Home / QBE / Determination 12-00-1005725

Determination 12-00-1005725

Storm damage remediation delays and loss of rent

FirmQBE
Decided2024-07-16
ProductGeneral Insurance · Strata
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss$3,000
Amount claimed—
SourceAFCA PDF

Summary

The owner's strata storm claim was accepted, but remediation was delayed after an agreed settlement and further water ingress occurred. AFCA ordered loss of rent increased to $1,197 per week from 1 October 2023 with interest, $3,000 non-financial loss, and completion of remediation, and declined replacement, maintenance and professional costs.

The insurer caused avoidable delays after the May 2023 agreement, but the property is repairable and the policy does not require the insurer to buy the property.

Issues

Subjects and remedies

home or building damagenatural disasterpay claimpay interestpay non financial lossrepair or rectify

Related

All QBE determinations · Find similar determinations

Text of the determination

Determination | Case number | 1005725 | Financial firm | QBE Insurance (Australia) Limited Case number: 1005725 28 June 2024 Determination overview Complaint The complainant holds a residential strata insurance policy with the financial firm (insurer) and lodged a claim for damage after his property was inundated during a storm in April 2021. The insurer accepted the claim, but issues arose with the repair and remediation process. The complainant lodged a complaint with AFCA (923033) over the delays and variations to the scope of works (SOW). The complaint was resolved in May 2023 with the parties by agreement with the insurer to: authorise completion of the necessary remediation (including to the damage which was not caused by the storm) as a priority and in a timely manner compensate the complainant for various non-financial and indirect financial losses. The complainant lodged the current complaint on 4 August 2023 after ongoing delays in obtaining a SOW and avoidable delays in the remediation caused further losses Issues and key findings Did the insurer cause avoidable delays? Yes. Avoidable delays occurred in the appointment of builders and during remediation process. Compensation of $3,000 for non-financial loss is fair in the circumstances. Is the insurer required to increase the loss of rent amount? Yes. The loss of rent should be increased to $1,197.00 per week starting from 1 October 2023. Is the complainant entitled to additional compensation? No. there is insufficient information warranting other compensation. Is the insurer required to pay the replacement value of the property? No. The panel is satisfied the property is repairable and the insurer is committed to completing the repairs. Why is the outcome fair? While the panel acknowledges the complainant’s frustration with the delays and remediation process, the outcome represents a fair assessment of the insurer’s obligations to the complainant under the terms and conditions of the policy and agreement. Determination The determination is partially in favour of the complainant. Within 14 days of receiving notice that the complainant accepts the determination the insurer is to: increase the loss of rent payment to $1,197 from 1 October 2023 (back pay required) until the completion of all authorised remediation pay the complainant $3,000 for non-financial loss provide updates with photos in support to the complainant fortnightly until the completion of the remediation Reasons for determination The panel notes the complainant seeks AFCA’s consideration for the entire timeline from the claim lodgement to the present. According to C.1.2 (C) of the AFCA’s rules, the Panel will not consider the previous issues between the complainant and the insurer that were dealt with by AFCA in complaint 923033 and resolved by agreement. The panel’s consideration in this determination will be limited to the issues occurring after 11 May 2023, which was the closure date of the previous complaint. Did the insurer cause avoidable delays? Yes. Avoidable delays occurred in the appointment of builders and during remediation process. Compensation of $3,000 for non-financial loss is fair in the circumstances. The parties dispute when the agreement of the previous complaint was made. After lodgement of complaint 923033 the parties reached an agreement with a preliminary assessment issued on 5 May 2023 confirming: To resolve the complaint, FF has offered the following terms in relation to remediation of the property: • FF will complete the remediation of the property to provide to you the property in a fully remediated state of repair. The remediation works will: > be performed to completion, at the sole cost of FF > include any secondary damage caused to the property arising from the incomplete remediation of the property. • At the sole cost of FF, it will appoint an external (and independent) project manager/consultant to coordinate and oversee the remediation works to ensure the timely completion of the remediation works and that the full remediation of the property is completed as a matter of priority without delay. To that end: > FF will propose a panel of independent project managers/consultants for your consideration and selection > the independent project manager/consultant will be appointed to protect the interests of you and FF, and to