Home / QBE / Determination 1012079

Determination 1012079

Cash settlement amount after insurer's builder began repairs then could not complete them

FirmQBE
Decided2024-03-07
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$20,220
Non-financial loss$1,500
Amount claimed$357,829
SourceAFCA PDF

Summary

A family trust claimed flood damage to its holiday home; the insurer's builder stripped the home, then could not repair it due to defects, and the insurer cash settled for about $87,919. AFCA required a higher settlement including strip-out costs and a 25% contingency, plus interest and $1,500 non-financial loss, but rejected the $357,828.52 rebuild quote.

The insurer should have cash settled before starting repairs it could not complete, so fairness requires putting the complainant in the position it would have been in, though the insurer is not liable for pre-existing construction defects or the rebuild.

Issues

Subjects and remedies

home or building damagenatural disastersmall businesspay claimpay interestpay non financial loss

Related

All QBE determinations · Find similar determinations

Text of the determination

Determination Case number 1012079 Financial firm QBE Insurance (Australia) Limited Determination | Case number: 1012079 Page 1 of 6 Case number: 1012079 7 March 2024 1 Determination overview 1.1 Complaint The complainant is a family trust and is represented by JA, one of the trustees. For simplicity, reference to the complainant in this determination includes JA. The complainant holds a home building and contents insurance policy with the financial firm (insurer) for a holiday home. It lodged a claim for flood damage which occurred on 27 February 2022. The insurer accepted the claim. It appointed builder AB to repair the damage. Whilst stripping the home, AB discovered non-compliant building work. It informed the insurer it could not warrant repairs. Work ceased, and the insurer cash settled the claim for $87,419. The complainant believes the payment is insufficient. It provided a quote from builder RB and seeks $357,828.52. The complainant is also unhappy with the handling of the claim. 1.2 Issues and key findings Is the insurer ’s cash settlement fair? No. The insurer elected through its builder to undertake work it could not complete. This prejudiced the complainant. Whilst the repair estimate is fair, the insurer must also pay the cost for the strip out work done and a contingencies uplift of 25%. Is an award of compensation appropriate? Yes. The insurer’s election to start repairs delayed settlement of the claim and caused an unusual degree or extent of physical inconvenience for the complainant. It is fair that the insurer pays non-financial loss compensation of $1,500. Why is the outcome fair? The insurer should not have started repairs, noting it could not finish them. This prejudiced the complainant. It must correct this and compensate the complainant for the distress caused. 1.3 Determination This determination is partially in favour of the complainant. To resolve the claim, the insurer is required to pay the complainant:  $10,059.92 to strip the property  $76,451.38 to repair the damage  a 25% contingencies uplift on the full settlement amount ($21,627.83). This equates to a settlement of $108,139.13. The insurer may deduct the amount it has already paid ($87,919.09), meaning it must pay $20,220.04. The insurer must pay interest on $87,919.09 from 15 March 2022 until 7 March 2023, pursuant to section 57 of the Insurance Contracts Act 1984 (the Act). It is otherwise required to pay interest on the balance of the settlement ($20,220.04) from 15 March 2022 until the date of payment. The insurer must also pay compensation for non-financial loss of $1,500. Determination | Case number: 1012079 Page 2 of 6 2 Reasons for determination 2.1 Is the insurer’s cash settlement fair? No. The insurer elected through its builder to undertake work it could not complete. This prejudiced the complainant. Whilst the repair estimate is fair, the insurer must also pay the cost for the strip out work done and a contingencies uplift of 25%. Insurer’s builder found defects and non -compliant building work in home It is not in dispute the insured building sustained flood damage from the claimed incident or that the insurer is liable for this damage under the policy. The insurer appointed AB to review the damage. AB confirmed about 100mm of water had swept through the home. Damage was caused to the kitchen, dining, living room, hallway, bathroom, laundry/carport and rear patio. There were no reported building defects identified during the initial inspection. AB later informed the insurer (after extensively stripping out the home) there was non- compliant building work present. AB said it could not continue with the required work. Based on this, the insurer changed its position and offered a cash settlement to the