Determination 12-00-1011466
Dispute over scope of works for water damage repairs and decline of claim for stormwater pipe damage caused by tree roots
Summary
The complainant disputed the insurer's scope of works for repairing water-related foundation damage and the decline of a claim for stormwater pipe damage. AFCA found for the insurer, upholding the scope of works and the tree root exclusion, with a cash settlement option available.
The insurer's uni-pier scope was the more appropriate repair method, and the pipe damage was caused by tree roots, which the policy excludes.
Issues
- Repairs or contractors primary · not upheld“The insurer has prepared a scope of works... This is the best proposed method to attend to repairs.”
- Claim denial secondary · not upheld“the insurer has shown that the cause of the damage to the pipe occurred from tree roots, which are excluded.”
- Delay secondary · unclear“Since December 2023, the scope of the repairs has been negotiated... delay resolves around unavailability of expert reports and disagreement between the experts.”
Subjects and remedies
home or building damageno remedy
Related
Text of the determination
Determination
|
Case number
|
12-00-1011466
|
Financial firm
|
QBE Insurance (Australia) Limited
Case number: 12-00-1011466 29 August 2025
1 Determination overview
1.1 Complaint
The complainant’s house was insured under a building policy underwritten by the financial firm (insurer).
The complainant says the house was damaged by water saturating the foundations leading to movement of the property and subsequent cracking and movement of the floor. The insurer initially accepted the claim for cosmetic damage but declined structural damage to the floor. The insurer has since accepted liability for all damage including rebuilding the piers.
The complainant says that the floor being relevelled may cause further damage. She questions whether the scope of works is appropriate to return the house into the condition it was before the water event.
The complainant also claims for damage to a pipe arising from a further and subsequently discovered event. The insurer has declined the damage to the pipe.
1.2 Issues and key findings
Is the insurer’s scope of works reasonable?
Yes. The insurer has prepared a scope of works to rectify the damage to the foundations of the property and some internal damage. After the initial works are undertaken, the insurer will then assess and scope to relevel the floor and any resultant damage from the initial works. This is the best proposed method to attend to repairs.
Is the second event covered under the policy?
No. On balance, the insurer has shown that the cause of the damage to the pipe occurred from tree roots, which are excluded. Therefore, it is fair that the insurer declines this portion of the claim.
Why is the outcome fair?
The insurer has shown that the proposed scope of works is appropriate to repair the claimable loss and, therefore, it is fair that it proceeds with the repairs. Although, the complainant can choose to accept a cash settlement if she wishes. The complainant has not established a claimable loss for the second event and it is fair that the insurer declines that part of the claim.
1.3 Determination
This determination is in favour of the insurer.
If the complainant accepts this determination, then the complainant must allow the insurer access to the property for the repairs as set out in the scope of works dated 7 March 2025 and the insurer must commence repairs to the complainant’s property.
If the repairs do not, or cannot, commence within 3 months, then the parties will need to work together to resolve the claim. If the reason that the repairs have not commenced is that the insurer is unable to repair the property by installing uni-piers, then the insurer will need to use the method of repair proposed by CE to install a new beam. If for any reason this cannot be undertaken, and if the parties cannot agree on a proposed course, then the parties will need to return to AFCA for a further determination.
2 Reasons for determination
2.1 Is the insurer’s scope of works reasonable?
Yes. The insurer has prepared a scope of works to rectify the damage to the foundations of the property and some internal damage. After the initial works are undertaken, the insurer will then assess and scope to relevel the floor and any resultant damage from the initial works. This is the best proposed method to attend to repairs.
Policy and terms
The complainant’s property is insured under a home insurance policy. The terms of the policy are set out in the product disclosure statement and the schedule.
There is no suggestion that those documents were not sent to the complainant and I accept that the insurer can rely on the terms of those documents.
Relevantly, the policy covers loss or damage to the building caused by subsidence where the cause of the subsidence was from liquid escaping from a pipe. The policy also covers loss or damage caused by an accident.
The policy excludes loss or damage caused directly or indirectly from tree roots.
The onus is on the complainant to establish on the balance of probabilities, that is more likely than not, that the cause of damage to her property was caused by an insurable event. This is known as a claimable loss. If a claimable loss is established and if the insurer wishes to rely on an exclusion clause, the insurer must prove, on the balance of probabilities, that an exclusion clause applies.
First water event caused damage
In December 2018, the complainant’s garage was flooded. This occurred on several occasions between 2018 and February 2020. In February 2020, the complainant noticed water leaking from her stormwater system. The local council determined that tree roots had blocked its pipe which was causing water to escape onto the complainant’s property. The council cleared the blocked pipe in about June 2020 and no further flooding has occurred.