ensure the timely and competent remediation of the property. • In consultation with the project manager/consultant, FF will enter into an agreed scope of works in respect of the remediation works to the satisfaction of you and FF (acting reasonably and with regard to its sole overall duty to ensure the complete, competent and timely remediation of the property). Loss of rent FF has agreed to the following: • FF will reinstate loss of rent to you, at market rate, from June 2022 until the completion of the Remediation Works (being the date when the fully remediated Property is returned to the control of you). The loss of rent market rate will be reached by agreement between you and FF or, failing agreement, to determine the market rate in respect of rent, an appropriately qualified property agent with expertise in the field of market rent appraisals will be appointed jointly by you and FF to provide a rent appraisal and the parties will be bound by that rental appraisal. • In accordance with the CoreLogic Estimated Renal Amount Report, FF has agreed to the valuation of $907.00 per week for rent. FF to pay indirect financial loss and non-financial loss compensation FF has agreed to pay you $5,400 in indirect financial loss and $5,400 in non-financial loss compensation in recognition of your claims experience. FF should reimburse part of the costs of dealing with the complaint of $3,401.75 Agreement made in May 2023 The complainant says the agreement was made in March 2023, whereas the insurer says it was made in May 2023. The available information shows the insurer first proposed the terms of the agreement to the complainant on 14 March 2023. However, there is no indication the agreement was accepted by the complainant on this date. In fact, the complainant rejected the insurer’s offer on 30 March 2023 as the offer only included part of the costs incurred. AFCA issued the preliminary assessment reflecting of the terms of the agreement to both parties on 5 May 2023. The complainant notified AFCA of acceptance of the agreement on 9 May 2023 and the insurer notified AFCA on 11 May 2023. In the circumstances the panel accepts the agreement was reached 11 May 2023. Insurer caused delay before inspections The claim notes show the insurer’s initial attempt to engage with a builder or an engineer was on 6 June 2023, which is more than three weeks after the agreement. Considering the length of time, the claim has already undergone, the panel considers the insurer should have handled this claim with more urgency. The panel considers one week would be sufficient for the insurer to start the process. Therefore, the panel is persuaded the insurer caused a two-week delay which should have been avoided. No delay identified following inspections started From the correspondence between the complainant and insurer, it shows: After discussing with the complainant, the engineer, IM, was appointed on 14 June 2023 to inspect the property and provide a scope of work (SOW). IM inspected the property on 21 June 2023 and recommended ALD conduct a leak test, which was completed on 2 August 2023. Following the inspections and tests, the insurer provided the SOW to the complainant on 24 August 2023. However, due to the concern about the leak report, a reinspection took place on 30 August 2023 to confirm a final version of the SOW. The final version of the SOW was provided to the complainant on 10 September 2023, which the complainant agreed. The panel accepts the above-mentioned actions and claim handling is reasonable, no further delay identified at this stage. Insurer caused delay work commencement After both parties agreed on the SOW, the remediation did not start. The insurer says it was making inquiries with relevant parties as to who would need to sign the contract. The available information shows the insurer has been trying to liaise with the body corporate of the building and the complainant’s broker. The insurer says it was not allowed to sign the contract on behalf of the complainant to authorise the remediation under the Queensland Building and Construction Commission Act (QBCC Act). It says only the complainant and the body cooperate can enter the contract. However, the panel is not satisfied this was clearly notified to the complainant because: the insurer did not inform the complainant of the relevant section of the QBCC Act. the information does not show it tried to contact the complainant directly for this matter. the complainant questioned why he was not informed of this, to which the insurer did not respond sufficiently. the contract was eventually signed by the complainant on 17 October 2023. Given all this, the panel accepts the insurer caused a four-week delay between 17 September 2023 (one-week allowance for the signing and returning of the contract) to 17 October 2023. Insurer caused delay during remediation The date of the work commencement was not provided. However, the available information indicates the work started in late October 2023 or early November 2023. The complainant informed AFCA on 11 December 2023, that the builder stopped work in earlier December 2023 without explanation. The insurer says the builder found additional maintenance-related issues after removing the external cladding, which required further inspection. The insurer was trying to arrange a further inspection