After a storm, the insurer cash settled a holiday rental's damage claim at $59,204.68 and the complainant disputed the amount, scope and delays. AFCA required an amended scope, two new quotes, a 30% uplift, loss of rent and $3,000 non-financial loss compensation.
Cash settlement was reasonable, but the amount must reflect a reasonable retail quote on an amended scope of covered storm repairs, excluding pre-existing upgrades.
Issues
- Claim amount dispute primary · upheld“No. Given the amended SOW and age of the quote, the quote does not represent the reasonable price payable by the complainant to get the work done.”
- Claim denial secondary · not upheld“The insurer is not required to cover those upgrades, as they are pre-existing issues and were not caused by the storm.”
- Delay secondary · upheld“The insurer's mistakes and delays caused the complainant unnecessary stress and inconvenience.”
- Poor communication secondary · upheld“The insurer caused lengthy delays and failed to adequately communicate with the complainant.”
- Repairs or contractors secondary · upheld“The insurer should modify the SOW to include the removal and reinstatement of the patio flyover, which it has not explained.”
Subjects and remedies
home or building damagenatural disasterpay claimpay compensationpay non financial lossreassess claim
Related
Text of the determination
Determination
|
Case number
|
12-00-1014453
|
Financial firm
|
Insurance Australia Limited
Case number: 12-00-1014453 22 July 2024
Determination overview
Complaint
The complainant holds a home insurance policy with the financial firm (insurer). Following a storm, on 26 February 2022 the complainant lodged a claim for damage to her holiday rental property. The damage included water damage to the house and, later, cracking damage to the pool patio.
The insurer says it accepted the claim in full. It has undertaken most of the internal repairs and paid $19,144.54 in compensation for rental losses in recognition of delays in its repair work. However, it says the property has pre-existing issues that are not covered by the policy. It has provided a scope of works (SOW) and quote for the remaining covered repairs, being $50,170.57. Based on the quote plus a 20% uplift for contingencies ($10,034.11), the insurer has offered to cash settle the claim by paying the complainant $60,204.68, less $1,000 excess. It has also offered to pay up to four weeks loss of rent for the repair period and $2,000 non-financial loss compensation.
The complainant disputes the existence of pre-existing issues at the property. She says the quote is insufficient to repair the claimed damage and the compensation offered does not compensate her and her partner for their time and loss of rent and business good will. She says the insurer should do the work itself and provide compensation or pay her the following:
$250,000 for the repair costs plus 20% for variations, or complete the work itself with a loss of rent penalty of $1,500 for each day over the estimated four week repair period
$28,000 for her time in dealing with the claim
$35,000 for her partner’s time in dealing with the claim, and
the balance of unpaid rent from April to September 2023.
findings
Is it reasonable for the repairs to be cash settled?
It is reasonable that the claim is cash settled. The policy allows the insurer to choose how to settle the claim. The insurer’s decision to cash settle is reasonable given that significant upgrades, not covered by the policy, are required for the repairs to be warrantable.
Is the SOW sufficient to repair the covered damage
Generally, yes. The SOW provides for repair of the covered damage but should be amended to include further items including the removal and reinstatement of the patio flyover and investigation and repair, if appropriate, of the bi-fold door damage.
Is the insurer’s cash settlement offer fair and reasonable?
No. Given the amended SOW and age of the quote, the quote does not represent the reasonable price payable by the complainant to get the work done. The insurer is to amend its SOW and obtain two new quotes and to increase the contingency to 30%.
Is indirect financial loss compensation payable?
No. The complainant has not provided sufficient information to establish that she or her partner lost income, business goodwill or incurred expenses because of the insurer’s conduct, beyond what the insurer has already paid. The insurer has offered to pay up to four weeks loss of rent for the period of repairs. In all the circumstances, it is reasonable that the insurer pay loss of rent for the reasonable repair period.
Is non-financial loss compensation payable?
Yes. The insurer’s mistakes and delays caused the complainant unnecessary stress and inconvenience. The insurer is to pay $3,000 to the complainant for non-financial loss compensation.
Why is the outcome fair?