complainant. Both parties accept the home had non-compliant building work present. The home has since been demolished. The complainant seeks cover based on RB’s quote ($357,828.52). The insurer paid a cash sett lement based on AB’s quote ($76,451.38). Insurer says the repair work could not be completed or guaranteed After AB informed the insurer it could not continue with the repairs and RB had prepared its quote, the insurer engaged building engineer MB to attend the property. MB provided a report dated 28 September 2022, in which it found:  the home was built in or about 1980  MB does not agree with the RB repair quote as it addresses structural issues not related to the claimed event  the building is ‘not structurally sound and is not built in accordance with the National Construction Code’  the observed defects are due to ‘lack of maintenance, defective and non - compliant works’ . MB noted in its photos that there were signs of long-term water ingress and damage, construction gaps, inappropriately installed struts and other defects. As it did not establish exactly when the building was constructed and what codes were applicable at that time, I am not satisfied MB has proven the construction was non-compliant. However, I accept there are defects and issues present which prevent the insurer from guaranteeing repairs. The insurer paid the complainant $87,919.09 on or about 7 March 2023. This settlement was based on the AB quote and included a 15% contingencies uplift. Complainant says the claimable damage is more extensive The complainant says the amount paid is not representative of its loss. RB says the flood caused significant structural damage and left the home ‘unsafe to be lived in’. It has since been torn down. RB said there were no footings, rotten timber bottom plates, insufficiently constructed load bearing walls, no cyclone tie downs and undersized second storey joists. Determination | Case number: 1012079 Page 3 of 6 RB quoted $357,828.52 to rebuild the home. I accept this quote includes items either already settled under the contents section of the policy or not related to the loss. The complainant notes there is no dispute the flood caused damage and repairs were required. It says the AB quote is not actionable as it would not repair the damage. Given this, the complainant says the RB quote is the only reasonable settlement option, as it is the only actionable quote prepared to address the claimed damage. Decision to strip out the home prejudiced the complainant I accept the home had substantive pre-existing issues, highlighted by MB, AB and RB. I acknowledge the complainant was not aware of these issues prior to the loss. However, I am satisfied the insurer is not liable to cover this damage. This means the insurer is not liable for the amount quoted by RB. This quote essentially covers the cost to rebuild the home. Whilst the water damage was extensive, it did not extend to all areas suggested by RB. I am not satisfied the insurer should be liable for this quote. Whilst I acknowledge the AB quote was not an actionable quote, I accept that it is not possible to obtain such a quote now that the home has been demolished. Broadly, I accept the amount AB quoted was not unreasonable and the complainant has not shown otherwise. I also accept it became impossible to revisit this once the home was demolished. Even so, I am not satisfied the insurer should be permitted to simply limit its liability to the value of the AB repair quote. AB elected to repair the damage and in doing so undertook a partial strip out of the home. If it had properly assessed the risk prior to starting repairs, the insurer should have cash settled the damage. If this was done, the complainant may have looked at other options to conduct repairs. This includes potentially leaving the home to dry out and/or engaging a builder to correct those issues which needed attention. Whether these options were viable or not, I accept they are now not possible. AB’s work at least contributed to this. Therefore, I consider the fair option is to (as much as possible) return the complainant to the position it would have been in but for the work undertaken by AB. Insurer must increase settlement offer to better compensate the complainant If the repairs had not been started by the insurer, I accept the complainant may have looked at other options to repair the damage. This does not mean the insurer is liable for the re-construction of the home. The complainant chose to demolish the home. I am not satisfied this was solely due to AB’s actions or the result of the flood. On balance, I consider it was mostly due to the expert-agreed building and design issues. I accept the insurer’s actions meant the complainant’s rectification options were limited. It meant the complainant considered the only viable option was to demolish the home. Given this, I consider it fair that the