for the additional damage mentioned above after the work stopped. Before it could do that, a severe storm occurred during Christmas 2023, which caused further water ingress to the property, naturally further delaying the remediation. IM reported in January 2024 that following removal of external cladding, moisture related damage to the structural elements such as floor joists and timber beams was identified. IE confirmed works ceased while the further inspection took place. During this time in late December 2023, a superstorm impacted the area causing additional water damage to the property. IM agreed that the insurer would cover any additional damage from this event. The complainant says the insurer has used the same reason to delay his claim several times previously. He says IM should have thoroughly inspected the property before authorising the remediation to avoid such delay. To support his assertion, the complainant provided a statement from his expert, JC. JC says if IM and the builder had initially inspected the damage by adopting below steps, the delay of remediation could have been avoided: testing moisture to determine the areas suffered water ingress removing sections of plaster or cladding to accurately assess the extent of the damage providing SOW commencing remediation. JC says the insurer skipped step 2 which directly caused the delay of remediation. After considering the above-mentioned information, the panel is satisfied the insurer has caused avoidable delay in this regard. This is because: the insurer did not dispute JC’s statement. The panel accepts the insurer should have adopting a more thorough and comprehensive testing before the repairs similar issues occurred several times previously, where the remediation works had to stop because the builder found additional maintenance-related issues. The complainant notified the insurer on 13 May 2024 of further damage caused to the property. According to the complainant the insurer’s builder had jack hammered the roof and had not properly covered the area. Heavy rain fell over the weekend causing further damage. The insurer confirmed remediation works were performed on the roof, which included the removal of the roof tiles. It says the exposed roof was protected by tarps with the joints taped. It acknowledged a further water ingress event occurred on or around 10 May 2024, concentrated to areas that previously had water ingress, and which fall within the current scope of works. Heaters have been installed in the property to mitigate any further issues. The insurer says the further water ingress event was caused by existing, but deficient and/or deteriorated, waterproofing membrane applied to the roof. These deficiencies will be rectified as part of the remediation works and any resultant damage will also fall within the current scope of works. Complainant is entitled to compensation for non-financial loss Under the AFCA Rules, we can award up to $5,400 compensation for non-financial loss. We will only award this type of compensation if the complainant suffers an unusual degree of stress, inconvenience, or delay because the insurer mishandled the claim. The complainant is holding the insurer solely responsible, saying: it failed to adequately secure the site while it was unattended the further water ingress would not have happened on either occasion if the insurer had properly made the site safe he warned the insurer about the inadequate make-safe methods. JC also provide his comment, in relation to the December water damage noting the previous SOW included to wrap the building in tarpaulins to secure the site, which did not happen. The insurer disagrees, saying: it properly secured the site, on each occasion which is consistent with the industry standard. the further water ingress did not cause additional damage. the water ingress occurred in areas overlapping with those already subject to remediation and will not impact on the practical completion date. The panel accepts that most likely the additional water damage from the December 2023 and May 2024 events will not cause any significant delay in the remediation process as it was to areas subject of the remediation. The insurer has confirmed that the additional damage has not altered the practical completion date of 15 August 2024. The insurer offered $1,000 in recognition of the complainant’s stress and inconvenience due to its claim handling. It has already paid the complainant $5,400 for events to 11 May 2023. The panel acknowledges the complainants ongoing frustration with the process. That frustration has been compounded by the further delays since May 2023. Considering the length of the claim and the stress the complainant has experienced, the panel considers the insurer should prioritise the claim and act more with more urgency. The panel accepts the insurer’s claims handling since 11 May 2023 has caused unnecessary delay after reaching the agreement with the complainant. The panel considers it fair in the circumstances that the insurer pays compensation for non-financial loss of $3,000 for the complainant’s stress and inconvenience. Is the insurer required to increase the loss of rent amount? Yes. The insurer is to increase loss of rent to $1,197.00 per week starting from 1 October 2023. Policy covers loss of rent The policy provides a special benefit