The outcome is fair because the insurer is entitled to cash settle and to limit its liability to the damage caused by the storm. It would not be fair to require the insurer to pay for upgrading fill and other components that have not been shown to have been damaged by the storm. However, it is fair that the insurer obtain further quotes and increase its uplift to recognise the contingencies of the repairs and the loss of insurer’s warranty.
Determination
This determination is substantially in favour of the insurer.
If the complainant accepts this determination, the insurer take the steps set out in section 2.7 of this determination.
Reasons for determination
Is it reasonable for the repairs to be cash settled?
It is reasonable that the claim is cash settled. The policy allows the insurer to choose how to settle the claim. The insurer’s decision to cash settle is reasonable given that significant upgrades, not covered by the policy, are required for the repairs to be warrantable.
Background to the complaint
The complainant rents the property for holiday lettings. On 26 February 2022, the complainant lodged a claim for storm damage. On 20 June 2022, the insurer told the complainant she needed to undertake maintenance repairs to chipped roof tiles and remove leaves on the roof before the insurer would start the covered repairs. The complainant cleared the leaf litter but was unable to find any broken tiles on the roof. She asked for proof of tile damage. In its email to the complainant of 8 December 2023, the insurer accepted that its maintenance repairs request was in error.
By August 2023, the insurer had completed the internal repairs with the exception of the kitchen kickboards and fridge panels, installation of the security camera and three GPO covers. The insurer says the property was then in a habitable condition. The complainant disputes this and says that she and her partner undertook repairs themselves so the property could be rented out. The insurer accepted its delay caused the complainant loss of income for cancelled bookings and potential earnings based on information provided by the complainant.
On or around 17 August 2022 the complainant asked the insurer to address the broken tiles on the pool patio. Later, by 22 May 2023, the complainant had told the insurer severe cracks were present in the pool patio and movement had occurred causing damage to pool fencing.
The insurer arranged assessment by an engineer, VE, and soil testing by site classifier, LS. Based on their reports, it said that some of the damage was due to storm related exacerbation of pre-existing issues (insufficient soil compaction and slab strength). While the insurer says it accepted the claim in full, it says it is not required to repair those pre-existing issues by upgrading the patio to a warrantable condition. Its builder, JL, provided a SOW on 22 September 2023 for the covered repairs and provided a quote for $50,170.57 based on the SOW.
The insurer requested the complainant to get her own quote. The complainant said she has been unable to get a quote on the SOW.
Complainant says insurer should do repairs
The complainant says it would be unreasonable for insurer to provide cash settlement of the repairs and that it should do the work itself. She says:
significant variations may be required that will only become apparent after works have commenced
her builder, PR, told her there is a significant risk that the concrete pool/dividing wall and pergola/pool fencing could be damaged during demolition of the concrete slab
builders will not quote the SOW because it is not possible to perform the works, or will not quote a firm price given the variables, including risk of damage to other structures during repairs, and
variations could be massive in cost were they to occur. Those variations include the unforeseen plumbing, electrical or pre-existing buried fixtures needing to be rerouted, and structural damage to the pool.
Reasonable for claim to be cash settled
The policy provides the insurer with a discretion as to whether to undertake repairs itself or cash settle the claim. Such discretion must be exercised fairly, reasonably and consistent with utmost good faith. In this instance, it is reasonable that the insurer cash settle the claim because:
the exchanged information shows significant upgrades are required to make the repairs warrantable
the insurer is not required to cover those upgrades, including replacing/compacting the fill and increasing the structural strength of the slab, as they are pre-existing issues and were not caused by the storm, and
while I accept the complainant is concerned that the patio repairs could damage other structures, in particular the swimming pool, no report or supporting information has been provided to support this as being a likely scenario.
Accordingly, based on the exchanged information, I am satisfied the insurer has exercised its discretion fairly to cash settle the claim.
Is the SOW sufficient to repair the covered damage?
Generally, yes. The SOW provides for repair of the covered damage but should be amended to include further items including the removal and reinstatement of the patio flyover and investigation and, if appropriate, repair, of the bi-fold door damage, and other items set out below.
