Claim for property damage (cracking and water ingress) declined on the basis that excluded causes were the proximate cause

FirmQBE
Decided2024-04-15
ProductGeneral Insurance · Strata
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The complainant claimed for cracking and water damage to his strata property, attributing it to an earthquake and nearby construction. AFCA found the insurer was entitled to decline the claim as the damage was caused by excluded factors.

Relying on the forensic engineer's evidence, the insurer showed on the balance of probabilities that the proximate cause was excluded factors (long-term ground movement, shrinkage, defective waterproofing and workmanship) and not the earthquake or construction.

Issues

Subjects and remedies

home or building damagenatural disasterno remedy

Related

All QBE determinations · Find similar determinations

Text of the determination

Determination Case number 1018953 Financial firm QBE Insurance (Australia) Limited Determination | Case number: 1018953 Page 2 of 8 Case number: 1018953 15 April 2024 1 Determination overview 1.1 Complaint The complainant lodged a claim for property damage under a residential strata insurance policy underwritten by the financial firm (insurer). The complainant says the damage was caused by earthquake and/or construction work near the property. The insurer denied the claim. It says the damage was caused by factors excluded by the policy. The complainant disagrees with the insurer’s decision. He wants the insurer to repair the claimed damage. 1.2 Issues and key findings Is the insurer entitled to decline the claim? Yes. Based on the exchanged information, the insurer has established, it is more likely than not, the damage was principally caused by excluded factors. Why is the outcome fair? The outcome is fair because the insurer has established, on the balance of probabilities, that the damage was caused by factors excluded by the policy. Accordingly, it would not be fair to require the insurer to cover the damage. 1.3 Determination This determination is in favour of the insurer. The insurer is entitled to deny the claim. Determination | Case number: 1018953 Page 3 of 8 2 Reasons for determination 2.1 Is the insurer entitled to decline the claim? Yes. Based on the exchanged information, the insurer has established, it is more likely than not, the damage was principally caused by excluded factors. Complainant must show a claimable loss under the policy The complainant is required to show, on the balance of probabilities (that is more likely than not), they he suffered a claimable loss under the policy. This means he must show the loss was caused by a risk for which he is insured. Subject to the terms and conditions set out in the Product Disclosure Statement (PDS), the complainant’s policy covers accidental loss and damage to the insured property caused by an incident during the policy period. The PDS defines ‘damaged, damaged’ as ‘any partial or total accidental physical loss of, or destruction of property from any sudden and accidental cause not otherwise excluded by this Policy’. In June 2023, a 4.6 magnitude earthquake occurred near Rawson, Victoria. At this time, construction work was taking place 6-8m from the complainant’s property. This work included machinery digging trenches, laying 1150mm pipes, earth compaction and large trucks driving to and from the construction site. The complainant says that after the earthquake he noticed cracking and movement damage to the porch slab and pillars. He says the building movement caused gaps to form causing water damage. The complainant attributes the damage to the earthquake, the construction work or a combination of these. If the complainant proves the existence of a claimable loss the insurer is liable for the loss unless it shows an exclusion or limiting condition applies. The insurer has the onus of proving on the balance of probabilities the application of the exclusion or condition. The policy contains the following relevant exclusions: 1. We will not pay for Damage caused by or arising directly or indirectly from : […] f. vibration or from the removal or weakening of or interference with the support of land or buildings or any other property, Erosion or Earth Movement. However, we will pay if the Damage is due to: i. earthquake or seismological disturbance, Tsunami, explosion, physical impact by aircraft; i. inherent defect or latent defect m. normal settling, creeping, heaving, seepage, shrinkage, or expansion in buildings, foundations/footings, walls, bridges, roadways, kerbing, driveways, paths, garden borders and other structural improvements’ ‘3. We will not pay for: […] c . the cost of rectifying faulty or defective materials or faulty or defective workmanship, design or specification Determination | Case number: 1018953 Page 4 of 8 Proximate cause must be determined In a general insurance claim, the term ‘proximate cause’ is used to describe whether an event is the cause of the loss or damage. The proximate cause of a loss is the dominant, effective or operative cause. It does not have to be the first, the last or the only cause. If there are several causes, each should be examined to determine whether it is a dominant, effective or operative cause of the loss. For example, if one cause would have caused the loss on its own, and the other cause would not have caused the loss without the first, then the first is the proximate cause. Insurer relies on expert reports to decline the claim The insurer relies on reports by structural/forensic engineer, LC, who inspected the property on 27 July 2023 . LC’s reports are dated 31 July 2023, 30 August 2023, 14 November 2023, 7 December 2023, 24 January 2024 and 2 February 2024 and say:  borehole soil tests showed stiff moist clay at 500mm  the property has site classification as P (problem) due to reactive clay soil and large trees close by  the distance from the epicentre meant the shaking experienced would have been no more than MMI IV (light) on the Modified Mercalli Intensity (MMI) scale and that the peak ground acceleration of 0.010g was recorded in the locality of the property.  