Determination 1028500
Complainants claimed the insurer caused delay and should pay increased repair costs and further temporary accommodation costs after a planning law change
Summary
Complainants claimed the insurer's delay caused increased fire-repair costs and extra temporary accommodation costs after planning laws changed. AFCA found for the insurer, as the delays resulted from the complainants' added private work and TA was paid to the policy maximum.
The insurer paid the claim related repairs and the maximum TA entitlement, owed no duty to give planning law advice, and did not cause the delay.
Issues
- Delay primary · not upheld
“The delays experienced, and the increased cost of repairs were the result of the private work the complainants added to the SOW.”
- Claim amount dispute secondary · not upheld
“The insurer paid BE the cost of claim related repairs; not required to pay increased amount for claim related repairs.”
- Failure to disclose secondary · not upheld
“insurers do not owe insured's a duty to provide planning law advice”
- Product terms interpretation secondary · not upheld
“It has paid TA costs for the maximum period available under the policy.”
Subjects and remedies
home or building damageno remedy
Text of the determination
Determination
Case number 1028500
Financial firm Allianz Australia Insurance Limited
Determination | Case number: 1028500 Page 2 of 7
Case number: 1028500 8 May 2024
1 Determination overview
1.1 Complaint
The complainants hold home building and contents insurance with the financial firm (insurer).
On 2 September 2020, they lodged a fire damage claim on the policy.
The insurer accepted the claim. On 25 September 2020, its engineer CR provided a scope of
works (SOW) for claim related building repairs. The insurer’s b uilder BE quoted $73,619.91
for the work. The complainants asked that the SOW be expanded to include non claim related
work. On 3 January 2021, CR provided its amended SOW, on which BE quoted $247,973.86.
T he complainants’ development application (DA) was rejected in February 2021 due to non-
provision of requested information. Following a planning law change on 19 March 2021, the
building work was delayed. The complainants say that caused the cost to increase, and
further temporary accommodation (TA) costs to be incurred.
The complainants say if the insurer had proceeded more quickly or had advised them of the
imminent planning law change, the DA would have lodged before 19 March 2021. They want
the insurer to pay the increased cost for the claim related repairs and the further TA costs.
1.2 Issues and key findings
Is the insurer required to pay the increased amount for claim related repairs?
No. The insurer paid BE the cost of claim related repairs. The delays experienced, and the
increased cost of repairs were the result of the private work the complainants added to the
SOW. Further, the insurer did not owe them a duty to provide planning law advice.
Is the insurer required to pay further TA costs?
No. The insurer paid out the TA entitlements under the policy and did not cause the building
work to be delayed.
Why is the outcome fair?
The outcome is fair because the insurer has met its obligations under the policy and is not
responsible for the delay experienced.
1.3 Determination
This determination is in favour of the insurer.
As the insurer has met its policy obligations in relation to the claim, it is not required to take
any further action.
Determination | Case number: 1028500 Page 3 of 7
2 Reasons for determination
2.1 Is the insurer required to pay an increased amount for claim
related repairs?
No. The insurer paid BE the cost of claim related repairs. The delays experienced, and the
increased cost of repairs were the result of the private work the complainants added to the
SOW. Further, the insurer did not owe them a duty to provide planning law advice.
Complainants say insurer caused delay
Subject to the terms and conditions set out in the certificate of insurance and the product
disclosure statement (PDS), the policy covers the complainants for accidental damage to their
home. It is not in dispute that their home was accidentally damaged by fire on 2 September
2020. The insurer accepted their resultant claim.
On 2 October 2020, a DA was lodged with the relevant local council (LC) based on CR’s
claim related repairs SOW dated 25 September 2020.
On 26 October 2020, LC wrote to the complainants, care of CR, requesting more information
including a scaled site plan. The letter stated that a response was required within 30 days,
failing which the DA would be refused.
The complainants say:
that a site plan covering the claim related repairs and the additional work they had
requested was provided by building designer MF on 3 December 2020
despite CR’s amended SOW being available from 3 January 2021, a response was still not
provided to LC’s request for information
on 18 February 2021, they approved BE’s updated quote dat ed 10 February 2021 based
on CR’s amended SOW
on 18 February 2021, LC notified them the DA had been refused due to non-provision of
the information it had requested
on 19 March 2021, planning laws changed
on 22 March 2021, they were advised the insurer had authorised repairs to proceed
due to the planning new changes, they had to make significant changes to their plans to be
complaint, which caused delay and increased cost.
According to the complainants, the process to change planning laws began in 2016 and
involved gradual implementation commencing from 2019. They say the insurer and the
external entities it engaged:
did not advise of the change in planning laws that they must / should have known
about. They, therefore, should have relodged the planning approval prior to 19
March 2021, or started the drafting process on 1 December 2020 to reflect the
new planning laws.
The complainants refer to recommendation 26 of the Commonwealth G overnment’s Financial
System Inquiry Final Report (2014) is ‘ Improve guidance (including tools and calculators) and
disclosure for general insurance, especially in relation to home insurance ’ (recommendation
26).