Complainant disputes the SOW is sufficient for the covered work
The complainant says the SOW is insufficient to complete the repairs. In particular:
the SOW should include all repairs, including full reinstatement of the pool patio. She disputes VE’s report and LS’s soil testing findings
significant variations may be required that will only become apparent after works have commenced
insufficient allowance has been made for the pool fence
no allowance has been made for removal and reinstatement of the patio flyover which is required for the work to be performed
it is not clear that adequate allowance has been made given access to the patio area is very limited, even getting a wheelbarrow through is difficult
she is not satisfied with the quote providing ‘best match existing’ tiles
the SOW should include repair of scratches to the paint on the aluminium track and broken screws in the bifold door mechanism. She says the storm damage and repair delay caused the beam above the doors to swell leading to the presenting problems
the insurer’s delay led to mould problems and its leaving the ceiling cavity exposed for months potentially spread mould through the house. She is unsure if the mould issues have been resolved
the insurer’s delay led to cracks in the plasterboard walls from prolonged damp.
Insurer not required to cover all patio repairs
The policy requires the insurer to cover damage caused by the storm. The complainant says that the insurer should cover repairs to the patio in addition to that which it has agreed to cover.
Having considered all the exchanged information, I am satisfied that the exchanged information shows, more likely than not, that the insurer’s SOW covers most of the storm related patio repairs. That is because:
while the complainant disputes the expert reports, saying they are based on assumptions and unsubstantiated by facts, she has not provided independent information to support her position or to refute the insurer’s experts
the complainant says the soil report was wrong as the samples were taken from the lawn, not under the patio. However, LS’s report says the soil samples were taken from the locations identified by VE. VE’s report provides a diagram labelling the sites as BH1 and BH2. LS’s report provides an aerial photo of the site labelling the sample sites. In LS’s photo, BH1 is partly obscured by foliage but appears to be in the location adjacent to the patio identified by VE. BH2 appears a little further from the pool. VE’s email to the insurer dated 7 December 2023 explains the soil sample could not be taken under the concrete slab without coring through (and damaging) the slab
no information has been provided indicating the fill has different characteristics to that indicated by VE and LS
I am satisfied that VE and LS have the qualifications and expertise to provide commentary on the matter
the exchanged information shows that the patio damage was due to a combination of design and construction issues that were pre-existing when the storm damage occurred, and were exacerbated by the storm
the policy does not cover upgrades such as replacing/compacting the fill and increasing the structural strength of the slab where they were pre-existing issues and were not caused by the storm.
Accordingly, it is reasonable for the insurer to limit its cover to the patio damage caused by the storm, as set out is its SOW.
Insurer’s SOW is generally reasonable
I am satisfied the insurer’s SOW generally sets out the repairs required to cover damage due to the storm or the insurer’s delay. That is because:
the ceilings have been repaired and no information has been provided showing mould in the ceiling or elsewhere in the house since the repairs were completed
the SOW covers the remaining internal repairs
the SOW covers supply and installation of new pool fencing on a ‘best match’ basis, acknowledging a variation for custom posts may be needed
it is reasonable for the insurer’s SOW to include best match to existing patio tiles. That is because the policy covers repair for damaged parts of the home. It does not pay for materials to match the undamaged parts of the home to create a uniform appearance
while the complainant says the insurer’s delays caused cracks in the wall linings, the information indicates this has been repaired
no expert information has been provided to show the insurer’s delay compromised the patio sub-straight and movement in pool fencing. The expert reports show this damage is due to existing defects, exacerbated by the storm, and
the insurer is not required to repair pre-existing defects including the issues with the patio set out above.
However, the insurer should modify the SOW as follows:
include the removal and reinstatement of the patio flyover. It has not explained how the covered repairs can be made without removing the patio flyover
follow VE’s advice to consult with the manufacturer of the bifold doors to ascertain potential water exposure or installation issues and then include item for repair in the SOW if the damage is found to be related to the storm or the repair delay
provide greater specifics in relation to the very limited access available to the rear patio so allowance for access difficulties can be factored into the quotes, and
given the additional components, provide an updated time estimate for which a retail customer could be expected to have the works completed.
