Determination 12-00-1000668

Refusal of indirect losses after claim delays; contents settlement outstanding; goodwill payment

FirmHollard
Decided2024-06-06
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss$1,500
Amount claimed$45,028
SourceAFCA PDF

Summary

The company complainant claimed $45,027.95 in indirect costs after building damage from a vehicle collision, arguing claim delays caused them. AFCA rejected the indirect losses, required contents reassessment on proof, and endorsed a $1,500 ex gratia goodwill payment for claim delays.

Indirect costs such as rates, premiums and interest are not recoverable under the policy exclusion and were not shown to result from the insurer's conduct, though a goodwill payment was endorsed because company complainants do not normally receive non-financial loss.

Issues

Subjects and remedies

home or building damagemotor vehicle collisionpay non financial lossreassess claim

Related

All Hollard determinations · Find similar determinations

Text of the determination

Determination | Case number | 1000668 | Financial firm | Hollard Insurance Partners Limited Case number: 1000668 20 May 2024 Determination overview Complaint The complainant company holds a home insurance policy with the financial firm (insurer). In February 2022 it lodged a claim for damage to its investment property, and some of the contents therein, after a motor vehicle impacted the house on 14 February 2022. The insurer accepted the claim and, after a delay of more than 17 months, authorised its builder to commence repairs. In the meantime, the insurer paid loss of rent (LOR) for a period of 52 weeks initially (being the maximum LOR allowable in accordance with the terms of the policy). However, when delays continued, the insurer offered a further $5,820.66 for LOR on an ex-gratia basis. This payment was intended to extend the LOR allowance to 18 July 2023. In July 2023, the insurer also paid the sum of $11,040 for several additional expenses incurred by the complainant, including lawn mowing, interest on loans (as the damage destroyed the complainant’s plan to sell the property) and travel expenses for a representative of the complainant to inspect the property. The insurer denied the claim for reimbursement of insurance premiums, council rates and water rates. When the complainant lodged its complaint with AFCA, repairs had not commenced. In its complaint form, the complainant said the insurer should therefore pay it the entire building and contents sum insured (being $562,658) so that it can engage a local builder to complete the repairs. In response, the insurer said a scope of works (SOW) for the repairs that was previously prepared by its builder, CS, in the sum of $135,936.76 remained valid and reasonable and any resolution of the claim should be based on that SOW. In addition, at that juncture, the insurer offered the complainant the sum of $1,500 of on a goodwill basis as recognition of claim delays and inconvenience, and the like. The offer of the $1,500 goodwill payment was made outside the terms and conditions of the policy. Subsequently, CS completed the repairs to the property on about 20 December 2023. Nevertheless, the complainant maintains the insurer’s delays and mishandling of the claim prevented it from selling the property and this, in turn, caused it to incur additional costs. The complainant says the insurer should therefore cover all additional costs it has incurred including, but not limited to, insurance premiums, council rates and water rates. The claim regarding these additional costs totals $45,027.95. Issues and key findings Are the building repairs and contents settlements finalised? The exchanged material shows the insurer has completed the repairs of the building damage. The insurer has settled the damaged carpets and the complainant is to provide further information to allow the insurer to assess cover for any additional contents that may have been damaged in the insured event. If the parties remain in dispute about the final claim settlements for the repairs and contents, the complainant can lodge a new complaint at AFCA. Should the insurer cover the complainant’s additional costs? No. The insurer is not required to cover the additional costs incurred by the complainant. Should the insurer make a ‘goodwill’ payment to the complainant? Yes. AFCA does not normally award non-financial loss compensation to a complaint that is not a natural person. However, in these specific circumstances, I endorse the insurer’s offer of a $1,500 ‘goodwill’ payment to the complainant company on an ex gratia basis. Why is the outcome fair? The outcome is fair in all the circumstances because: the insurer has finalised the repair of the building damage and is entitled to further assess cover for any additional damaged contents the insurer is not required to reimburse the complainant for the additional indirect losses it has claimed although AFCA does not normally award non-financial loss compensation to a complaint that is not a natural person, in these specific circumstances I endorse the insurer’s offer of a $1,500 ‘goodwill’ payment on an ex gratia basis. Determination This determination is predominantly in favour of the insurer. Within 14 days of receiving notice the complainant accepts this determination, the insurer is required to pay the complainant the sum of $1,500 on an ex gratia basis. Otherwise, the insurer is to assess the claim for any additional damaged contents in accordance with the terms and conditions