for loss of rent. If the property was leased out or could have been leased out at the time of a claimable loss, the policy covers the actual rent loss or the rent which would have been lost until it is fit to be able to relet. Parties dispute the loss of rent amount The available information shows the insurer is currently paying the complainant the loss of rent on an agreed amount of $907 per week. The amount is not based on an actual lease agreement; rather, it was an estimated amount from a property website C on 17 April 2023, which both parties agreed upon. The complainant says, due to delay of the remediation, this amount cannot reflect the correct rental value of the property. He provided an updated estimate amount of $1,197 per week from C, saying the insurer should pay him this amount from 1 July 2023 onwards with an additional $100 per week every three months. The insurer says the amount the complainant sought are not warranted. It provided a comparable property in the same area listed for $1,150 per week in November 2023. Therefore, the insurer offered to increase the loss of rent to $1,100 per week from 1 October 2023. Insurer to increase offer for loss of rent After carefully considering the available information, the panel is persuaded that the loss of rent payable should be increased to $1,197.00 from 1 October 2023. This is because: Both parties agree $907 was the correct reflection of the rent loss at the time of the agreement 11 May 2023. The original proposed completion date was in November 2023. However, as mentioned above, the SOW initially provided was inadequate. The panel considers that even if no delays occurred, it is unlikely the remediation would have been completed before October 2023. by agreeing to increase loss of rent from 1 October 2023, the complainant is already in a favourable position. the insurer has not provided any evidence of a comparable property letting for less than $1,150/week (and the complainant makes some reasonable points about why that property is not comparable), the 19 October 2023 C report, is persuasive of the true rental value. Interest should be paid on any arrears of compensation from 1 October 2023 to date of payment of the claim pursuant to section 57 of the Insurance Contracts Act 1984 (Cth). The complainant also seeks that further increases in rent should guaranteed. The panel does not agree. The panel considers it fair that, should the remediation not be completed by October 2024 (noting the practical completion date is 15 August 2024) any further increase can be negotiated considering market conditions. Is the complainant entitled to additional compensation? No. there is insufficient information warranting other compensation. Insurer is not required to pay ongoing maintenance and associated costs The complainant says he was planning to sell the property as soon as the remediation was completed. However, he cannot do that due to the delays caused by the insurer. He says by not being able to sell the property, he incurred costs associated with financing and maintaining the property, such as increased mortgage costs, body corporate fees, council rates, water, and sewage rates, etc. The complainant is seeking coverage on these costs, which the insurer declined. The panel is not persuaded that the insurer is required to cover the above-mentioned costs. This is because; if the property were in good condition, he would be incurring these costs and receiving rent to cover these costs he is receiving rent at the same rate (to be increased) if the complainant keeps the property and rent it out, regardless of the result of the claim, he will still need to incur the above-mentioned costs. there is no evidence that the complainant has incurred additional costs due to the insurer’s conduct Insurer is not required to pay for professional fees Under the AFCA rules, we can ask the insurer to reimburse a complainant for costs incurred in making the complainant. This may include paid representation and/or expert report fees. If a complainant asks the insurer to contribute to these costs, we will consider whether they were reasonable and whether they helped resolve the complaint. We try to make our service accessible and understandable, without any need for paid representation. If a complainant chooses to be represented, they will have to pay for this themselves. However, we may still require the insurer to contribute to costs if a complaint raised complex issues or if a complainant could not have handled the complaint without obtaining help. Unless there are exceptional circumstances, we will not require an insurer to contribute more than $5,000 to these costs. Following the Christmas storm, the insurer says the storm only caused minor damage unrelated to the previous accepted areas. The complainant disagrees and wants JC to inspect the property independently, with the insurer covering the cost. The information shows the insurer asked the complainant to provide a quote for its consideration. The complainant provided a quote from JC for $49,599.00. The insurer says it is excessive and declined the request. The complainant is unhappy with the insurer’s decision, saying the insurer: has already agreed to pay for the inspection. breached its promise and caused unreasonable delay again. The panel is not satisfied the insurer is required