Cash settlement amount and scope of works for escape of liquid claim, plus delay and non-financial loss
Text of the determination
Determination
Case number 1027404
Financial firm AAI Limited
Determination | Case number: 1027404 Page 2 of 8
Case number: 1027404 2 May 2024
1 Determination overview
1.1 Complaint
The complainant holds home and contents insurance with the financial firm (insurer). In
August 2023, he lodged a claim after water surcharged from the bathroom, laundry and toilet.
The insurer accepted the claim and sought to cash settle based on a scope of works (SOW)
from builder AR, as there was non-claim related damage present. It later said AR could attend
to repairs. It also proposed a dual assessment and to obtain an SOW from another builder.
The complainant has lost faith in the insurer. He says AR’s SOW is insufficient and under-
priced. He wants a cash settlement based on an SOW from builder SB, plus allowances for
contingencies and temporary accommodation (TA). He seeks stress-related compensation.
1.2 Issues and key findings
How is the claim to be resolved?
It is reasonable that the claim is cash settled given the parties’ deteriorated rel ationship.
T he insurer has conceded AR’s SOW missed items and may be considered inadequate, so it
is reasonable that the settlement is mostly based on SB’s SOW . However, the allowances for
replacing the undamaged kitchen floor are to be removed as they do not meet the policy’s
‘same room’ requirements to be covered. A 15% contingencies uplift is to be applied.
Based on the exchanged information, a ten-week allowance for TA is reasonable. The insurer
is to pay the complainant $20,750, the midpoint of the pricing it provided in late March 2024.
Is non-financial loss compensation payable?
Yes. The insurer has caused some unreasonable delay, mostly by basing its claim response
on an SOW it belatedly accepted was unreliable. The delay has caused the complainant and
his wife (who is also an insured) stress and inconvenience. The insurer is to pay $1,500.
Why is the outcome fair?
It is fair that the claim is cash settled based on an actionable quote that adequately addresses
claim-related damage. As the insurer has unreasonably caused stress and inconvenience, it
is fair that it pays non-financial loss compensation.
1.3 Determination
This determination is substantially in favour of the complainant.
If the complainant provides written notice (notice) he accepts this determination:
the parties are to take the steps outlined in section 2.1 below to cash settle the claim, and
within 14 days of receiving the notice, the insurer is to pay him:
> $20,750 as a TA cash settlement
> a total of $1,500 in non-financial loss compensation.
Determination | Case number: 1027404 Page 3 of 8
2 Reasons for determination
2.1 How is the claim to be resolved?
It is reasonable that the claim is cash settled given the parties’ deteriorated relationship.
The insur er has conceded AR’s SOW missed items and may be considered inadequate, so it
is reasonable that the settlement is mostly based on SB’s SOW . However, the allowances for
replacing the undamaged kitchen floor are to be removed as they do not meet the policy’ s
‘same room’ requirements to be covered. A 15% contingencies uplift is to be applied.
Based on the exchanged information, a ten-week allowance for TA is reasonable. The insurer
is to pay the complainant $20,750, the midpoint of the pricing it provided in late March 2024.
Background circumstances
Subject to the terms and conditions set out in the certificate of insurance and the product
disclosure statement (PDS), policy held by the complainant and his wife covers damage to
their home caused by a listed insured event during the period of insurance. The listed insured
events include ‘Escape of liquid’ (EOL).
On 7 August 2023, the complainant notified the insurer that the day before water had
surcharged from the main bathroom, laundry and toilet/powder room and had flowed through
the house. After inspecting the home, AR advised the insurer that the EOL had been caused
by tree root intrusion blocking the sewer line.
On 7 September 2023, the insurer informed the complainant the claim had been accepted but
would be cash settled due to the presence of maintenance issues and the presence of non-
claim related mould on the laundry wall. The insur er proposed to rely on AR’s itemised SOW
estimating repair costs at $53,600.02.
The complainant was dissatisfied with the ins urer’s cash settlemen t proposal. He obtained an
SOW dated 19 September 2023 from SB estimating repair costs at $118,179.37. SB also
provided written commentary on AR’s SOW, describing it as ‘inaccurate and severely
understated’. SB itemised its concerns.
T he insurer’s assessor concluded that SB’s SOW was excessive. The assessor maintained
that the claim had to be cash settled due to the maintenance issues, non-claim-related
damage and as there would be matching issues between the flooring to be replaced and the
non- damaged flooring. The assessor said AR’s updated $53,979.52 quote was reasonable.
In response, the complainant provided SB’s adjusted SOW dated 9 October 2023 quoting
$115,341.37. He also submitted an undated SOW/quote from builder EC totalling $126,467.
The insurer considered the complainant’s SOWs to be unreasonable. To progress the matter,
it proposed a dual assessment take place. The complainant was initially agreeable but
because mutually convenient dates could not be identified and the deteri oration of the parties’
relationship, the dual assessment did not occur.