of the policy. The insurer is not required to reimburse the complainant for the indirect losses that it claims. Reasons for determination Are the building repairs and contents settlements finalised? The exchanged material shows the insurer has completed the repairs of the building damage. The insurer has settled the damaged carpets and the complainant is to provide further information to allow the insurer to assess cover for any additional contents that may have been damaged in the insured event. If the parties remain in dispute about the final claim settlements for the repairs and contents, the complainant can lodge a new complaint at AFCA. Claim has a significant history In February 2022 the complainant lodged a claim for damage to the house on its investment property, and some of the contents therein. The damage was caused when a motor vehicle collided with the freestanding, single story dwelling on the property on 14 February 2022. The external wall cladding on the dwelling is asbestos sheeting. The insurer accepted the claim and, after a delay of more than 17 months, authorised its builder, CS, to commence repairs. The repairs were then completed on around 20 December 2023. In the meantime, the insurer paid LOR for a period of 52 weeks initially (being the maximum LOR allowable in accordance with the terms of the policy). However, when delays continued, the insurer offered a further $5,820.66 for LOR on an ex-gratia basis. This payment was intended to extend the LOR allowance to 18 July 2023. Finally, the insurer offered to extend the LOR allowance to 20 December 2023, being the date the building repairs were completed, again on an ex gratia basis. In July 2023, in addition to its payment of LOR, the insurer paid the complainant the sum of $11,040 for several additional expenses it had incurred, including lawn mowing and travel expenses. This payment also included an amount for interest on loans. The complainant says its plans to sell the property were scuppered by the insured event. The complainant also claimed reimbursement of insurance premiums, council rates and water rates incurred while the property was not tenanted due to damage. However, the insurer denied this aspect of the claim. It says the policy does not include cover for any indirect financial loss the complainant has incurred as a result of the insured event. Repairs did not commence until late 2023 The complainant lodged its complaint with AFCA on 16 July 2023. At that time, repairs had not commenced, although the insurer had arranged for asbestos to be removed from the building. As part of its complaint, the complainant said the significant delays meant the insurer should pay it the entire building and contents sum insured (being $562,658) so that it could engage a local builder to complete the repairs. In response, the insurer said the scope of works (SOW) for the repairs that was previously prepared by CS in the sum of $135,936.76 remained valid and was reasonable. The insurer said that any resolution of the claim should be based on that SOW. In addition, at that juncture, the insurer offered the complainant the sum of $1,500 on a ‘goodwill basis’ as recognition of claim delays and inconvenience, and the like. The offer of the $1,500 goodwill payment was made outside the terms and conditions of the policy. Repair of the building has been completed CS completed repairs to the property on about 20 December 2023, being 22 months or so after the insured event occurred. Whilst the repairs of the property have been completed, at this juncture there is no information to indicate the complainant has inspected the property. I am satisfied the exchanged material shows the building repairs have been completed. However, should any repair or quality issues arise, the insurer is required to assess such issues in accordance with the terms and conditions of the policy. The complainant is to provide further information to assess the contents claim The complainant seeks cover for replacement of contents that were damaged in the insured event. The complainant’s main concern was the replacement of carpets, but it agrees these have now been replaced. However, the complainant says it still seeks cover for window coverings which will cost around $200 to $300. The insurer says the complainant is yet to provide a complete list of damaged contents, proof of ownership and replacement values. The insurer says, once this information has been provided by the complainant, it will complete its assessment of the contents portion of the claim. The terms and conditions of the policy are set out in the policy documents, including the Product Disclosure Statement (PDS) and the Certificate of Insurance. I note page 60 of the PDS says an insured must provide the insurer with all information and proof that is reasonably necessary in order to establish: that the insured has suffered a loss that is covered by the policy; and the amount that fairly represents the value of the insured’s loss. It follows the complainant must provide the necessary and relevant information to the insurer to enable it to further assess any outstanding issues regarding contents coverage. If the parties are unable to agree on the final contents settlement, the complainant is entitled to lodge a new complaint with AFCA for a decision on this point. Should the insurer cover the complainant’s additional costs? No. The insurer is not required to cover the additional costs incurred by the complainant. Other expenses are not covered under the policy