Determination | Case number: 1028500 Page 4 of 7
The recommendation’s description includes ‘t he general insurance industry should enhance
existing tools and calculators for home insurance, including providing up-to-date information
about building costs and building code changes ’ .
The complainants submit:
This recommendation makes it clear that home insurance providers must give up
to date information regarding building code changes. Clearly [insurer] and [it’s]
associates have not done this, and this negligence is the cause of the building
delays that my complaint is based on.
The complainants note that BE’s quoted price went from $247,973.86 on 3 January 2021 to
$333,859.26 on 1 October 2021. They say that equates to a 212% increase on the cost per
square metre. On that basis, the adjusted cost for claim related repairs is $156,628.87.
Allowing for the previous $73,619.91 payment, the insurer owes them $83,008.96.
Insurer says it did not cause delay or increased repair costs
The insurer’s claim notes show that after receiving an invoice from BE on 1 April 2022 for the
$73,619.91 cost of claim related repairs, the insurer paid BE that amount on 12 April 2021.
The insurer says that the DA lodged with LC on 2 October 2020 only covered the claim
related repairs. As the complainants requested on 30 October 2020 that extensive unrelated
work be added to the SOW, the DA became redundant.
According to the insurer:
It was not possible to re-lodge the [new] application straight away. Due to the
renovations, new drawings and plans had to be drafted and approved and a new
council application had to be drawn up and submitted. Had the [complainants] not
chosen to change the design of the residence, the original council application
would have likely followed through and been granted.
The insurer notes the following comments from BE:
We submitted a quote to the owners, for the completely revised design on
10/02/21, and did not receive any correspondence until 24/03/21. On the 24 th of
March we were asked to engage [MF] to complete the drawings so an application
could be submitted…. Please note this is after the 19 th of March 2021 so no
party could have lodged the application prior to the 19 th of March 2021 . On
20 th of April, the drawings were completed and sent through to [the complainants],
who approved the drawings the same day. We then started the…application
which was ultimately not accepted due to the changes in planning laws.
BE also advised that:
it was unaware of the upcoming change to the planning laws
it acted in a timely manner, and did not delay relodging the second DA
‘ The owners requested for a complete re-design of their addition to be undertaken and
costed, this was a ll undertaken in a reasonable amount of time’
Determination | Case number: 1028500 Page 5 of 7
the main reason repair costs increased from $247,973.86 to $333,859.26 was that there
was an increase in scope. This included additional items added, which were unrelated to
the claim.
The insurer maintains that it is not responsible for the increased cost of claim related repairs.
Insurer not required to pay increased amount for claim related repairs
Based on the exchanged information, I am not satisfied that it would be reasonable to require
the insurer to pay an increased amount for claim related repairs. This is because:
the insurer paid BE the cost of claim related repairs promptly after the works as a whole
were approved
the information BE has provided supports a finding that the delays experienced, and the
increased cost of repairs, were the result of the private work the complainants added to the
SOW
once the complainants requested the additional work, the original DA was redundant so
there was no point responding to LC’s request for information
the thirty day period in which to respond to that request expired on 25 November 2020,
before MF’s site plan and CR’s updated SOW were available
insurers do not owe insured’s a duty to provide planning law advice
recommendation 26 related to information suggested an insurer make available to
consumers when a policy is taken out or renewed so as to reduce the risk of
underinsurance
recommendation 26 was not enacted or otherwise codified.
2.2 Is the insurer required to pay further TA costs?
No. The insurer paid out the TA entitlements under the policy and did not cause the building
work to be delayed.
Policy covers TA costs in specified circumstances
As set out on page 16 of the PDS, if an insured home is unable to be lived in after sustaining
covered loss or damage, the insurer will pay TA costs as an additional benefit under the
policy. The insurer will pay TA costs for up to 12 months. The maximum amount payable is
20% of the building sum insured. In the complainants ’ case, that amounts to $78,647.40.
The insurer has paid the complainants 12 months of TA costs, totalling $52,489.90.
Insurer is not required to pay further TA costs
The complainants say that due to the delays it has caused, the insurer should pay them an
additional $13,000 in TA costs.
The insurer says that it is likely that the claim related repairs would have been completed
within 12 months, and that it is not responsible for the delays experienced.
I agree with the insurer. It has paid TA costs for the maximum period available under the
policy. For the reasons set out in section 2.1 above, I am not satisfied that it caused delays
such that it should pay TA costs outside the policy terms.
Determination | Case number: 1028500 Page 6 of 7
2.3 Why is the outcome fair?
The outcome is fair because the insurer has met its obligations under the policy and is not
responsible for the delay experienced.
Determination | Case number: 1028500 Page 7 of 7
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. I have reviewed and considered
all the information the parties have provided.
While the parties have raised several issues in their submissions, I have restricted this
determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no
relevant documents, we will decide what most likely occurred based on the available
information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim
cannot be established.