Is the insurer’s cash settlement offer fair and reasonable?
No. Given the amended SOW and age of the quote, the quote does not represent the reasonable price payable by the complainant to get the work done. The insurer is to amend its SOW and obtain two new quotes and to increase the contingency to 30%.
Insurer’s cash settlement based on builder’s SOW and quote
The insurer’s settlement amount of $59,204.68 was based on JL’s quote on its SOW. This is made up of JL’s quote amount ($50,170.57) plus a 20% uplift ($10,034.11) = $60,204.68, less excess ($1,000). The insurer also offered to pay loss of rent for the four week period it estimates the repairs will take. It has also offered to pay up to four weeks loss of rent for the duration of the covered patio and kitchen repairs.
Complainant says the insurer’s cash settlement should be higher
The complainant says the insurer’s offer is unreasonable. She says the insurer, if the insurer will not do the work itself, it should pay her $250,000 plus 20% uplift for the repairs. She says:
she has been unable to get a quote because builders will not quote on the SOW because it is not possible to perform the works, there is a risk of damage to existing structures, and/or builders will not quote a firm price given the variables
the variations could be massive in cost were they to occur. Those variations include the patio fly over, unforeseen plumbing, electrical or pre-existing buried fixtures needing to be rerouted, and structural damage to the pool, and
given the time the insurer took to do the repairs to date, the insurer should pay her loss of rent for a longer period to allow for the repairs
Insurer should increase its SOW and obtain further quotes
A cash settlement must be based on a reasonable quote for claim related repairs, actionable by a retail customer. An uplift is then typically applied to the quoted amount to allow for contingencies and the loss of the lifetime warranty that applies to insurer approved repairs.
The complainant has not provided any reports, SOWs or quotes to support her $250,000 repair costing. There is no basis to accept this is a reasonable amount for the covered repairs.
Having considered the exchanged information, I am also not satisfied that the insurer’s quote reflects the price the complainant would pay to have the repairs completed, as required by its policy terms. The quote is almost ten months old, does not include the patio flyover and other items and has no builder’s margin. Further, given the extent of the possible variations, it does not provide sufficient allowance for contingencies.
If the complainant accepts this determination, the following steps are to be taken to enable cash settlement of the repair costs:
amend the SOW as set out in section 2.7 of this determination
the insurer is required to obtain two reasonable quotes, based on the updated SOW, for claim related repairs, actionable by a retail customer.
pay the complainant the average of the total quote amounts plus a 30% uplift recognising the extent of possible variations involved in making the repairs
pay the complainant loss of rent based at the average rate for the two years occupancy at it its current rental rate for the reasonable time for the covered repairs to be done, and
pay the complainant $3,000 compensation for non-financial loss.
Is indirect financial loss compensation payable?
No. The complainant has not provided sufficient information to establish that she or her partner lost income or incurred expenses because of the insurer’s conduct, beyond what the insurer has already paid. The insurer has offered to pay up to four weeks loss of rent for the period of repairs. In all the circumstances, it is reasonable that the insurer pay loss of rent for the reasonable repair period.
AFCA can award indirect financial loss compensation
Under paragraph D.3.2 of the AFCA Rules we may require an insurer to compensate a complainant for indirect financial loss. The maximum amount we may award is capped at $5,400.
Complainant says insurer should compensate her for loss of income
The complainant says the insurer should compensate her further for loss of rental income on account of its claim handling delays. She says the insurer’s failure to complete all the repairs and the temporary nature of other repairs meant that it left the property uninhabitable. She says that, but for the works she and her partner undertook, the property would not have been rentable and she would have suffered further loss of rent.
The complainant also says the insurer’s loss of rent payment to her of $19,144.54 for the April 2023 to September 2023 period covered only part of her loss for that period. The amount was calculated based on the average of the previous two years earnings over that period. The complainant says that was not the full amount calculated but, because she was financially exhausted, she accepted it.
Further, the complainant says the insurer should pay her and her partner, at their professional rates, for dealing with the claim. She says this has taken a lot of time and could have been avoided if the insurer had properly handled the claim. She also seeks an amount for loss of business good will.
