Determination 1006438
Amount of cash settlement for storm damage claim and non-financial loss for poor claim handling
Summary
The complainant's storm damage claim had been partly accepted, and the insurer offered a cash settlement of $191,363.81 plus an uplift. AFCA found in her favour, ordering a higher cash settlement of $304,842.56 and $5,400 non-financial loss compensation.
A cash settlement must be based on a reasonable quote actionable by a retail customer, so a builder's margin and a higher uplift were added, and poor claim handling and delay justified the maximum non-financial loss award.
Issues
- Claim amount dispute primary · upheld“An 18% builder's margin must be added to the May 2023 quote. A 35% uplift is then to be applied.”
- Poor claim handling secondary · upheld“The insurer's poor claim handling and delays have caused the complainant significant stress and inconvenience.”
- Delay secondary · upheld“The claim has been on foot for four years, which is too long.”
- Poor communication secondary · upheld“Nor has it provided claim notes or other information to establish it has kept the complainant appropriately informed.”
Subjects and remedies
home or building damagenatural disasterthird party authoritypay claimpay non financial loss
Related
Text of the determination
Determination
Case number 1006438
Financial firm QBE Insurance (Australia) Limited
Determination | Case number: 1006438 Page 1 of 6
Case number: 1006438 12 February 2024
1 Determination overview
1.1 Complaint
The complainant holds home building and contents insurance with the financial firm (insurer).
On 20 January 2020, she lodged a storm damage claim, which the insurer partially accepted.
In a claim decision letter dated 28 May 2021, the insurer said the pool fence damage was
excluded as it was due to tree roots, and the pool pump issues were excluded due to wear
and tear.
On 12 September 2022, the insurer’s builder JL quoted $274,393.63 for repairs (September
2022 quote) . On 23 February 2023, the insurer’s building consultant SB raised concerns
about the September 2022 quote. On 30 May 2023, JL provided a revised quote for
$191,363.81 (May 2023 quote).
The insurer has offered the complainant a cash settlement of $191,363.81 plus a
contingencies uplift (initially 15%, then 30%). The complainant says she should receive
$274,393.63 plus a 30% uplift. She is also dissatisfied with the insurer’s claim handling.
1.2 Issues and key findings
Is the insurer to pay more as a cash settlement?
Yes. So that it may be relied on for cash settlement purposes, an 18% builder’s margin must
be added to the May 2023 quote. A 35% uplift is then to be applied, comprising a 10%
allowance for contingencies and a 25% allowance for price increases.
Is non-financial loss compensation payable?
Yes. The insurer’s poor claim handling and delays have caused the complaint significant
stress and inconvenience. It is to pay her $5,400.
Why is the outcome fair?
The September 2022 quote cannot be relied upon as it includes items that are not claim
related. It is therefore fair to formulate a cash settlement offer based on the May 2023 quote,
but with a builder’s margin added and higher than usual uplift. It is also fair that the insurer
compensates the complainant for the significant stress and inconvenience it has caused.
1.3 Determination
This determination is in favour of the complainant.
Within 21 days of receiving written notice the complainant accepts this determination, the
insurer is to pay her:
$304,842.56 ($191,363.81 plus 18% plus 35%) as a cash settlement for the claim. if the
applicable policy excess has not yet been paid, the insurer is entitled to deduct that
amount, and
$5,400.00 in non-financial loss compensation.
Determination | Case number: 1006438 Page 2 of 6
2 Reasons for determination
The complainant is represented by her friend, NM. In this determination, the complainant and
NM are referred to as ‘the complainant’.
2.1 Is the insurer to pay more as a cash settlement?
Yes. So that it may be relied on for cash settlement purposes, an 18% builder’s margin must
be added to the May 2023 quote. A 35% uplift is then to be applied, comprising a 10%
allowance for contingencies and a 25% allowance for price increases.
Insurer has made cash settlement offers
Under the policy terms, the insurer may settle a claim for damage by:
repairing the damage or rebuilding the insured property, or
paying the insured the cost of doing so, to a condition as close as possible to when new.
In choosing the way it will settle a claim, the insurer must act reasonably. In this case, the
insurer has opted to cash settle the claim. I am satisfied that the insurer’s choice is
reasonable given that the complainant has agreed to receive a cash settlement.
The insurer engaged JL to provide a quote for repair costs. JL initially quoted $93,373.71.