The complainant’s claim for the 2020 event was lodged in May 2022. The insurer appointed a builder, an engineer and a geotechnical engineer. The reports prepared by those experts lead to the insurer accepting the claim for cosmetic damage but declining the claim for structural damage on the basis that the movement was caused over time and not by a single event.
Subsequently, and following additional information provided by the complainant, the geotechnical engineer prepared a supplemental report dated 12 July 2023. That report accepted that the amount of water in February 2020 was sufficient to cause foundation movement of the stumps and structural damage to the house.
In December 2023, the insurer accepted that the structural damage was covered under the policy. Relevantly, the insurer then wrote to the complainant accepting liability for:
· ‘jacking and packing’ between the isolated piers and timber bearers to the required level
· removal and replacement of the damaged brickwork including provision to tooth into existing
· excavation of the collapsed soil in the drainage channel
· repair any damaged timber flooring
· removal and replacement of damaged cornices within the pantry
· patch repair cracks within plasterboard wall and ceiling linings within the bedroom hallway and dining room
· seal the gap between the existing kitchen stone benchtop
· replacement of damaged garage door to match existing
· preparation and application of three (3) coats of acrylic paint to the entire affected areas.
Scope of the repairs for the first water event.
Since December 2023, the scope of the repairs has been negotiated between the complainant and the insurer. The delay resolves around unavailability of expert reports and disagreement between the experts over the best method to repair the damage.
Ultimately, the insurer has provided a scope of works dated 7 March 2025. That scope includes installing uni-piers and construction of the footings for those piers. The piers are to replace the stumps adjacent to the drainage channel under the house, and those compromised by the storm. That method was first proposed by the insurer’s building consultant PB. Subsequently that approach was approved by the insurer’s engineer SE.
CE, an engineer initially appointed by the complainant, says that it is better to reinforce the floor with steel beams, rather than installing uni-piers. This was based on the limited access to the underfloor of the complainant’s property.
However, a scope of works has been prepared which includes installation of the uni-piers, the insurer will be responsible for arranging the trades to undertake that work. CE does not say that uni-piers cannot be installed, just that its proposed method of repair will be better. SE says that the repairs should use uni-piers. Accordingly, I accept on balance, SE’s proposal is appropriate. I am not persuaded the repair method proposed by CE is faster or will result in a better outcome.
The complainant also says that the scope of works does not include releveling of the floor which the insurer has said it will do. By letter dated 13 December 2024, the insurer has said it will relevel the floor, if such a step is necessary after the uni-piers are installed, and has not attempted to resile from that position.
The insurer says that releveling should not occur until the uni-piers have been installed. The exchanged documents show that the process of installing the uni-piers may cause further damage internally and settling of the floor may cause additional damage. I accept, therefore, that once the stumps have been repaired, and after any settling period, a further scope of works will need to be prepared by the insurer to relevel the floor and undertake any rectification works.
CE recommends against a full releveling of the house. CE recommends instead that a portion of the house be demolished and rebuilt. The reasons given for this are that releveling is less predictable than demolition and reconstruction of (approximately half) of the house. However, while the report recommends against releveling, I am satisfied SE’s preferred approach is more appropriate. I am not satisfied CE’s proposed method should be adopted, but if the complainant wishes it is fair that she accept a cash settlement for the repair of the piers with the insurer to then arrange for a further assessment once the complainant has repaired the piers to assess the costs of releveling the floor. This will enable the complainant to pursue CE’s method of repair.
2.2 Is the second event covered under the policy?
No. On balance, the insurer has shown that the cause of the damage to the pipe occurred from tree roots, which are excluded. Therefore, it is fair that the insurer declines this portion of the claim.
Further damage at house was caused by a separate and excluded cause
In about June 2023, the complainant’s plumber DP attended the property to investigate liquid escape through the garage roller doors.
DP found that the left side of the house storm water drainage is not functional and the drainage is crushed in two sections and has a ball wedged into one of the sections.
The complainant has claimed under the policy for this damage.
The exchanged documents show that the cause of the damage to the storm water system was from tree roots, which the insurer says is excluded under the policy, I agree.
On balance, it is fair that the insurer applies the terms of the policy to decline cover for damage to the storm water drainage from tree roots.
For completeness, the insurer has accepted that the storm water drainage may have contributed to the resulting damage at the house. However, as the insurer’s proposed scope of works for the first water event will repair any damage caused by the blocked drain nothing turns on the insurer’s decision about this issue.
2.3 Why is the outcome fair?
The insurer has shown that the proposed scope of works is appropriate to repair the claimable loss and, therefore, it is fair that it proceeds with the repairs. Although, the complainant can choose to accept a cash settlement if she wishes. The complainant has not established a claimable loss for the second event and it is fair that the insurer declines that part of the claim.
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:
· the legal principles
· applicable industry codes or guidance
· good industry practice
· previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided.
While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence.
When we assess complaints, we consider:
· available documents
· the recollections of the parties
· all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.