Insurer to pay loss of income for reasonable repair period
The insurer has offered to pay loss of rent for the period of the covered patio and kitchen repair, not exceeding four weeks. Given the delays experienced by the complainant to date, the offer is appropriate but should be extended to the reasonable period for repairs set out in the amended SOW.
I note that the complainant’s efforts to make the property rentable took time and likely mitigated loss of rent. However, the complainant has not showed that it caused her financial loss. The insurer has asked for invoices for work completed, with a view to reimburse these costs, but the invoices have not been supplied by the complainant.
From the exchanged information I am not persuaded that the complainant suffered loss of rent for periods beyond that paid by the insurer for the April 2023 to September 2023 period. The complainant has not quantified the loss of rental income nor provided information to support that calculation.
The complainant has not provided information to establish loss of professional income. I have dealt with the complainant’s time, stress and inconvenience in dealing with this claim as non-financial loss.
Is non-financial loss compensation payable?
Yes. The insurer’s mistakes and delays caused the complainant unnecessary stress and inconvenience. The insurer is to pay $3,000 to the complainant for non-financial loss compensation.
AFCA can award compensation for poor claims handling
Under paragraph D.3 of the AFCA Rules, we may award compensation for non-financial loss (capped at $5,400) where the insurer’s actions have caused an unusual amount of:
physical inconvenience
time taken to resolve the situation
interference with the complainant’s expectation of enjoyment or peace of mind.
We take a conservative approach to compensation and expect a complainant to bear a normal degree of inconvenience during a claim. When considering non-financial loss compensation AFCA looks at what is reasonable and fair in all the circumstances. In considering what is fair in all the circumstances, it is appropriate to factor the overall claims experience, rather than focusing on specific individual events.
Insurer is required to pay non-financial loss compensation
The complainant says the insurer mishandled her claim causing her to spend days, over a period of years, dealing with the claim and leading to mental anguish and financial stress.
The insurer accepts that delays were experienced. It submits it has paid the complainant for loss of income beyond her policy entitlement, and has offered $2,000 compensation for the claims handling difficulties she experienced.
Having reviewed the information provided, including the insurer’s claim notes, I am satisfied it caused lengthy delays and failed to adequately communicate with the complainant. Accordingly, it is reasonable for the insurer to pay $3,000 non-financial loss compensation.
Why is the outcome fair?
The outcome is fair because the insurer is entitled to cash settle and to limit its liability to the damage caused by the storm. It would not be fair to require the insurer to pay for upgrading fill and other components that have not been shown to have been damaged by the storm. However, it is fair that the insurer obtain further quotes and increase its uplift to recognise the contingencies of the repairs and the loss of insurer’s warranty.
Determination
If this determination is accepted by the complainant, the insurer is required to:
within 28 days from being notified of the complainant’s acceptance, request its builder to, as soon as reasonably possible, provide an amended SOW to:
> complete the accepted repairs in the earlier SOW
> include allowance for the removal and reinstatement of the patio flyover
> provide for consultation with the manufacturer of the bifold doors to ascertain potential water exposure or installation issues and then include repairs in the SOW if the damage is found to be related to the storm or the repair delay
> provide greater specifics in relation to the very limited access available to the rear patio so allowance for access difficulties can be factored into the quotes
> provide a realistic time estimate for which a retail customer could be expected to have the works completed, given the additional components
within 28 days of receiving the amended SOW, send that SOW to two builders to provide quotes based on that SOW, as soon as reasonably possible. The quotes are to represent a reasonable price for which a retail customer can get the repairs completed and provide a realistic time period for the complainant to have the repairs completed
within 14 days of receiving the quotes, the insurer is to:
> provide the complainant with a copy of the amended SOW and quotes
> pay the complainant the average of the total quote amounts plus a 30% contingency uplift recognising the extent of possible variations involved in making the repairs, less the policy excess
pay the complainant loss of rent based at the average rate for the two years occupancy (prior to the storm) at it its current rental rate for the reasonable time for the covered repairs to be done as set out in the amended SOW, and
pay the complainant $3,000 compensation for non-financial loss.
Supporting information
The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided.
While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.