After the insurer accepted the pool damage, JL was asked to provide a revised quote based
on a scope of works (SOW) prepared by the insurer’s engineer, MB on 21 June 2021. In the
accompanying report, MB noted:
access to the rear yard for pool removal and associated demolition was:
> restricted on the south east side due to the sloping retaining wall, although that may
prove the favoured option for entry by a small excavator and bobcat (if deemed
necessary). A temporary compacted soil access ramp could be installed
> access was possible on the west side but would involve more invasive disturbance of
the sloping gardens as well as more restorative remediation work
pool removal would involve demolition of the brick coping surround to the pool perimeter,
but it was expected that further surface finish demolition would not be required (subject to
availability and procurement of a pool shell that replicated the existing edge profile)
JL provided a revised quote dated 9 July 2021 for $152,049.23, followed by the September
2022 quote for $274,393.63.
The insurer then appointed building consultant SB, to provide commentary on the September
2022 quote. SB inspected the complainant’s home on 23 January 2023 and reported that:
it considered the allowances to remove/replace the rear rendered retaining block walls,
remove boulders and remove the entire concrete pavement to be excessive. It noted there
were architecture joins in the paving enabling partial removal
construction industry material and labour costs had gone up 20% to 30% in the last year
nevertheless, the quoted $274,393.63 cost was not fair and reasonable
the best way to move forward would be to engage a specialist pool builder to prepare a
SOW/quote for it to review
‘we consider the project to be very complex, with many constraints to take into
consideration during the assessment’
it recommended the pool builder be asked to advise on whether it would be more cost
effective to replace the existing fibreglass pool with a built-in concrete pool.
Determination | Case number: 1006438 Page 3 of 6
The insurer says that it endeavoured to engage a specialist pool builder but encountered
difficulty doing so. The complainant also objected to a possible replacement of her fibreglass
pool with a concrete pool as it would not be ‘like for like’.
The insurer asked JL to revisit its S eptember 2022 quote in light of SB’s comments. As a
result, JL provided the May 2023 quote. JL had removed the following items that were in the
September 2022 quote (all listed amounts are exclusive of GST):
tree lopping six trees (required for access to retaining wall) - $2,880
garden bed excavation and removal (required for access to retaining wall) - $3,300
remove and reinstate four palms to facilitate retaining wall rebuild - $1,200
replace soil behind new retaining wall - $1,980
remove and replace new block retaining wall - $9,600 (NB both quotes refer to a $600
allowance to prop up the existing retaining wall section not damaged or requiring
replacement)
remove and replace external wall tiles to match existing retaining wall section - $3,520
labour to remove concrete covered boulders linked to retaining wall - $1,200
supply and install artificial grass (owner does not want garden bed reinstated) - $3,850
slab installation and surface preparation for synthetic turf - $8,800
allowance for concrete pump to access rear of house - $2,200
redesign fence using existing panels and new hardware (full removal including footings
required to facilitate repairs) - $1,200
remove and replace boundary fence - $6,000
remove and replace retaining wall section along northern pool end - $6,000
allowance for crane to lift pavers to rear of property - $2,200.
In addition, JL reduced the allowance for removal and replacement of external pool pavers,
including ground levelling works down from 62m 2 ($12,400) to 32m 2 ($5,440). The pricing for
individual items did not otherwise change.
In June 2023, the insurer offered to cash settle the claim for $191,363.81. On 7 July 2023, it
offered to also pay a 15% contingencies uplift, in recognition of the difficulty experienced in
engaging a pool specialist.
On 29 November 2023, the insurer said it had recently received a quote from builder AD, who
was not prepared to attend to repairs. The insurer said in the circumstances, it would increase
the contingencies allowance to 30%.
Compl ainant says the insurer’s latest offer is insufficient
The complainant says the insurer’s offer to pay her $191,363.81 plus a 30% contingencies
uplift is insufficient. She says the September 2022 quote better reflects the scope of claim
related repairs required.
She also questions the validity of the costings in the May 2023, given the lack of increase to
individual item pricing, despite the September 2022 quote being prepared more than eight
months earlier.
The complainant wants to be paid a cash settlement of $274,393.63 plus a 30% uplift.
Insurer is to pay a higher cash settlement
A cash settlement must be based on a reasonable quote for claim related repairs, actionable
by a retail customer. An uplift is then to be applied to the quoted amount to allow for
contingencies and the loss of the lifetime guarantee that applies to insurer approved repairs.