As mentioned, the insurer acknowledged delays during the claim and offered payment of $11,040.00 to cover costs associated with lawn mowing, interest on loans and travel costs. This offer was made in addition to the LOR being paid by the insurer. Nevertheless, the complainant maintains the insurer’s delays and mishandling of the claim prevented it from selling the property and this, in turn, caused it to incur additional costs it would not have otherwise incurred had the repairs been completed in a timely manner. The complainant maintains the insurer should therefore cover all additional costs it has incurred including, but not limited to, insurance premiums, council rates and water rates. This aspect of the claim totals $45,027.95 for the following additional expenses: council rates water rates insurance premiums gardening (so the property did not look derelict) land tax project management reinstatement of services interest on loans. The policy excludes cover for losses which are not directly related to a claimable event under the policy. Page 55 of the PDS states: | General exclusions | General exclusions apply to all sections of this policy except for domestic workers compensation cover. 38. losses which are not directly related to a claimable event under your policy such as, but not limited to, loss of income or profit because you cannot go to work following an insured event, or the cost to clean up following an event where no claimable damage has occurred; However, this exclusion does not apply to indirect losses that are caused by the insurer’s mismanagement of the claim, if it can be established the insurer’s conduct, rather than the nature of the claim itself, was unreasonable and caused the loss. After having examined all exchanged material in detail, I am satisfied the indirect losses claimed by the complainant are not recoverable. I consider the complainant has not shown it suffered these indirect losses as a result of the insurer’s conduct or the claim delays. This is because of the following considerations: the exchanged material includes a notice for cancellation of the sale of the property dated 25 February 2022 LOR was paid by the insurer until 20 December 2023 when repairs to the building were completed. Expenses associated with the property (such as garden maintenance, council rates, water rates, and the like), should have been paid by the complainant from this LOR (i.e. rental ‘income’) during the period the property was not tenanted council and water rates, land tax and ongoing garden maintenance are expenses incurred by all property owners regardless of any claim or repair delays insurance premiums are payable under a contract of insurance. In this case, the complainant received the benefit of the policy cover with the settlement of its claim and, in addition, received the benefit of any further cover which may have been activated by the occurrence of another insured event that could have occurred during the period of insurance project management and managing trades and repair is expected when managing repairs and dealing with an ongoing claim interest on loans are payable as part of an agreement with a financial provider, regardless of claim delays. The complainant says the above costs were incurred as he was unable to sell the property due to the claim delays. I disagree. Moreover, I am satisfied the expenses were generally offset by the LOR paid by the insurer. Given this, I am not satisfied the complainant has adequately shown he suffered indirect financial losses by reason of the insurer’s conduct. Should the insurer make a goodwill payment to the complainant? Yes. AFCA does not normally award non-financial loss compensation to a complaint that is not a natural person. However, in these specific circumstances, I endorse the insurer’s offer of a $1,500 ‘goodwill’ payment to the complainant company on an ex gratia basis. AFCA does not normally award non-financial loss compensation to a company The complainant seeks compensation for inconvenience and loss of enjoyment caused by claim mismanagement and claim delays. This is akin to compensation for non-financial loss. Under the AFCA rules, non-financial loss compensation is not normally awarded to a complainant that is not a natural person. However, in this instance, the insurer offered to pay the complainant the sum of $1,500 as a ‘goodwill’ payment on an ex gratia basis. The offer was intended, in part, to acknowledge the complainant’s claims experience. I endorse this offer. If the insurer has not already done so, within 14 days notice that the complainant accepts this determination, the insurer must pay the complainant the sum of $1,500 on an ex gratia basis. Why is the outcome fair? I am satisfied the insurer has finalised the repairs of the building damage and should further assess cover for any additional damaged contents upon receipt of the necessary information. I am not satisfied it is fair for the insurer to reimburse the complainant for the additional indirect losses that are claimed. However, the insurer must pay the complainant the sum of $1,500 on an ex gratia basis. Supporting information The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to: the legal principles applicable industry codes or guidance good industry practice previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstance AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider: available documents the recollections of the parties all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.