On 6 December 2023, the insurer said it was willing to ‘accept upgrades to [the] repairs in
order to make them compliant at [the insurer’s ] expense and to conduct the works with the
mould in the laundry…’. AR would therefore be able to attend to repairs.
Determination | Case number: 1027404 Page 4 of 8
However, noting the complainant’s concerns with AR, the insurer offered to arrange for
another of its panel builders to provide a quote bas ed on AR’s updated SOW. That SOW
included bathroom floor tiling and the mould remediation and totalled $54,914.35.
T o deal with one of the insurer’s objections to SB’s SOW, on 23 January 2024 the
complainant provided it with a version prepared on 21 January 2024 with detailed itemisation.
In an email dated 12 February 2024, AR provided comments on SB’s itemised SOW. AR
conceded that its previous SOW was missing items, and also noted some items were to be
cash settled. AR provided an updated SOW quoting $56,059.19.
On 20 February 2024, the insurer offered to engage independent building consultant QT to
prepare a SOW on which SB and a panel builder other than AR could provide quotes.
The complainant provided a letter dated 16 February 2024 from SB outlining its continuing
concerns with AR’s SOW. In its response dated 4 March 2024, the insurer submitted that:
it does not dispute that the scope of works provided by [AR] has missed items or
may be considered to be inadequate. The Insurer submits [SB] have not provided
a quote in a format line-by-line in order for the Insurer to properly assess the
proposed repair methods or costings for fair and reasonable and to ensure the
proposed repairs meet the policy terms, conditions, limitations, and exclusions to
cover and are in accordance with the Australian Building Standards and National
Construction Codes applicable.
The Insurer agrees that questions remain outstanding on the information provided
by [SB] and [AR] which the Insurer has not had the opportunity to review and
assess.
The insurer reiterated its proposals for a dual assessment and to obtain a SOW from QT.
The complainant has engaged SB to undertake the repairs pursuant to its SOW. The works
are due to start imminently (if they have not already commenced).
TA will be required
As set out on page 57 of the PDS, the policy covers the cost of TA for up to 52 weeks where
the insured property is rendered unliveable due to claim related damage, until the property is
returned to a liveable state. The coverage does not extend to pet boarding.
There is no dispute that the complainant and his family will require TA during repairs.
SB previously provided a detailed project schedule based on repairs commencing on 10
October 2023. The schedule indicates repairs would be concluded on 6 December 2023. That
is a 58-day period (just over eight weeks).
The complainant has provided a long stay quote dated 21 March 2024 for 70 days (ten
weeks). Inclusive of pet and parking fees, the quote comes to $51,100.
The insurer’s assessor has estimated repairs will take ten to twelve weeks. The insurer says it
does not use serviced apartments for long term stays, but places customers in Airbnb or other
rental homes. On 27 March 2024, the insurer provided three pet friendly examples in the
c omplainant’s local area. The cost for a ten-week period ranged from $16,562 to $24,984.82.
Determination | Case number: 1027404 Page 5 of 8
Reasonable for claim to be cash settled
It appears the parties are agreeable to the claim being cash settled. In any event, I am
satisfied that it should be, based on the exchanged information. While the insurer wants to
obtain another SOW, the relationship between the parties has deteriorated to the point where
further extended interactions between them will very likely result in additional disputes.
A cash settlement must be based on a reasonable quote for claim related repairs, actionable
by a retail customer. An uplift is then typically applied to the quoted amount to allow for
contingencies and the loss of the lifetime guarantee that applies to insurer approved repairs.
Cash settlement to be mostly b ased on SB’s SOW
The insurer has conceded that AR’s SOW is missing items and may be regarded as
inadequate. This means the only available SOWs to be considered are those of SB and EC.
The complainant seeks a cash settl ement based SB’s SOW, being the lower of the two.
The insurer previously objected to three main categories of repair in SB’s SOW, being to:
the bathroom and waterproofing
cabinetry and stone benchtop
the kitchen.
However, on 18 April 2024, the insurer said ‘it agreed to settlement in relation to the bathroom
and waterproofing and acknowledges the quote provided by its preferred repairer was
insufficient in this respect’.
The issue in relation to the cabinetry and benchtop is whether the cabinetry can be repaired
with the benchtop either propped up or removed and reinstated, then the drawers and doors
reinstated. The insurer says that is possible most of the time, and that the policy does not
respond until such time as damage actually occurs.
In a letter dated 16 February 2024, SB said it had been advised by two cabinetmakers that:
there is no possibility the carcass of the cabinetry can be replaced while using the
same doors and drawers. The fixings and alignment will never allow this to
completed to a professional standard and they would not be able to provide a
warranty.
They have also advised that as the benchtop is both glued and screwed to the
substrates and would be impossible to remove without cracking the stone
particularly around weak spots where cuts outs for plumbing exist.
