little weight on the report provided by the complainants from DP dated February 2006 and DC dated February 2008 which were obtained in relation to construction works on the eastern side of the property. The reports do not comment on the state of the retaining wall on the western boundary of the property.
The reports from JK are preferred. JK has provided a clear and logical explanation as to how it concluded that the damage was pre-existing, although noting that the storm likely exacerbated the cracking. JK’s qualification as a geotechnical engineer mean that he is suitably qualified to provide his comments. JK has provided an analysis of each of the cracks and explained the basis of why it reached the conclusion that there was long term damage. This included JK noting that for the southern most crack, the surface of the sandstone bedrock on which the wall was founded also appeared to have dropped in level.
The cracking to the intermediate crack was found to have been caused by differential lateral movements associated with the stiffness provided by the step out.
The northern crack was considered by JK to have been caused by several behind the wall pressures which included lateral earth pressures, vehicle surcharges loads and horizontal ‘jacking’ due to tree roots. While the complainants say that the area was not used by vehicles, this is only one of the proposed pressures. I am not satisfied that the absence of vehicle loads diminishes the effects of the other pressures.
JK noted that the wall was not sufficiently built in accordance with general engineering principles. That is, that for a gravity retaining wall, it must have a base width of half, to two thirds its height. The retaining wall did not have a sufficient width base to provide stability. I am satisfied that this failing has contributed to the gradual deterioration of the wall.
M concluded that the wall had come to the end of its serviceable life. While JK disagreed with M’s assessment of the cause of the cracking as being from inadequate drainage, it is otherwise agreed that the damage had occurred over a period and was not from a single insured event.
I am not satisfied, on the balance of probabilities, that the proximate cause of damage to the retaining wall was the storm event. While the evidence from JK suggests that the storm event may have worsened the damage, the cracks were pre-existing and the same remediation of the wall was required. That is, the wall needs to be demolished and rebuilt.
I am satisfied that the insurer can rely on its exclusion clauses for ground movement and gradual deterioration to decline the claim.
Is the insurer required to reimburse expert costs?
No. The complainant’s engineering report from TC has not supported their claim.
AFCA can require the insurer to contribute to professional costs
The AFCA Rules enable AFCA to require an insurer to contribute to the professional costs incurred by the complainant. These costs are, however, usually capped at a total of $5,000, unless special circumstances apply.
When considering whether to require an insurer to make a costs contribution, AFCA takes into account the complexity of the complaint and whether the particular complainant needed to incur costs to understand or establish their claim.
TC has not established the complainants’ claim
As TC’s report has not assisted the complainants’ in establishing their claim, the insurer is not required to reimburse the complainants for this cost.
Why is the outcome fair?
The exchanged material does not persuasively show the storm event caused the damage to the retaining wall. It would not be fair to require the insurer to cover the damage to the retaining wall when the policy does not respond.
Supporting information
The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. I have reviewed and considered all of the information the parties have provided.
While the parties have raised several issues in their submissions, I have restricted this determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.
Ceiling damage not considered
When the complainants lodged the claim with the insurer, they also claimed for damage to the staircase ceiling. The insurer has cash settled the complainants for repairs to the ceiling and this did not form part of the determination.