the lateral stability and bracing analysis of the structure shows the building can resist maximum lateral force imposed by that level of ground acceleration and would not have sustained damage  the nearby construction is below ground infrastructure pipe laying and is a standard and common project and construction methodology. That work is within the lateral design capacity of the building and would not be expected to cause the claimed damage  movement and damage to porch pier was not caused by excavation or vibration from construction  the cracking damage is consistent with stress cracks from bending and shrinkage and not consistent with earthquake or vibration from construction  cracking to porch caused by building movement due to one or more of the following factors: > long term differential footing movement due to differential moisture content variation in the reactive foundations > inadequate founding depth of the footing system given proximity to large trees > long term dilapidation and normal building stress  it made its assessment based on the relevant building codes that were in place at the time it was constructed  the issuing of an occupancy certificate does not certify that a structure is fully compliant in every aspect. It therefore does not mean that waterproofing is compliant.  water ingress was caused by inadequate installation of the waterproofing system. In particular, the pattern of water ingress on the balcony identifies inadequate or non- compliant detailing of waterproofing termination at the edges  pavement cracking caused by inadequate placement and positioning of reinforcement with a section of the pavement along the slab edge being unreinforced allowing the concrete to fracture  cracking in the façade is visible in the 2017 sales photo  past repairs of pavement and balcony wall cracks confirm the damage and movement has been long-term Determination | Case number: 1018953 Page 5 of 8  water ingress can be latent and can progress without the owner noticing. Moisture damage to the porch ceiling is clearly long-term given the extent of damage. The damage pre-dates the earthquake and excavation work. In any event, waterproofing is flexible and able to withstand claimed events  trees are a contributing factor to expected ground movement. Australian Standard 2870 identifies the influence zone within which tree roots are considered an adverse effect on the soil causing problem site classification. The trees reference d in LC’s earlier reports are within that influence zone. Complainant says earthquake and construction caused the damage The complainant strenuously disagrees wi th the insurer’s claim denial. He says that LC ’s conclusions are based on insufficient inspection, testing, information, are inconsistent and not objective. He has provided numerous submissions and attachments including photos, a video, an extract from plumber, an email from arborist, various permits and certificate and statements from neighbours. He says:  the damage to pillars was caused by the earthquake in combination with heavy construction in front of his property, exacerbated by problematic foundation soil (clay). The complainant says these factors caused a significant shift to the pillars, which in turn has caused gaps in the horizontal/vertical tiles of the balcony, via which the water leaks downwards. He says this the water damage seen by LC was 30 days after the claim during which time heavy rain fell and the construction dirt was flushed through the gaps  heavy machinery including compactors was used in the construction. He and his neighbours felt vibrations in their houses from the construction work  the trees could not have impacted the property, they are further away from the property than construction site  the balcony was constructed in 2000-2001 and any poor workmanship such as to cause cracking or water damage would have been seen earlier  the insurer and/or its engineer should have undertaken further testing and obtained reports from arborist, plumber, seismologist and geologist  LC’s inspection was too brief and inadequate and did not see the balcony from above  LC’s assessment was inadequate in numerous respects including assessing the property using incorrect standards, failing to examine photos of the construction work, disregarding the arborist advice, not making enquiries with the department responsible for the construction work and failing to obtain structural document about his property  There was no cracking damage before the earthquake and construction work. He provides 2017 photos of the pillar with no damage and video in which no cracking damage is seen  damage due to ground movement would have caused more major damage, and  there were no Australian Standards that applied to balcony waterproofing at the time the property was constructed. It follows that the waterproofing could not have not complied with those standards. Further, as the building passed inspections and an occupancy certificate was obtained, it could not be defective. The complainant provided an email from arborist, MG, dated 22 October 2023 which says:  he inspected a tree near the property  there was no evidence of roots close to building  