Noting SB has obtained specific advice from two specialists, I am satisfied that other than in
the kitchen, the cabinetry and benchtop work SB has listed in its SOW is to be included as
part of the cash settlement.
The kitchen was not damaged. However, the parties disagree on whether the insurer is
nevertheless obliged to replace its flooring. The PDS confirms on page 79 that if it cannot
match materials with undamaged parts of the building, the insurer will rebuild/repair th e
undamaged parts to achieve a uniform appearance in limited circumstances.
One of those circumstances is where there is continuously joined damaged and undamaged
flooring in the ‘same room’. The PDS states on pages 81 and 82 that:
‘same room’ is a room st arting and finishing at:
Determination | Case number: 1027404 Page 6 of 8
> its nearest walls
> nearest doorway, archway or similar opening of any width
> a change in floor covering
a hallway next to a room is not the same room, even if it has the same continuously joined
floor covering
any archway or similar opening separates a room unless it is a combined lounge-dining
room.
The complainant says the kitchen is part of an open plan area where the ceiling and floor runs
through both without any architectural break. He has provided photos in support of his
position. The insurer says the photos in fact prove the kitchen does not meet the definition of
‘same room’.
Having carefully examined the photos, I agree with the insurer. There are timber beams
running up both sides of the opening into the kitchen of the same style and colour of the door
architraves for three nearby rooms. Further, the continuously joined floor covering runs from a
hallway into the kitchen.
SB’s SOW includes specific itemised allowances for the kitchen as wel l as more generalised
items that would or may include allowances relating to the kitchen. These include preliminary
works and items such as disconnecting and reconnecting plumbing. None of the kitchen items
and related items/allowances should be included in the cash settlement.
As EC’s quot e price was similar to that of SB, and as SB remains prepared to undertake the
works based on its quote, I am satisfied SB’s SOW and pricing is otherwise reasonable.
I also consider it fair to allow an uplift for contingencies and the loss of the lifetime guarantee
that applies to insurer approved repairs. The complainant seeks an uplift of 20% to 25%. The
insurer submits that 10% is sufficient. I consider 15% to be reasonable, based on the
background circumstances outlined above.
SB has estimated repairs will take 58 days. If the 15% contingencies uplift is applied, that
period becomes just under ten weeks. The insurer recently provided costings for a ten-week
TA period ranging from $16,562 to $24,984.82. The mid-point of that range is approximately
$20,750. I am satisfied it is reasonable that the insurer pays the complainant that amount.
If the complainant accepts this determination, the following steps are to be taken to enable
cash settlement of the repair costs:
the complainant is to obtain from SB an updated version of its SOW which does not
include the kitchen items or any related items/allowances
within 14 days of receiving from the complainant the updated SOW, the insurer is to pay
him the quoted amount plus a 15% uplift.
I understand that the insurer has already collected the policy excess. If that is not correct, it is
permitted to deduct the excess from the repair cash settlement payment.
2.2 Is non-financial loss compensation payable?
Yes. The insurer has unreasonably caused some delay, mostly by basing its claim response
on an SOW it belatedly accepted was unreliable. The delay has caused the complainant and
his wife (who is also an insured) stress and inconvenience. The insurer is to pay $1,500.
AFCA can award compensation for poor claim handling
Determination | Case number: 1027404 Page 7 of 8
Under the applicable AFCA Rules, we may award compensation (capped at $5,400) for non-
financial loss where a complainant has suffered an unusual degree or extent of physical
inconvenience, time taken to resolve the situation or interference with their expectation of
enjoyment or peace of mind.
In determining whether it is appropriate to award non-financial loss compensation, AFCA
considers whether a complainant’s conduct has contributed to their loss. If so, it may be
appropriate to discount the award of compensation that might otherwise have been made.
Insurer has unreasonably caused stress and inconvenience
The complainant says the insurer has unreasonably delayed progressing the claim, has
communicated poorly, and has at times acted in a disingenuous manner. He says the
insurer’s conduct has severely impacted his whole family, including their health.
It is clear the claim has not progressed smoothly and there have been delays. I consider both
parties have contributed to the issues experienced, but the insurer more so by basing its
claim response on an SOW it belatedly accepted was unreliable. I accept that has caused the
complainant and his family stress and inconvenience.
In the circumstances, I am satisfied it is reasonable to require the insurer to pay a total of
$1,500 in non-financial loss compensation.
2.3 Why is the outcome fair?
It is fair that the claim is cash settled based on an actionable quote that adequately addresses
claim-related damage. As the insurer has unreasonably caused stress and inconvenience, it
is fair that it pays non-financial loss compensation.
Determination | Case number: 1027404 Page 8 of 8
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. I have reviewed and considered
all the information the parties have provided.
While the parties have raised several issues in their submissions, I have restricted this
determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no
relevant documents, we will decide what most likely occurred based on the avai lable
information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim
cannot be established.