Determination | Case number: 1006438 Page 4 of 6
I acknowledge that some of the items JL removed from the September 2022 quote when it
prepared the May 2023 quote are more likely than not:
excluded (‘damage which is caused directly or indirectly by…roots from trees…’)
unnecessary (for example, full concrete removal, noting the comments by MB and SB)
not claim related (for example, the complainant’s request for the garden bed to be replaced
with artificial turf).
On the other hand, some of the changes between the two quotes are not adequately
explained. For example, why would a crane not be needed to lift 32m 2 of tiles? The insurer’s
provision of limited information despite AFCA’s requests for more, has not assisted.
More concerning is the lack of pricing increases between the two quotes. I especially note
SB’s observation that prices for labour and materials have increased by 20% to 30%.
Further, I am not satisfied that either the September 2022 quote or the May 2023 quote would
be actionable by a retail customer such as the complainant. Neither quote included a builder’s
mark up, which is a percentage charged to consumers.
The insurer did not provide a copy of AD’s quote to AFCA. For that reason, and as AD
specifically indicated it was not prepared to do the work, the insurer may not rely on AD’s
quote. However, the complainant has provided a copy and I note that AD included a 18%
builder’s margin. That is within the typical range of 15% to 19%.
The claim has been on foot for four years, which is too long. Understandably, the complainant
wants it finalised as soon as possible. Given the insurer’s poor claim handling to date, I am
not satisfied giving it another opportunity to undertake investigations would be reasonable. I
also consider that ongoing interactions between the parties will result in further disputes.
Accordingly, based on the exchanged information and so as to promptly bring the claim to a
fair and reasonable conclusion, the insurer is to pay a cash settlement as follows:
May 2023 quote $191,363.81
Plus 18% builder’s margin $34,445.49
Plus 35% uplift (comprised of 10% for
contingencies and 25% for price increases)
$79,033.26
Total $304,842.56
2.2 Is non-financial loss compensation payable?
Yes. The insurer’s poor claim handling and delays have caused the complaint significant
stress and inconvenience. It is to pay her $5,400.
AFCA can award compensation for poor claim handling
Under paragraph D.3 of the AFCA Rules, we may award compensation for non-financial loss
(capped at $5,400 per claim) where the insurer’s actions have caused a complainant an
unusual amount of:
physical inconvenience
time taken to resolve the situation
interference with the complainant’s expectation of enjoyment or peace of mind.
Determination | Case number: 1006438 Page 5 of 6
Insurer has caused major stress and inconvenience
The complainant says the insurer’s delays, poor claim handling and miscommunication have
caused her major stress and inconvenience. She emphasises the severe anxiety and
financial hardship she has experienced.
The insurer deems the complainant’s request for compensation to be unreasonable. It says it
has not inordinately delayed the claim. It says the delays are due to difficulties sourcing a
pool building specialist, the complex issues involved, and the complainant refusing to allow its
trades access to her home (seemingly, from around mid 2023).
The insurer also notes that pursuant to an agreement reached in June 2021 to resolve a
previous complaint concerning the claim, it has already paid the complainant $3,500 in non-
financial loss compensation.
I do not find the insurer’s submissions p ersuasive. The claim has taken too long to resolve.
The complainant has been forced to make numerous prior complaints. The insurer has not
provided documents to show the extent of steps taken to retain a pool builder. Nor has it
provided claim notes or other information to establish it has kept the complaint appropriately
informed of developments.
The insurer’s previous agreement to pay $3,500 in non -financial loss compensation does not
assist the insurer. If anything, it indicates the insurer accepted there were issues with its claim
handling more than 2.5 years ago. Nevertheless, the issues and delays have continued.
I accept that the complainant’s claim experience has been extremely distressing for an
unreasonably long time. The insurer is required to pay her $5,400 in compensation.
2.3 Why is the outcome fair?
The September 2022 quote cannot be relied upon as it includes items that are not claim
related. It is therefore fair to formulate a cash settlement offer based on the May 2023 quote,
but with a builder’s margin added and higher than usual uplift. It is also fair that the insurer
compensates the complainant for the significant stress and inconvenience it has caused.
Determination | Case number: 1006438 Page 6 of 6
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. I have reviewed and considered
all of the information the parties have provided.
While the parties have raised several issues in their submissions, I have restricted this
determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no
relevant documents, we will decide what most likely occurred based on the available
information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim
cannot be established.