to pay for JC’s quote. This is because: No information shows the insurer promised to pay for the JC’s inspection. The complainant’s request was for inspection of property damage. However, JC’s quote focused on claim and management, such as reviewing and responding to emails, reviewing project delays, reviewing correspondence between parties and AFCA etc. These costs are irrelevant to the inspection for the property damage. Insufficient information to show the insurer’s behaviour is offensive After an onsite inspection by JC (prior to the above quote), the insurer says JC was underprepared for the inspection and did not add any value regarding the remediation process. It also says JC’s quote was for legal cost and JC was not a lawyer. The complainant strongly disagrees and is offended by the insurer’s comment. He says: the legal cost reference was clearly a typo, and the insurer should not use it against him. the comments towards to JC were offensive and unjust, with no information to support it. The complainant requests the insurer to withdraw these comments, which the insurer did not. After reviewing the correspondence, the panel does not consider the incident to have impacted the complaint or the claim. The insurer’s comments are an observation. The panel did not find them offensive. As such, the panel is not asking the insurer to take any further action in this regard. Insurer is not required to pay other compensation The complainant also seeks reimbursement from the insurer for: $7,000 for the maintenance work he incurred in 2022. Legal costs he incurred by seeking independent legal advice in 2022. The panel is not satisfied the insurer requires to pay these costs. This is because: The policy does not cover maintenance-associated costs. The policy does not cover legal costs the complainant incurred for claim management. These costs occurred prior to the agreement between the complainant and the insurer which was to resolve the previous dispute in full. The insurer has offered the maximum amount AFCA can award for such compensation. Is the insurer required to pay the replacement value of the property? No. there is insufficient information showing the property in dispute needs to be replaced or rebuilt. Complainant demands market value of the property for settlement The complainant says the policy covers him the replacement value of the property. He says after three years without settlement, it shows the insurer is incapable of completing the remediation works. As such, the complainant says he wants the insurer to pay him the market value of the property, including the land value, so he can buy another property for replacement. Policy does not require the insurer to purchase the property The policy provides options for the insurer on how it can settle a claim. The insurer can choose to either rebuild, replace, repair, or pay the amount it would cost to rebuild, replace, or repair. The policy defines replacement as: The reasonable cost of rebuilding, replacing, or repairing to a condition which is equivalent to or substantially the same as but not better nor more extensive than when it was new. The insurer declined the complainant’s request for purchasing his property by market value, saying no information shows the property cannot be fully remediated. It says all the experts, including JC, indicated the property can be fully remediated, therefore, it does not need to be replaced. The panel agrees. There is nothing in the policy that requires that an insurer to purchase a property if repairs cannot be completed. The policy provides that an insurer has the option to repair replace or pay the cost to repair replace the damaged property. The insurer has elected, and the parties agreed to the remediation of the property. There is no information to show the property needs to be fully replaced. The complainant says insurer’s builder is not capable of completing the remediation. However, other than the delays, there is no information to show the builder is not qualified to complete the remediation. The available information shows the delay was caused by various reasons, not solely contributed by the builder. The insurer has elected to complete the repairs. It is required to complete the remediation. Why is the outcome fair? While the panel acknowledges the complainant’s frustration with the delays and remediation process, the outcome represents a fair assessment of the insurer’s obligations to the complainant under the terms and conditions of the policy and agreement. Supporting information The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to: the legal principles applicable industry codes or guidance good industry practice previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all the information the parties have provided. While the parties have raised several issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. A panel determined this matter Due to the nature of this complaint, we referred it to a panel for determination. The panel includes: an ombudsman a member with considerable experience in consumer and small business advocacy a member with extensive experience within the insurance industry. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider: available documents the recollections of the parties all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.