insurer be liable to the complainant for the costs to:  undertake the partial strip out of the property ($10,059.92), and  repairing the damage ($76,451.38). Whilst I acknowledge the insurer paid for the strip out work, I consider it was unnecessary and should never have been done. AB should have arranged with the insurer to cash settle the claim if it could not do the repairs. MB notes several issues with the construction which I Determination | Case number: 1012079 Page 4 of 6 consider should have been realised prior to repairs starting. These included (but are not limited to):  the underpitched roof  poorly installed roof struts  the floor being situated at the same height as the external ground level  the absence of any fall from the main home to outside areas  gaps between the sliding door and the substrate  pre-existing damage issues highlighted with the stumps. None of the above issues required stripping of the internal walls to be discovered. All attest to the overall construction concerns. I acknowledge the stripping uncovered other issues with the home, but the above issues meant AB should have realised the home was not appropriate for it to repair. Electing to begin work prejudiced the complainant, because this decision denied it the option to choose how it might want to address the issues. For this reason, I am satisfied the insurer should reimburse the complainant the value of this work ($10,059.92) as part of the settlement. Whilst the work can no longer be re-done, it represents costs incurred by the insurer which left the complainant in a poorer position. Paying the cost of this work to the complainant is a fair way of off-setting this imbalance. Further, I accept such a settlement warranted the payment of a significant contingencies uplift. I am satisfied a 25% allowance is fair on the full sum of the proposed settlement. I acknowledge a contingencies uplift is no longer required, but this amount represents what I consider the insurer should have paid at the outset. I therefore accept the insurer should have paid $86,511.30 plus the contingency. This equates to a settlement of $108,139.13. The quote for the strip out of the property was 15 March 2022. This is when the settlement should have been paid, therefore I am satisfied the insurer is liable for interest from this date. Noting the insurer paid $87,919.09 on 7 March 2023, it must pay interest on that amount from 15 March 2022 until 7 March 2023, pursuant to its requirements under the Act. It is otherwise required to pay interest on the balance of the settlement from 15 March 2022 until the date of payment. 2.2 Is an award of compensation appropriate? Yes. The insurer’s election to start repairs delayed settlement of the claim and caused an unusual degree or extent of physical inconvenience for the complainant. It is fair that the insurer pays non-financial loss compensation of $1,500. AFCA can award compensation for non-financial loss Under our Rules, AFCA can award up to $5,400 compensation for non-financial loss. This must relate to poor claims handling or other actions of the insurer which cause an unusual degree of stress, delay, or inconvenience. We expect complainants to be moderately robust, and we will not award compensation for the ordinary degree of inconvenience involved in making a claim. Insurer must pay compensation of $1,500 to the complainant Noting the complainant is a family trust, I am satisfied it is entitled to be considered for compensation. The insurer raised no objection on this point. Determination | Case number: 1012079 Page 5 of 6 The complainant says it has been unable to use the insured property, which is a family holiday home for more than 12 months. The damage caused by AB meant it was uninhabitable, causing significant distress to the family. I accept the insurer should not have attempted the repair work through AB. A proper and thorough examination of the home should have told the expert this. I also accept this error caused significant delay in relation to the resolution of the claim and distress for the complainant. Given this, I accept compensation should be paid. The complainant is left without a usable holiday home. I acknowledge this is largely due to construction issues for which the insurer is not liable. However, the matter could and should have been resolved with a cash settlement from the outset. Noting the distress suffered by the complainant and that this was avoidable, I consider the insurer must pay compensation for non-financial loss of $1,500. 2.3 Why is the outcome fair? The insurer should not have started repairs, noting it could not finish them. This prejudiced the complainant. It must correct this and compensate the complainant for the distress caused. Determination | Case number: 1012079 Page 6 of 6 3 Supporting information 3.1 The AFCA processes AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.