the tree is not big enough or close enough to the building to cause any issues, and  the cracks were on the second story which would not be caused by tree roots. The complainant provided an extract of plumber, LL, who found there was a storm water pipe holding water proximate to his property and an image of this. Determination | Case number: 1018953 Page 6 of 8 The complainant provided a statutory declaration from on neighbour and a letter another providing information about the size of the trenches, vibrations felt and new damage one neighbour found in their property. Insurer is entitled to deny the claim While the parties have raised a number of issues in their submissions, I have restricted this determination to the issues that are relevant to the outcome. Based on the exchanged information, I am satisfied the insurer has established, it is more likely than not, that the proximate cause of the damage to the property are excluded factors. These include the failure of the waterproofing, long-term ground movement, gradual deterioration and wear and tear issues. The causes are excluded by the policy. I make this finding because:  I am persuaded by LC’s evidence. It has set out analysis and methodology and some supporting images. I am satisfied it is appropriately qualified to provide expert opinion  LC unequivocally concludes that neither the earthquake nor the construction was the cause of the damage claimed  the ShakeMap shows an earthquake’s intensity decreases with increasing distance from the epicentre. The MMI scale is commonly used to describe the damage and felt effects of an earthquake at a given location. The earthquake intensity using ShakeMap was assessed at MMI IV (light) which indicates the earthquake forces are not expected to cause damage to buildings  LC says the peak ground acceleration of 0.010g was recorded in the locality of the property. Having investigated the house, is confident it understands the construction methodology, and found the structure would not sustain damage from such earthquake loads . LC’s analysis of crack patterns found they were not consistent with earthquake imposed forces  LC considered the excavation, vibration and proximity of the nearby construction work as well as assessing the nature of movement and cracking of the property. It concluded it was not caused by the construction work (laying major water pipes). It says that was based on engineering expectations and norms used in below ground infrastructure pipe laying which, it says, is a standard and common project and construction methodology. Given the absence of information indicating non-standard or uncommon construction methods were used, I am satisfied this is a reasonable approach  I am satisfied that the proximate cause of the water ingress was the failure of the waterproofing, not earthquake or construction. The extent of the moisture deterioration shows it to be a long-term problem. LC says waterproofing systems are manufactured to have flexibility to accommodate building movement. I am satisfied that, even if compliant with Australian Standards, the exchanged information shows the water ingress damage was caused by inadequate installation of the waterproofing system. In particular, the pattern of water ingress on balcony identifies inadequate detailing of waterproofing termination at the edges. In any event, the weight of the exchanged information does not show that the water ingress was, more likely than not, caused by earthquake, the effects of nearby construction or other sudden and accidental cause  I am persuaded by LC’s evidence that the proximate cause of damage to the porch was stresses induced from long term building movement due to one or more of: long term differential footing movement, inadequate footing depth, and/or long-term dilapidation and normal building stress Determination | Case number: 1018953 Page 7 of 8  I am persuaded by LC’s evidence that the proximate cause of cracking of the concrete porch slab was due to long term ground movement, concrete shrinkage stress cracking and inadequate installation of the reinforcement  I accept LC’s evidence that an occupancy certificate does not establish that a property has no defects  I consider a structural engineer is more qualified than an arborist to assess the effects tree roots can have on a built structure  LC has provided a 2017 image of the property that shows a number of cracks in the render at the top of the balcony. LC also provides photos of a crack and prior repair of concrete porch slab and concrete piers of front porch. This supports LC’s conclusion that movement was already occurring when the complainant purchased the property and this has continued, and  while I accept the information provided b y the complainant’s neighbours, I give greater weight to evidence from a forensic structural engineer about the cause of the damage. Therefore, based on the information provided, it has not been shown that the damage was proximately caused by the earthquake, construction work or combination of both, or other sudden and accidental cause. Rather, it is more likely than not that the damage was due to excluded factors of: normal settling, heaving, shrinkage, or expansion in buildings, foundations/footings, together with faulty or defective workmanship, design or specification. 2.2 Why is the outcome fair? The outcome is fair because the insurer has established, on the balance of probabilities, that the damage was caused by factors excluded by the policy. Accordingly, it would not be fair to require the insurer to cover the damage. Determination | Case number: 1018953 Page 8 of 8 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.